chunk_id
stringlengths
3
9
chunk
stringlengths
1
100
9828_274
upon the number of Earth orbits required to attain the lunar window for translunar trajectory.
9828_275
History Development
9828_276
Inspiration for the J-2 dates back to various NASA studies conducted in the late 1950s, of
9828_277
LH2-fuelled engines producing thrust of up to following the success of the RL-10 used on the
9828_278
Atlas-Centaur's Centaur upper stage. As ever-heavier launch vehicles entered consideration, NASA
9828_279
began to look at engines producing thrusts of up to , with development being officially authorized
9828_280
following the 1959 report of the Saturn Vehicle Evaluation Committee. A source evaluation board was
9828_281
formed to nominate a contractor from five bidding companies, and approval was given on 1 June 1960
9828_282
for Rocketdyne to begin development of a "high-energy rocket engine, fuelled by LOX and hydrogen,
9828_283
to be known as the J-2". The final contract, awarded in September 1960, was the first to explicitly
9828_284
require the design "insure maximum safety for crewed flight."
9828_285
Rocketdyne launched the development of the J-2 with an analytical computer model that simulated
9828_286
engine operations and aided in establishing design configurations. The model was supported by a
9828_287
full-sized mockup which was used throughout development to judge the positioning of the engine's
9828_288
components. The first experimental component, the engine's injector, was produced within two months
9828_289
of the contract being awarded, and testing of the engine's components began at Rocketdyne's Santa
9828_290
Susana Field Laboratory in November 1960. Other test facilities, including a vacuum chamber and
9828_291
full-size engine test stand, were used during the development, with the engine's turbopumps
9828_292
entering testing in November 1961, the ignition system in early 1962, and the first prototype
9828_293
engine running a complete 250-second test run in October 1962. In addition to flight hardware, five
9828_294
engine simulators were also used during the development process, assisting in the design of the
9828_295
engine's electrical and mechanical systems. Contracts were signed between NASA and Rocketdyne in
9828_296
the summer of 1962, requiring 55 J-2 engines to be produced to support the final designs for the
9828_297
Saturn rockets, which required five engines for each S-II second stage of the Saturn V and one
9828_298
engine for each S-IVB Saturn IB and Saturn V third stage.
9828_299
The J-2 entered production in May 1963, with concurrent testing programs continuing to run at
9828_300
Rocketdyne and at MSFC during the manufacturing run. The first production engine, delivered in
9828_301
April 1964, went for static tests on the S-IVB test stage at the Douglas test facility near
9828_302
Sacramento, California and underwent its first full-duration (410 seconds) static test in December
9828_303
1964. Testing continued until January 1966, with one engine in particular igniting successfully in
9828_304
30 successive firings, including five tests at full duration of 470 seconds each. The total firing
9828_305
time of 3774 seconds represented a level of accumulated operational time almost eight times greater
9828_306
than the flight requirements. As successful single-engine tests moved toward their completion,
9828_307
integration tests of the propulsion system with the S-IVB accelerated with the availability of more
9828_308
production engines. The first operational flight, AS-201, was scheduled in early 1966 for the
9828_309
Saturn IB using the S-IB first stage and the S-IVB as the second stage.
9828_310
The first all-up test of a complete S-IVB, including its single J-2, in July 1965 was inconclusive
9828_311
when a component malfunction in one of the pneumatic consoles prematurely ended the test after a
9828_312
successful propellant loading and automatic countdown. Confidence in the design was regained in
9828_313
August, however, when the same stage, S-IVB-201, performed flawlessly on a full-duration firing of
9828_314
452 seconds, which was the first engine test sequence to be controlled entirely by computers. The
9828_315
J-2 was cleared for flight and, on 26 February 1966, AS-201 went through a flawless launch.
9828_316
In July 1966, NASA confirmed J-2 production contracts through 1968, by which time Rocketdyne agreed
9828_317
to finish deliveries of 155 J-2 engines, with each engine undergoing a flight qualification firing
9828_318
at the Santa Susana Field Laboratory before delivery to NASA. Reliability and development testing
9828_319
continued on the engine, with two uprated versions being used by NASA in the later flights of the
9828_320
Apollo program.
9828_321
Upgrades
9828_322
J-2S
9828_323
An experimental program to improve the performance of the J-2 started in 1964 as the J-2X (not to
9828_324
be confused with a later variant by the same name). The main change to the original J-2 design was
9828_325
a change from the gas generator cycle to a tap-off cycle that supplied hot gas from a tap on the
9828_326
combustion chamber instead of a separate burner. In addition to removing parts from the engine, it
9828_327
also reduced the difficulty of starting up the engine and properly timing various combustors.
9828_328
Additional changes included a throttling system for wider mission flexibility, which also required
9828_329
a variable mixture system to properly mix the fuel and oxygen for a variety of different operating
9828_330
pressures. It also included a new "Idle Mode" that produced little thrust for on-orbit maneuvering
9828_331
or to settle the fuel tanks on-orbit prior to a burn.
9828_332
During the experimental program, Rocketdyne also produced a small run of six pre-production models
9828_333
for testing, the J-2S. These were test fired many times between 1965 and 1972, for a total of
9828_334
30,858 seconds burn time. In 1972 it became clear no follow-on orders for Saturn boosters were
9828_335
coming, and the program shut down. NASA did consider using the J-2S on a number of different
9828_336
missions, including powering the Space Shuttle in a number of early designs as well as on the Comet
9828_337
HLLV.
9828_338
J-2T
9828_339
While work on the J-2S continued, NASA also funded a design effort to use the J-2S turbomachinery
9828_340
and plumbing to a toroidal combustion chamber with a new aerospike nozzle. This would improve
9828_341
performance even further. Two versions were built, the J-2T-200k that provided thrust, allowing it
9828_342
to be "dropped in" to the existing S-II and S-IVB stages, and the J-2T-250k of .
9828_343
Like the J-2S, work on the J-2T had progressed to a lengthy series of ground-based test runs, but
9828_344
further development ended in the post-Apollo draw-down.
9828_345
J-2X
9828_346
What became a different engine with a similar name, called the J-2X, was chosen in 2007 for the
9828_347
Project Constellation crewed lunar landing program. A single J-2X engine, generating of thrust,
9828_348
was to be used to power the Earth Departure Stage (EDS).
9828_349
NASA began construction of a new test stand for altitude testing of J-2X engines at Stennis Space
9828_350
Center (SSC) on 23 August 2007. Between December 2007 and May 2008, nine tests of heritage J-2
9828_351
engine components were conducted at SSC in preparation for the design of the J-2X engine.
9828_352
The new J-2X is designed to be more efficient and simpler to build than its Apollo J-2 predecessor,
9828_353
and cost less than the Space Shuttle Main Engine (SSME). Design differences include the removal of
9828_354
beryllium, modern electronics, a centrifugal turbo pump versus the axial turbo pump of the J-2, a
9828_355
different chamber and nozzle expansion ratios, a channel-walled combustion chamber versus the
9828_356
tube-welded chamber of the J-2, a redesign of all the electronics, supersonic injection and the use
9828_357
of 21st-century joining techniques.
9828_358
On July 16, 2007 NASA officially announced the award to Pratt & Whitney Rocketdyne, Inc. of a $1.2
9828_359
billion contract "for design, development, testing and evaluation of the J-2X engine" intended to
9828_360
power the upper stages of the Ares I and Ares V launch vehicles. On Sept. 8, 2008 Pratt & Whitney
9828_361
Rocketdyne announced successful testing of the initial J-2X gas generator design. The completion of
9828_362
a second round of successful gas generator tests was announced on September 21, 2010.
9828_363
Project Constellation was cancelled by President Barack Obama on October 11, 2010, but development
9828_364
of the J-2X has continued for its potential as the second stage engine for the new, heavy-lift
9828_365
Space Launch System. The first hot-fire test of the J-2X was scheduled for late June, 2011.
9828_366
On November 9, 2011 NASA conducted a successful firing of the J-2X engine of 499.97 seconds in
9828_367
duration.
9828_368
On February 27, 2013 NASA continued testing of the J-2X engine of 550 seconds in duration at NASA's
9828_369
Stennis Space Center.
9828_370
Specifications See also Comparison of orbital rocket engines References
9828_371
Rocket engines using hydrogen propellant Rocketdyne engines North American Aviation
9828_372
Apollo program hardware Rocket engines using the gas-generator cycle
9828_373
Rocket engines of the United States