University
stringclasses
19 values
Text
stringlengths
458
20.7k
Virginia Tech
The mixture velocity at intake 4 was set to 5.5 ft/s and the SF mass fraction was 6 computed as 0.0001078 according to Equation (4-9). In the experiment, only SF was 6 released from intake 4 but both air and SF were released in this model. If only SF was 6 6 released in the model, it would take a long time for SF to be carried by the airflow 6 coming from the upstream. However, if air was released together with SF from intake 4, 6 SF would get a higher velocity at the beginning due to the high mixture velocity. At the 6 same time, SF mass fraction was changed from 1 to 0.0001078 to match the 6 experimental release rate. Then SF would be able to join the main flow stream quickly. 6 The reason why the mixture velocity was set to 5.5 ft/s was that the amount of SF 6 released from intake 4 was very small (200 SCCM, which is 4.53× 0−5 lb/s in the experiment) and therefore, the velocity was also small compared to the average velocity across a cross-sectional area in the upstream before the release point measured as 5.6 ft/s in the model. The mixture velocity was smaller than 5.6 ft/s so the downstream flow would not be affected by the injection of the mixture. Simple calculation was claimed below to prove the injection of mixture did not change the flow behavior in the downstream very much. The volumetric flow rate measured in the upstream before the release point was 883.874 ft3/s and the volumetric flow rate at the intake 4 was 5.5 ft3/s. So the ratio between these two flow rates was computed as 0.00618, which meant the mixture released from the cube was negligible. 𝑚̇ 𝑆𝐹6 𝑝 𝜑 = (4-9) 𝑚𝑎𝑠𝑠 ∗ ∗𝐴 𝑎 𝑟 𝑛𝑡𝑎 4 𝑛𝑡𝑎 4 where 𝜑 represents the SF mass fraction in the mixture, 𝑚̇ is the mass flow rate 𝑚𝑎𝑠𝑠 6 𝑆𝐹6 (lb/s) of SF measured in the experiment, is the air density, is the velocity 6 𝑎 𝑟 𝑛𝑡𝑎 4 for the mixture at the release plane, 𝐴 is the area of the release plane. Since the 𝑛𝑡𝑎 4 cube volume is 1 ft3(1ft×1ft×1ft), 𝐴 is 1 ft2. 𝑛𝑡𝑎 4 4.5.3 Assumptions Several assumptions are made to save the time on establishing the model without affecting the results significantly. There is no leakage between air passages. The gravity of the air in the underground mine is neglected. Airflow in the underground is incompressible and fully turbulent. 69
Virginia Tech
4.5.4 Governing Equations All the equations shown below were obtained directly from the theory guide of Ansys Fluent (Ansys 2009a). Species transport equations: ∂ (ρ𝑌)+∇∙(ρ𝑣 𝑌) = −∇∙𝐽⃗⃗ +𝑅 + (4-10) ∂t 𝑖 where ρ is the mixture density, 𝑌 is the local mass fraction of each species (in this model, there are two species, which are SF and air), 𝑣 is the mixture velocity, 𝐽⃗⃗ is the diffusion 6 𝑖 flux of species i, 𝑅 is the net rate of production of species i by chemical reaction, is the rate of creation by addition from the dispersed phase plus any user-defined sources. In this case, both 𝑅 and equal to zero since there is no chemical reaction and user- defined sources in the model mine. In turbulent flows, mass diffusion is computed by using the following equation in ANSYS Fluent: ∇𝑇 𝐽⃗⃗ = −(ρ𝐷 + 𝑡 )∇𝑌 −𝐷 (4-11) 𝑖 ,𝑚 𝑇, 𝑇 𝑡 where ρ is the mixture density, is the turbulent Schmidt number ( 𝑡 where is the 𝑡 𝑡 𝑡 turbulent viscosity and 𝐷 is the turbulent diffusivity). The default is 0.7. 𝐷 is the 𝑡 𝑡 ,𝑚 mass diffusion coefficient for species i in the mixture, 𝐷 is the thermal (Soret) diffusion 𝑇, coefficient. Momentum equations: 𝜕 ( 𝑣 )+∇∙( 𝑣 𝑣 ) = −∇𝑝+∇∙(𝜏̿)+ 𝑔 +𝐹 (4-12) 𝜕𝑡 where p is the static pressure, 𝑣 is the mixture velocity, 𝜏̿ is the stress tensor, and 𝑔 and 𝐹 are the gravitational body force and external body forces, respectively. 𝐹 also contains other model-dependent source terms such as porous-media and user-defined sources. The tensor stress 𝜏̿ is given by 70
Virginia Tech
4.5.5 Model Setup As aforementioned, species transport model was applied to simulate both the airflow and the SF flow in the underground. Obviously, the mixture species were air and SF . The 6 6 standard k-epsilon model was also used to take care of the turbulence. For near-wall treatment, the standard wall functions were applied. 4.5.6 Mesh Independence Study Mesh independence study was conducted to make sure the results from the species transport model were mesh independent. It also meant that the modeling results were constant with various mesh sizes. Three meshes, which were fine mesh, medium mesh, and coarse mesh, were created for this study. A comparison of nodes number for the three meshes were shown in Table 9. Plan view of the three meshes were provided in Figure 13. 4.5.6.1 Comparisons at the Monitor Points Based on the three meshes, three species transport models were created. Transient solver was chosen to complete the simulation in six hours for all the three models. For comparison purposes, SF mass concentration were monitored at SP1, SP2, SP3, and 6 SP9, respectively, in the three models. Monitor points were created in the center of the planes where the sample points are located. An example of the monitor point location was shown in Figure 50. Results for the sample points were shown from Figure 51 to Figure 54. 72
Virginia Tech
with time for the medium mesh and coarse mesh models. However, the final SF mass 6 concentration after the six-hour simulation is nearly the same for the three models. The range of the final SF mass concentration is from 650 PPB to 700 PPB, which is not a big 6 difference in terms of the small unit (PPB). Figure 52. SF mass concentration over time at SP2 for the three meshes. 6 In Figure 52, the three curves represent the results from the three meshes, respectively. SF mass concentration at SP2 almost reach a stable level (about 320 PPB) after six hours 6 in the medium and coarse mesh models. The SF concentration still has an increasing 6 trend after six-hour simulation in the fine mesh model. However, the final SF mass 6 concentration in the fine mesh model was also 320 PPB in the ten-hour simulation as shown in Figure 93. The reason why the three curves have not reached a stable level is that SP2 is further away from the release point compared to SP1 and it takes longer for SF to reach SP2. 6 74
Virginia Tech
Additionally, the following simulations, which were steady-state simulation and transient simulation, were performed in the fine mesh model. 4.5.7 Steady-State Simulation The purpose for the steady-state simulation is to have an overall idea about the final SF 6 flow and airflow status in the steady state flow domain. There were two steps to finish the steady-state simulation. The first step was to let the species transport model run on a steady solver to let the airflow reach its steady state. Boundary condition for intake 4 was assigned as wall and no mixture was released in the steady state simulation. The second step was to continue running the model on the steady solver and begin to release the mixture from the intake 4. Boundary condition for intake 4 was changed to velocity inlet in the second step. Convergence criteria was set to 0−3 in both the steps. It took 6900 iterations for the airflow in the first step of the steady-state simulation to get converged. Results at the monitor points and planes were recorded right after the first step. After 16000 iterations of calculation in the model, SF mass concentration at the monitor points 6 and planes reached their stable levels except return 1. Then the CFD model was kept running to 36560 iterations when the SF mass concentration reached a stable level. 6 Contours shown below were created at 16000 iterations. Contours and figures created at 36560 iterations would be specifically mentioned if they were shown below. A monitor point was created for each sample point in the center of the plane where the sample point was located. An example for the location of a monitor point was shown in Figure 50. Results from the steady state simulation were shown in Table 19. 79
Virginia Tech
4.5.7.1 Results Comparisons Table 19. Results from the steady state simulation in the species transport model. CFD Air CFD Air SF 6 Sample SF Results 6 quantity SF (kcfm) Results Error Error 6 points (cfm) Air (kcfm) SF (kcfm) (%) (%) 6 (kcfm) 1 81.00 0.0129 1.29× 0−5 87.04 1.15× 0−5 7.45 10.49 2 19.60 0.0033 3.30× 0−6 19.68 1.31× 0−6 0.40 60.33 3 17.00 0.0028 2.80× 0−6 11.50 1.28× 0−6 32.35 54.42 7 53.74 53.04 1.31 9 63.00 0.0089 8.90× 0−6 64.05 5.31× 0−6 1.67 40.28 RP1 53.60 0.0088 8.80× 0−6 53.04 7.05× 0−6 1.05 19.93 In Table 19, the first four columns are the data obtained from the experiment. Column five and six represent the CFD results of airflow quantity and SF flow quantity, 6 respectively. The SF flow quantity was computed based on the SF mass concentration 6 6 in the center of the cross-sectional area instead of the area-weighted concentration across the area. The last two columns show the CFD errors of airflow quantity and SF flow 6 quantity, respectively. The errors are calculated based on Equation (3-3). Figure 58 and Figure 63 were made according to Table 19 to show the comparisons more straightforwardly. In Figure 16, there was no SF data at SP7 for both experiment and CFD. The reason was 6 that SP7 was located far away from RP1 in the upstream and there was no SF detected in 6 the field study. Obviously, there was also no SF found at SP7 in the CFD model. 6 Both air and SF data were monitored at RP1 to make sure what was released in the CFD 6 model matched that in the experiment. Results at RP1 in the model actually came from the results at monitor plane A. The reason why the results at intake 4 were not used as the results at RP1 was that the airflow quantity at intake 4 could not represent the airflow quantity across the entry in the model mine. In addition, the airflow quantity at RP1, which was shown in the second column in Table 19, was measured across the entry in the experiment. 80
Virginia Tech
Airflow Quantity (kcfm) Comparison 100.00 ) 80.00 m f c k ( 60.00 y t i t n Experiment Results a 40.00 u Q CFD Results r i 20.00 A 0.00 SP1 SP2 SP3 SP7 SP9 RP1 Points Figure 58. Airflow quantity (kcfm) comparison. As aforementioned, in the species transport model, a mixture of air and SF were released 6 from intake 4. However, since the SF mass fraction is only 0.0001078 in the mixture, the 6 following mixture velocity magnitude contours were treated as airflow velocity magnitude contours to make the comparisons between the experiment and CFD model more clearly. It is clear that the airflow quantity at SP3 has the largest error, which is 32.35%, among all the sample points. There are several reasons for this error. Firstly, SP3 is located right next to the gob. It is very hard for the personnel to get access to and get the experimental data. Secondly, the CFD model does not simulate everything in the underground. For instance, there are people and machine moving around SP3 but CFD model does not simulate it. Thirdly, the experiment itself is not accurate at SP3. There are falling rocks at SP3 and it creates problems for the personnel to collect data. Finally, airflow at SP3 is complex and the velocity contours at SP3 can be found in Figure 59 and Figure 60. 81
Virginia Tech
Figure 60. Contour (XY plane) of velocity magnitude (ft/s) at SP3 in the CFD model. From Figure 58, airflow quantity at SP1 simulated in the CFD is a little bit higher than that measured in the experiment. The airflow magnitude contour in the cross-sectional area where SP1 was located is shown Figure 61 and Figure 62. It is clear that velocity is also not evenly distributed in the cross-sectional area as shown in Figure 61. The range of velocity magnitude is from 0 to about 10 ft/s. Since the area of the plane where SP1 is located was measured as 187.7 𝑡2 in the field study, the velocity magnitude at SP1 in the experiment, which is computed by dividing the volumetric flow rate (81 kcfm) by area, then becomes 7.19 ft/s. The experimental result, which is 7.19 ft/s, is actually within the range obtained from the CFD model. Another velocity contour (in XY plane) is shown in Figure 62 to have a better idea about the complexity of the airflow behavior at around the SP1. 83
Virginia Tech
In Figure 63, the SF flow quantity at the sample points obtained from the experiment and 6 the CFD model are compared with each other. It is obvious that all the results from the experiment are higher than that from the CFD model. It looks like there are big differences between the results. However, the largest SF flow quantity is still smaller 6 than 1.4× 0−6 kcfm in Figure 63. In other words, the differences between the experimental and CFD results are not that big in terms of units of the SF flow quantity. 6 There are several reasons for the higher SF mass concentration results in the experiment. 6 The k-epsilon turbulence model is not perfect and does not represent turbulent flow in the model very well due to the complex mine geometry. Additionally, there were people and mining equipment (a huge chuck) moving when the experiment was conducted. However, these factors were not simulated in the model. Besides, the injection of tracer gas was not modeled exactly as what it was in the underground. In the species transport model, SF was released from a cube but in reality, the tracer gas was released from a 6 container held by an individual. Moreover, the airflow and SF flow might not be well- 6 mixed when the sample points were taken in the experiment. Oppositely, the conditions set in the 3D CFD model are perfect and flows of air and SF are mixed very well in the 6 model. The reason why the SF mass concentration measured in the experiment is higher than 6 that in the CFD mode is that the results at RP1 actually come from the results at monitor plane A as aforementioned. Due to the diffusion of SF across the monitor plane A, the 6 SF mass concentration measured in the CFD model is lower than what is released from 6 intake 4. However, the SF6 mass concentration at intake 4 is measured The contour of SF mass concentration distribution near the RP1 can be found later in Figure 72. 6 Contours of the SF mass concentration at SP1 and SP3 are shown below to illustrate the 6 SF mass concentration distribution in the cross-sectional area, where the sample points 6 are located. Contours of the SF mass concentration at SP2 and SP9 can be found in the 6 Appendix. 86
Virginia Tech
From Figure 68, there is no airflow in the gob area in the model mine. However, in Figure 69, SF diffuses to the gob and the SF mass concentration is lower in the center of 6 6 the gob and higher close to the walls. Additionally, Figure 69 shows that the diffusion of SF is affected by the velocity magnitude, which agrees with Equation (4-10). According 6 to Equation (4-10), as long as the mass fraction of the species (SF in this case) is 6 constant, the sum of convection and diffusion of SF should also be constant. When the 6 velocity magnitude is high, the convection term in the equation dominant the SF flow 6 behavior. If the velocity magnitude is low, the effects from convection will be reduced and diffusion will dominant the behavior of SF . For instance, SF diffuses less in the 6 6 high velocity magnitude areas like the working face. The contour of velocity magnitude and SF mass concentration near the working face were shown in Figure 70 and Figure 6 71, respectively. Figure 70. Visualization (in XY plane) of velocity magnitude (ft/s) near the working face in the CFD model. According to Figure 70, it is obvious that most of the airflow goes to the working face and the rest of the airflow goes to the gob and the entry next to the gob. However, SF 6 diffuses more to the entry next to the gob than to the working face. 92
Virginia Tech
Figure 72. Visualization (in XY plane) of SF concentration distribution near the RP1 in 6 the CFD model. From Figure 72 and Figure 73, SF released from the intake 4 is concentrated in the 6 centerline of the entry for a while and then slowly diffuses across the cross-sectional area. The contour is more meaningful than that shown in Figure 24 and Figure 25, which are obtained from the CFD models with and without turbulent viscosity. The reason is that SF should not fully diffuse to the cross-sectional area right after the RP1 due to the 6 effects from airflow convection. In addition, SF does not back diffusion in the upstream 6 before RP1 in Figure 72. However, there is SF back diffusion in Figure 24 and Figure 6 25, which does not make sense according to the governing equations. The distance from RP1 to the place where SF is evenly distributed is 37 ft (measured in 6 the CFD model). This 37 ft can be used as a reference for determining the locations of sample points in future field study. If the sample points are located at the places where SF mass concentration are evenly distributed, the error from experiment can be 6 94
Virginia Tech
Figure 76. SF mass concentration over iterations at the monitor planes. 6 Locations of the monitor planes are shown in Figure 48. Although they are called monitor planes in Figure 77, a monitor point was created in the center of each monitor plane and was used to record the changing of SF mass concentration with iterations. According to 6 Figure 76, it is obvious that the SF mass concentration at the monitor plane A is the 6 largest among the three monitor planes. The final SF mass concentration is about 19000 6 PPB at the monitor plane A, while it is lower than 1000 PPB at monitor plane B and C. It seems 19000 PPB (1.9× 0−5) at monitor plane A is unreasonable. However, it is still smaller than the SF mass fraction at intake 4, which is 1.078× 0−4. The reason why the 6 SF mass concentration at monitor plane A is different from that at intake 4 is due to the 6 SF diffusion across the monitor plane A. The differences of SF mass concentration at 6 6 the monitor planes are due to their locations in the model mine. For example, the SF 6 mass concentration at monitor plane A is higher than that at monitor plane B because the SF flow is separated before arriving at monitor plane B but it is not separated at monitor 6 plane A. To better visualize the SF mass concentration at plane B and C, Figure 77 is 6 created below. It is obvious that the final SF mass concentration at monitor plane B and 6 C are about 500 PPB and 400 PPB, respectively. 98
Virginia Tech
Figure 78. SF mass concentration over iterations at the sample points. 6 According to Figure 78, the SF mass concentration at the four sample points reach a 6 stable level after about 14000 iterations in the model. The final SF mass concentration at 6 SP1 is the largest among the four sample points while it is the smallest at SP2. The reason is that SP1 is located right next to RP1 and SP2 is located in the entry close to neutral 2 as shown in Figure 48. The SF flow, which is originally released form RP1, is separated 6 several times before reaching SP2. However, it reaches SP1 without any separations or obstacles. 4.5.8 Transient Simulation Transient simulation was also processed in two steps. At first, the species transport model was ran on a steady solver to let the airflow reach its steady state. Boundary condition for intake 4 was changed to wall and no mixture was released in the steady state simulation. Then the model continued to be ran on a transient solver and the mixture was released from intake 4. Boundary condition for intake 4 was changed to velocity inlet. Convergence criteria for both the steady state simulation and transient simulation were 100
Virginia Tech
set to 0−3. The transient simulation, which was the second step, has been run for ten hours. Compared to the six-hour experiment, it was longer. The reason was that the SF 6 concentration has not reached a steady level in six hours for some returns and sample points far from the release point in the CFD model. The ten-hour simulation made it possible to visualize the final SF mass concentration at different locations. 6 4.5.8.1 Results from the Species Transport Model The results from the transient simulation were made up of two parts. One was from the six-hour simulation and the other was from the ten-hour simulation. Both the results were compared to the results from the six-hour experiment. SF mass concentration was 6 monitored at various locations in the model mine. 4.5.8.1.1 Six-hour Simulation The six-hour transient simulation was performed to make a comparison with the six-hour experiment. SF mass concentration was monitored at two returns, one neutral, and three 6 monitor planes. A monitor point was created for the returns and neutral, respectively. The monitor point was located at the center of the returns, neutral, and monitor planes because the sample points were located in the center of entries in the experiment. An example for the location of the monitor point in return 3 was shown in Figure 50. 101
Virginia Tech
Figure 80. SF mass concentration over time at all the monitor planes. 6 The three monitor planes were created in the species transport model. Locations of the monitor planes were shown in Figure 48. Monitor plane A was located right after the release point 1. Monitor plane B was a plane created in the entry where the airflow was about to enter the working face. The monitor plane C was a plane created in the working face. Contours of velocity magnitude and SF mass concentration were created at the 6 three monitor planes to have an idea about the distribution of the velocity magnitude and SF mass concentration. Monitor points were also created at the three planes, 6 respectively. All the monitor points were located in the center of the monitor planes like the location of the monitor point in return 3 in Figure 50. SF mass concentration over 6 time was monitored at the monitor points in the three monitor planes and was presented in Figure 80. Figure 80 shows the SF mass concentration over time at the monitor points located in the 6 three monitor planes. It is clear that the SF mass concentration reach a stable level in a 6 short period of time at monitor plane A because it is located right after the release point 1. The final SF concentration at monitor plane A is about 19000 PPB (19 PPM), which is 6 much higher than that in the monitor plane B and C. There are two main reasons for the 103
Virginia Tech
higher SF mass concentration in monitor plane A. One is SF flow has not been 6 6 separated because of turns or obstacles in the entry. The other one is no new airflow joins the original mixture at monitor plane A. So the amount of SF originally released from 6 the intake 4 is not reduced A while the airflow rate keeps the same at monitor plane. SF 6 mass concentrations are much lower at monitor plane B and C due to the aforementioned reasons. Figure 81 was created because the SF mass concentration values at monitor 6 plane B and C are hard to be read in Figure 80. Figure 81. SF mass concentration over time at monitor plane B and C 6 From Figure 81, the SF mass concentration reaches a stable level after the six-hour 6 simulation for monitor plane B and C. The final SF mass concentration are 500 PPB and 6 400 PPB for the monitor plane B and C, respectively. The difference in the SF mass 6 concentration between the two monitor planes is caused by the distribution of the amount of SF at monitor plane B before arriving monitor plane C. In addition, the SF mass 6 6 concentration at monitor plane B shows up about half an hour earlier than that at monitor plane C. It is because the monitor plane B is located closer to the release point 1 compared to the monitor plane C. 104
Virginia Tech
directly from the VnetPC model used in the preliminary study (Zhang et al. 2014) for this study. Trace element (PADT, 2014) (in this case, SF ) was created in the Flownex model 6 to simulate the distribution of the SF concentration in the model mine. 6 Figure 101. Plan view of the Flownex model. 4.6.2 Results Table 20. Results from the Flownex model with tracer gas. Air Flownex Flownex Air SF 6 Sample SF SF 6 6 quantity Results Air Results SF Error Error 6 points (cfm) (kcfm) (kcfm) (kcfm) (kcfm) (%) (%) 1 81.00 0.0129 1.29× 0−5 86.36 8.73× 0−6 6.62 32.36 2 19.60 0.0033 3.30× 0−6 19.59 1.98× 0−6 0.05 40.02 3 17.00 0.0028 2.80× 0−6 0.51 5.19× 0−8 96.98 98.15 7 53.74 53.70 0.07 9 63.00 0.0089 8.90× 0−6 63.07 6.37× 0−6 0.10 28.41 RP1 53.60 0.0088 8.80× 0−6 52.38 8.72× 0−6 2.28 0.85 From Table 20, sample point 3 has the largest error for both airflow quantity and SF 6 concentration. Airflow quantity at sample point 3 is only 17 kcfm (1000 cubic feet per minute). It is reasonable because network modeling is not significantly sensitive to the areas with low airflow velocity. In addition, the gob was represented by four pathways with high resistance values in the Flownex model. There was no accurate gob model in 123
Virginia Tech
the Flownex model, which made the model less accurate compared with the 3D CFD model. Since sample point 3 is located next to the gob, both the airflow quantity and the SF concentration are certainly affected due to the lack of an accurate gob model in the 6 Flownex model. 4.7 Hybrid Model After taking the computing time into account, a hybrid model of Fluent and Flownex become the idea to simulate both the airflow quantity and SF concentration for the 6 model mine. Working face area in the model mine was determined to be the CFD component in this case. However, according to the results from the Flownex model, sample point 3 should be taken into account in the hybrid account since the airflow near sample point 3 was complex and had the largest error compared to the experimental results. The reason for not having the area close to sample point 3 as the CFD component in this specific geometry was that the gob would be added to the CFD component together with the area around sample point 3. It would increase both the complexity and difficulty of the hybrid model, which was not the purpose of the study. The rest of the model mine was simulated in Flownex. An overview of the link was shown in Figure 102. The working face CFD component and an enlarged view for part of the mesh in the CFD model were presented in Figure 103. Figure 102. Plan view of the hybrid model. 124
Virginia Tech
In Figure 102, there were four data transfer links established between Flownex and Ansys Fluent. An enlarged view of the data transfer links was shown in Figure 104. The data transfer link 3 was used to check the error of mass flow rate between Fluent and Flownex. The big yellow Ansys icon in this link acted as a Fluent controller. It passed the updated boundary conditions and mass flow rate data between Fluent and Flownex back and force. Behind the Ansys icon were large amounts of code that making this hybrid model works. Due to the requirements of Flownex, inlet and outlet boundary conditions in the CFD model should be set as pressure-inlet and pressure-outlet separately. The inputs for inlet and outlet in the CFD component were not important because Flownex would transfer the two inputs to Fluent through data transfer link 1 and 4 (Figure 104) no matter what the inputs were at the beginning. To get more stabilized results from the CFD model, the standard k-omega model was used in this hybrid model after several tries with other turbulent models. Average total pressure values were used for both inlet and outlet boundary conditions. The reason was that this hybrid model was made by a 1D Flownex model and a 3D CFD model. Since the pressure distribution in the 3D model was not constant, average values were taken to be filled in the 1D model. Fluent was run 50 iterations per coupling iteration. The coupling simulation did not stop until the error of mass flow rate values reached an acceptable convergence. Here, mass flow rate values came from both Fluent and Flownex. To stabilize the coupling results, Fluent was set to not stop running even if it reaches its convergence criteria. Fluent ran much longer than it need to until the coupling converged. Flownex was converging very well in this hybrid model. 126
Virginia Tech
Figure 106. Convergence history for some parameters in the CFD model. Table 21. Hybrid Model Results. Air Hybrid Hybrid Air SF 6 Sample SF SF 6 6 quantity Results Results SF Error Error 6 points (cfm) (kcfm) (kcfm) Air (kcfm) (kcfm) (%) (%) 1 81.00 0.0129 1.29× 0−5 86.59 8.76× 0−6 6.90 32.08 2 19.60 0.0033 3.30× 0−6 19.59 1.98× 0−6 0.05 39.92 3 17.00 0.0028 2.80× 0−6 0.41 4.12× 0−8 97.60 98.53 7 53.74 53.70 0.07 9 63.00 0.0089 8.90× 0−6 63.01 6.37× 0−6 0.02 28.47 RP1 53.60 0.0088 8.80× 0−6 52.60 8.76× 0−6 1.87 0.43 From Table 21, airflow quantity at SP3 in the hybrid model is still inconsistent with the experimental results. The reason is that gob area is not simulated in this hybrid model. SP3 is right next to the gob and airflow at SP3 is affected by the gob. The ideal solution for this case is to establish a hybrid model with gob taken into account. It means that the CFD component in the hybrid model will contain the gob and several entries connected with the gob. Then Flownex will be able to update the boundary conditions for the CFD component. However, it will be too complex if including the gob in the hybrid model in this study. The purpose of establishing this hybrid model in the study is to show that CFD can be linked with other software to get an accurate solution. 128
Virginia Tech
modeling results. However, the y axis in the figure represents the SF flow quantity and 6 the largest SF flow quantity value is still less than 0.000014 kcfm. The comparison was 6 made in Figure 108 to show the fact that SF flow quantity from the experiment is higher 6 than that from the three models. One reason is that SF concentration was affected by the 6 airflow recirculation at the sample points. The other reason is that experimental data is not recorded accurately due to human error and moving equipment. Overall, the 3D CFD model are the most accurate model among the three models. However, the long computing time make the CFD model time-consuming. In terms of the results, the Flownex and hybrid model are almost the same for this mine geometry. On one hand, the CFD component in the hybrid model does not affect the results very much because the gob area was not simulated accurately. On the other hand, the hybrid model works correctly in this paper, and it verifies the coupling capability of Flownex. Moreover, the CFD component in the hybrid model will make a big difference for other cases, such as a mine gob area, and areas with low airflow velocity. The reason is that network modeling is not sensitive to the areas with low airflow velocity. If the CFD component can be applied in this areas, network modeling will be as good as the CFD model. Then the hybrid model will save both the time for building up and solving the CFD model. 131
Virginia Tech
5 Conclusions and Future Work The purpose for this research was to figure out the best approach to simulate the flow behaviors in an underground mine. Both the experiment and the models with different software packages have been conducted in this research. The field study was done in the underground mine for a six-hour period with the help of releasing-sampling SF in different locations. The models created for the model mine 6 basically consisted of network modeling and CFD modeling. Network modeling was built at first. For the network modeling, a VetPC model and a Flownex model were made. In terms of the CFD modeling, several 2D CFD models and 3D CFD models with various settings were made. Finally, a hybrid model was made. From Chapter 3, two models were created based on the mine geometry. One was the VnetPC model provided by the mine. The other one was a 2D CFD model without the mine gob. In examining the results from these two models, the 2D CFD model appeared to be the better choice to simulate the underground mine. However, it did not take the gob into account. Besides, distribution of the SF concentration was not simulated in both the 6 VnetPC model and the 2D CFD model. Airflow quantity results from the two models were compared with the results from experiment and then the results from the two models were compared with each other. Several conclusions are made for Chapter 3. The network modeling is not sensitive to the low airflow quantity areas. Besides, an underground mine can be simulated with both a CFD model and a network model to achieve a high accuracy on the results. The network model should be created at first and the CFD model will be applied to the areas where there are large errors appearing in the network model. To improve these models, 3D CFD models with the gob included and a Flownex model were built in Chapter 4. Since Flownex has the capability to model a trace element, Flownex was used to represent network modeling instead of VnetPC. Several 2D CFD models were created in Chapter 4 to verify the fact that the gob area had no need to be divided into five zones for this specific model mine. All the 3D CFD models were then 132
Virginia Tech
built up with the one-zone gob. At the same time, SF concentration was simulated in the 6 3D CFD models. A mesh independence study and a sensitivity study on the porosity and permeability values were generated for the 3D CFD model with and without turbulent viscosity to make sure that mesh size, porosity and permeability values did not affect the results from the 3D CFD model. Another mesh independence study was performed for the 3D CFD model with species transport model. As a result. the fine mesh and the porosity and permeability values from Lolon’s dissertation (Lolon 2008) were determined to be applied in both the steady-state simulation and transient simulation in the two 3D CFD models. In terms of the 3D CFD model using UDF approach, two cases (with and without turbulent diffusivity) were created for the steady-state simulation to see the effects of interpreting the turbulent diffusivity. Surprisingly, the turbulent diffusivity did not affect the 3D CFD results for this mine geometry. Then a transient simulation was established without turbulent diffusivity interpreted. Results from both the steady-state simulation and the transient simulation were carefully analyzed in Chapter 4. Because the SF mass concentration contours obtained from the 3D CFD model using UDF approach 6 cannot be explained, the 3D CFD model with species transport model was created to explore the correct results. Similar to the 3D CFD model using UDF approach, both steady-state and transient simulation were conducted in the species transport model. Results were analyzed in detail in Chapter 4. The hybrid model was the last model built up in Chapter 4 and the purpose was to make full use of the coupling capability of Flownex. It was much easier to establish the hybrid model than the 3D CFD model for the model mine because both the Flownex part and the CFD component part were not complex. Although the results from the hybrid model was almost the same to that from the Flownex model without the CFD component, it still proved the success of the hybrid model. Since working face in the 3D CFD model was taken out and used as the CFD component in the hybrid model, it was correct to have no difference between the Flownex model and the hybrid model. If the gob area was used as the CFD component in the hybrid model, results from the hybrid model should be the same as that from the 3D CFD model. However, it will increase the complexity for building up the hybrid model, which is not the purpose of this research. 133
Virginia Tech
To sum up, the goal of this research is to find an optimal method to simulate an underground mine with an easy-setup and high-accuracy model. Obviously, the ideal approach will be the 3D CFD model with species transport model. But it is impractical and time consuming to simulate an entire underground mine only with the 3D CFD model. Practically, the hybrid model is the best approach to achieve the goal. The hybrid model represents a combination of network modeling and CFD model. It takes advantages of both the two models. According to the findings in this research, there are several suggestions on using this hybrid model for an underground mine. The hybrid model is unique only when it is applied appropriately. For a large scale underground longwall mine where a 3D CFD model is impractical to use, the hybrid model will be a good fit. Areas with low airflow velocity should be simulated in the CFD component. Gob area is also required to be modeled in the CFD component. Computing time should be considered when using the hybrid model. The hybrid model is time-saving but it also depends on how you assign the CFD component. It is not a good idea to simulate the airways without any obstacles or areas where airflow is not complex in the CFD component. The reason is that Flownex can also simulate these areas with less time on establishing and solving the model. The CFD component should be used to simulate the areas with complicated airflow, which cannot be simulated in the Flownex model. It is always good to build up a model for the entire underground longwall mine with only Flownex. Then the low airflow velocity areas can be determined. There are also some limitations for the hybrid model. Like other modeling software, both Ansys Fluent and Flownex have numerical errors. Then the hybrid model also has some numerical errors. The hybrid model cannot simulate exactly what happens in the underground, such as equipment moves in the underground while samples are taken. Besides, turbulent models used in the CFD component in the hybrid model does not perfectly represent turbulent flow when the model mine geometry is considerably complex. 134
Virginia Tech
References Ansys. 2006. Fluent 6.3 User’s Guide. Ansys. 2009a. Ansys Fluent 12.0 Theory Guide. Ansys. 2009b. Ansys Fluent 12.0 UDF Manual. Edwards, J C, and C C Hwang. 2006. “CFD Modeling of Fire Spread Along Combustibles in A Mine Entry.” In SME Annual Meeting, St. Louis, Missouri, 1–5. Esterhuizen, G, and C Karacan. 2007. “A Methodology for Determining Gob Permeability Distributions and Its Application to Reservoir Modeling of Coal Mine Longwalls.” In SME Annual Meeting, Denver, CO, 1–6. Gerwin, H., W. Scherer, and E. Teuchert. 1989. “The TINTE Modular Code System for Computational Simulation of Transient Processes in the Primary Circuit of a Pebble- Bed High-Temperature Gas-Cooled Reactor.” Nuclear Science and Engineering 103: 302–12. Heerden, Johan Van, and Peter Sullivan. 1993. “The Application of CFD for Evaluation of Dust Suppression and Auxiliary.” In The 6th US Mine Ventilation Symposium, Salt Lake City, Utah. Huang, T H. 2008. “Integrated System CFD Modelling of the Flow Distribution.” In Proceedings of the 16th International Conference on Nuclear Engineering, Orlando, Florida, USA, 1–7. Janse Van Rensburg, J. J., and M. Kleingeld. 2010. “A CFD Method to Evaluate the Integrated Influence of Leakage and Bypass Flows on the PBMR Reactor Unit.” Nuclear Engineering and Design 240(11): 3841–50. http://dx.doi.org/10.1016/j.nucengdes.2010.08.011. Jong, E. 2013. “Development and Evaluation of a Permeation Plug Release Vessel ( PPRV ) for the Release of Perfluoromethylcyclohexane ( PMCH ) in Underground Mine Tracer Gas Studies.” Virginia Polytechnic and State University. Karacan, C Ö, T Ren, and R. Balusu. 2008. “Advances in Grid-Based Numerical Modeling Techniques for Improving Gas Management in Coal Mines.” In 12th U.S./North American Mine Ventilation Symposium, Pittsburgh, Pennsylvania, USA, 313–20. Kelsey, Adrian et al. 2003. “CFD Modelling of Methane Movement in Mines Ian S Lowndes David Whittles.” In Johannesburg, South Africa, 475–86. 136
Virginia Tech
Lazzara, C.P., and F.J. Perzak. 1987. “Effect of Ventilation on Conveyor Belt Fires.” In Symposium on Safety in Coal Mining, Pretoria, South Africa. Lolon, S.A. 2008. “Computational Fluid Dynamics Simulation Study on Hot Spot Location in a Longwall Mine Gob.” The University of Utah. Marais, D. 2007. “Validation of the Point Kinetic Neutronic Model of the PBMR.” Potchefstroom Campus of the North-West University Supervisor: Olivier, Jacobus C. 2005. “Network Modelling of Transient Heat Exchanger Performance.” Potchefstroom University for Christian Higher Education. PADT. 2013. Flownex–Fluent Link. PADT. 2014. Flownex General User Manual. Ren, T, and R Balusu. 2005. “CFD Modelling of Goaf Gas Migration to Improve the Control of Spontaneous Combustion in Longwalls.” In Brisbane, QLD, 26–28. Ren, T, R Balusu, and C Claassen. 2011. “Computational Fluid Dynamics Modelling of Gas Flow Dynamics in Large Longwall Goaf Areas.” In Wollongong, NSW, 24–30. Ren, T, R Balusu, and P Humphries. 2005. “Development of Innovative Goaf Inertisation Practices to Improve Coal Mine Safety.” In COAL OPERATORS’ CONFERENCE, Brisbane, QLD, 26–28. Scheidegger, A.E. 1957. The Physics of Flow through Porous Media. New York: The Macmillan Co. Slabbert, Rohan. 2011. “Thermal-Hydraulics Simulation of a Benchmark Case for a Typical Materials Test Reactor Using FLOWNEX.” North-West University. Smith, A C, and L Yuan. 2008. “Simulation of Spontaneous Heating in Longwall Gob Area with a Bleederless Ventilation System.” Mining Engineering (August): 61–66. Walter, Ayelet, Alexander Schulz, and Günter Lohnert. 2004. “Comparison of Two Models for a Pebble Bed Modular Reactor Core Coupled to a Brayton Cycle.” In 2nd International Topical Meeting on HIGH TEMPERATURE REACTOR TECHNOLOGY, Beijing, China. Xu, Guang. 2013. “Remote Characterization of Underground Ventilation Systems Using Tracer Gas and CFD.” Virginia Polytechnic Institute & State University. Yuan, L, and A C Smith. 2008a. Computational Fluid Dynamics Modeling of Spontaneous Heating in Longwall Gob Areas. 137
Virginia Tech
Applications of Queuing Theory for Open-Pit Truck/Shovel Haulage Systems Meredith Augusta May Abstract Surface mining is the most common mining method worldwide, and open pit mining accounts for more than 60% of all surface output. Haulage costs account for as much as 60% of the total operating cost for these types of mines, so it is desirable to maintain an efficient haulage system. As the size of the haulage fleet being used increases, shovel productivity increases and truck productivity decreases, so an effective fleet size must be chosen that will effectively utilize all pieces of equipment. One method of fleet selection involves the application of queuing theory to the haul cycle. Queuing theory was developed to model systems that provide service for randomly arising demands and predict the behavior of such systems. A queuing system is one in which customers arrive for service, wait for service if it is not immediately available, and move on to the next server or exit the system once they have been serviced. Most mining haul routes consist of four main components: loading, loaded hauling, dumping, and unloaded hauling to return to the loader. These components can be modeled together as servers in one cyclic queuing network, or independently as individual service channels. Data from a large open pit gold mine are analyzed and applied to a multichannel queuing model representative of the loading process of the haul cycle. The outputs of the model are compared against the actual truck data to evaluate the validity of the queuing model developed.
Virginia Tech
Chapter 1: Introduction Surface mining is the most common mining method worldwide, and open pit mining accounts for more than 60% of all surface output (Hartman & Mutmansky, 2002). Open pit mining consists primarily of the removal of topsoil and overburden, drilling and blasting of ore, and the transportation of material using a system of shovels or excavators and haul trucks. After the haul trucks have been loaded, the trucks transport the material out of the mine to a dumping location where the material will either be stored or further processed. The trucks then return into the mine and the cycle repeats itself. For most surface mines, truck haulage represents as much as 60% of their total operating cost, so it is desirable to maintain an efficient haulage system (Ercelebi & Bascetin, 2009). As the size of the haulage fleet being used increases, shovel productivity increases and truck productivity decreases, so an effective fleet size must be chosen that will effectively utilize all pieces of equipment (Najor & Hagan, 2004). When selecting earth-moving equipment for a particular mine site, shovels and trucks must be matched based on their characteristics. The loader needs to be an appropriate size relative to the height and width of the benches being mined, and the dumping height of the loader must be sufficient to clear the side of the haul truck. The loader selected should also be able to fully load a haul truck in three to six passes without using any partially filled buckets (Alkass, El- Moslmani, & AlHussein, 2003). The number of trucks required to meet production requirements and maximize efficiency is difficult to determine, and the number of trucks necessary will change over time as mining advances and haul routes become longer. One method of fleet selection involves the application of queuing theory to the haul cycle. Queuing theory was developed to model systems that provide service for randomly arising demands and predict the behavior of such systems. A queuing system is one in which customers arrive for service, wait for service if it is not immediately available, and move on to the next server once they have been serviced (Gross & Harris, 1998). For modeling truck-shovel systems in a mine, haul trucks are the customers in the queuing system, and they might have to wait for service to be loaded and at the dumping locations. 1
Virginia Tech
Chapter 2: Literature Review 2.1 Methods of Fleet Selection Before computer systems were readily available, estimates about haul cycles were made which would approximate average times for specific activities such as loading, travelling, dumping, and delay times. The reliability of this approach varies widely based on the analyst’s ability to obtain accurate average times for the cycle. This conventional method assumes that trucks make each round trip in exactly the same amount of time and that the productive capacity of a carrier is not affected by the number of carriers in the system. This method is not able to analyze variations between different cycles or different operating periods (Deshmukh, 1970). Optimal fleet size can also be estimated based on production tonnage requirements and individual truck productive capability. In this method a truck’s productive capacity is calculated based on a truck’s effective payload and its estimated cycle time multiplied by a productivity factor. The number of trucks that need to be operated is then calculated by dividing the hourly tonnage required by the tons per truck per hour, based on the calculated productive capacity (Burton, 1975). This method does not provide an accurate model of truck-shovel systems, but it does provide a rough estimation of the number of trucks required to meet production needs. Another common method for modeling fleet-loader systems involves stochastic simulation. In stochastic simulation a random number selection technique such as Monte Carlo simulation creates probability distributions from a stochastic variable based on data from time studies. This is done to obtain a sequence of variable times that might occur during actual operations. This can be used to find values for sections of the haul cycle such as loading time, dump time, or delay time. A model of a haul cycle is created based on the loading, haulage, and waiting times obtained through Monte Carlo simulation (Deshmukh, 1970). Computer simulation programs can quickly perform these simulations and the optimum number of trucks can be found by comparing models of a given haul route using different fleet sizes. Due to the stochastic and dynamic nature of shovel-truck interactions, different simulation models used to calculate fleet requirements will yield different fleet sizes for the same input parameters. This is largely due to the assumed 3
Virginia Tech
probability distributions applied to variables in the cycle and the waiting times for haulers and loaders calculated based on those assumptions (Krause & Musingwini, 2007). Talpac is a commonly used computer simulation program designed for evaluating haulage fleets that was developed by Runge. Users can input site specific parameters affecting fleet productivity such as material characteristics, haul route, truck and loader types, work roster, and operating limitations. Talpac can then calculate fleet productivity for long term and short term planning, equipment evaluation, optimum loading techniques, haulage costs, and other production values (Runge, 2011). Talpac is commonly used throughout the mining industry for shovel-truck analysis even though it can only fit a maximum of five probability distributions for cycle variables (Krause & Musingwini, 2007). Another method of fleet selection involves the application of queuing theory to the haul cycle. Queuing theory was developed to model systems that provide service for randomly arising demands and predict the behavior of such systems. A queuing system is one in which customers arrive for service, wait for service if it is not immediately available, and move on to the next server once they have been serviced (Gross & Harris, 1998). For modeling truck-shovel systems in a mine, haul trucks are the customers in the queuing system, and they might have to wait for service at the loader and at the dumping location. 2.2 Applying Queuing Theory to Mining Ernest Koenigsberg first applied queuing theory to mining practices in 1958. Koenigsberg modeled conventional, mechanized room and pillar mining operations using closed loop queuing systems with a finite number of customers based on the assumption of exponential service time distributions. The mining system being considered consists of a set of specialized machines which work in succession on a series of active mine faces. The entities involved in the cycle include a cutting machine, drilling machine, blasting crew, loading machine group – a loader and one or more shuttle car, and a roof bolting machine. Each machine proceeds to the next face when it is done with its task. The time it takes for each machine to complete its task is non- constant and subject to random time variations. Transit time and machine breakdowns also add to random time variation. This setup was translated into queuing theory notation by considering 4
Virginia Tech
the machines to be fixed in sequence with the mining faces queuing for service in cyclic, first come-first served order. In queuing theory notation, this translates to a closed queue with N customers receiving service in order of arrival from M machines. After the Mth stage, the customer (mine face) rejoins the queue at stage one (Koenigsberg, 1958). Koenigsberg adapts formulas to determine the probability that the system is in a given state, the mean number of units waiting for service at a given stage, the delay at a given stage, mean cycle time, probability that a stage is idle, and daily output. These equations can be recalculated for different numbers of servers and customers so that the results for different machine configurations can be compared. Koenigsberg finds that output increases as N, the number of working faces is increased, and the rate of change of increase decreases with increasing N. He also finds that the overall output is limited by the service rate of the slowest machine (Koenigsberg, 1958). Queuing theory gained popularity as a method of fleet selection and haul cycle analysis in the 1970s and 1980s. Simulation models were a commonly used technique for analysis of shovel- truck systems during this time period because they could provide useful results that accounted for the variability inherent in the system (Barnes, King, & Johnson, 1979). A major drawback of computer simulation was the method’s requirement of computer memory and CPU time, which was costly and time consuming. Analytical modeling methods with little to no computing requirements, such as queuing theory, were a viable alternative to computer simulation models (Billette, 1986). In 1973 Maher and Cabrera applied cyclic queuing theory to civil engineering earthmoving projects, similar to haulage systems found in open pit mining. Queuing theory is used here to find the optimum number of trucks that should be used to minimize the cost per unit volume of earth moved. The haulage system is analyzed with the option of considering loading and transit times to be constant or variable, fitting a negative exponential distribution. This study also recognizes that with more than one excavator in operation the system can have either two separate queuing systems or one joint queue. The end result of this modeling is a set of charts for choosing the most cost-effective number of trucks based on the ratio of the loading time and haulage time and the ratio of the costs to operate the loader and the trucks (Maher & Cabrera, 5
Virginia Tech
1973). These charts could be applied to any earthmoving or mining operation as long as the data about cost and cycle time is known. In 1977 Jorgen Elbrond developed a straightforward calculation technique based on queuing theory to be used as an alternative to computer simulation for evaluating open pit operation capacity. Elbrond’s technique is based on queuing theory’s formula for waiting time in a closed circuit with added correction factors which reflect variability in loading, travel, and dumping times. Waiting times at service stations are calculated as a function of the number of trucks in the circuit by averaging the results found through simulations for three different cases: constant travel time and constant service time, exponentially distributed travel time and exponentially distributed service time, and exponentially distributed travel time and constant service time. Correction factors are calculated using an interpolation procedure combining theoretical and simulated cases. Other data relevant to the haul cycle such as dumping time and shift composition is found using time studies. Once formulas had been completely developed, time studies made at Hamersley Iron found a correlation coefficient of 0.865 between observed and calculated wait time at shovels (Elbrond, 1977). This suggests that the technique used is a reasonably accurate method of modeling haulage systems. Barnes, King, and Johnson approach queuing theory as an alternative to costly computer simulation and rough-estimate match factor and efficiency factor methods of approximating production capacities of open-pit systems. In their paper Ernest Koenigsberg’s approach to mine modeling using cyclic queues and Jorgen Elbrond’s work with finite queues are outlined and compared to one another and to the results of stochastic simulation. The goal of this comparison is to observe any systematic relationship between the estimates found using each method (Barnes, King, & Johnson, 1979). This comparison found that stochastic simulation is more flexible than the two queuing theory methods and provides more accurate results. Unlike the methods relying on queuing theory, simulation does not assume steady state conditions for the entirety of the cycle time; simulation is able to account for startup time and end of shift activity. The main disadvantages associated with stochastic simulation are the significant amount of time and manpower necessary to develop the simulator and the considerable amount of computer time that is used to run the simulation. 6
Virginia Tech
This study found that cyclic queuing as it existed at the time, such as Koenigsberg’s model, is not an adequate method of estimating truck-shovel production. This is largely based on the mathematical requirement that all segment times be exponentially distributed. This causes the effects of bunching and mismatch to be greatly exaggerated, and for production to be understated. It was concluded that this method does not produce a true representation of the system’s productive capacity. Elbrond’s finite queuing theory application can produce a fairly accurate estimate of production values by applying a correction factor to account for the results found using exponentially distributed activity times. Elbrond generates waiting times and subsequently production predictions which closely approximate observed values by interpolating between his three cases, which are: constant travel time and constant service time, exponentially distributed travel time and exponentially distributed service time, and exponentially distributed travel time and constant service time. Barnes, King, and Johnson conclude that while Elbrond’s finite queuing theory method produces a more accurate model than Koenigsberg’s cyclic queues do, modifications are needed either to the correction factors or to the method itself in order to more closely resemble actual operations output (Barnes, King, & Johnson, 1979). In the late 1970s nearly all applications of queuing theory to mine production used exponential distributions. There were few alternatives available since the use of more-general distributions such as normal or log-normal distributions involved prohibitively complex mathematics. However, the Barnes, King, and Johnson study does address the possibility of using an Erlang K distribution with finite queues, similar to Elbrond’s technique. For this proposed method only two cases would need to be analyzed: exponential arrival with Erlang K service and deterministic arrival with Erlang K service. The Erlang distribution parameters account for the effects of variability in the service rate. Correction factors need only be applied as a function of arrival rate variability. An extension of these models would be one with Erlang arrival and Erlang service times to eliminate the need for interpolation or correction factors, but the math involved with such a model would be exceptionally complex. At the time their paper was published, no solution to an Erlang/Erlang finite queuing model had been developed, but it was determined that developing such a model would provide a useful, inexpensive analytical alternative to simulation methods for open pit production calculations (Barnes, King, & Johnson, 1979). 7
Virginia Tech
Barbaro and Rosenshine presented a paper in 1986 which uses a cyclic queuing theory model to evaluate the productivity of a truck-shovel system. A cyclic queuing model with exponentially distributed service times is used to model an example problem and the results are compared to those from simulation to demonstrate that the assumptions of exponentially distributed service times and steady state behavior are not major problems. Barbaro and Rosenshine compare their cyclic queuing model to the methods used in the 1979 Barnes, King, and Johnson study and achieve results more favorable than those reached in the original paper. Barnes et al. consistently reported results from queuing theory-based models that exceeded the theoretical maximum capacity of the mine in question. The results of the Barbaro and Rosenshine study find that the cyclic queuing model in question is correctly coded and provides valid results. In their study, shovel utilization rates found using cyclic queuing models only differ from the results found through simulation by 0.4% and productivity values differ by 0.9%. No explanation is offered to explain the discrepancy between the different results found in the 1979 and 1986 studies (Barbaro & Rosenshine, 1987). Engineering Queues in Construction and Mining by D. G. Carmichael contains queuing theory models based on assumptions applicable to mining and construction operations which have been validated by reference to field data records comparing theory and practice. Models for many different situations are provided, including queues with random arrivals and exponential service times; queues with alternative distributions for arrivals and servicings; cyclic queues; serial queues and storage; earthmoving, quarrying, and open-cut mining operations; and machine maintenance and repair. While there are many formulas and equations supplied for each of these topics that can easily be used as tools in scheduling, planning, productivity analysis, and cost analysis, there is little information given about how closely these models follow actual operations (Carmichael, 1987). Muduli and Yegulalp’s 1996 paper presents an analytical method of modeling truck-shovel systems as a multiple-chain closed queuing network. This allows the model to account for haulage systems which do not necessarily contain identical trucks. Prior to this, nearly all queuing theory-based models of haulage systems were based on the assumption that the fleet is composed of only one truck type. Carmichael addresses heterogeneous cases where trucks are not assumed to be identical in his book (Carmichael, 1987). Carmichael uses an approximation 8
Virginia Tech
method to adapt the heterogeneous system into an equivalent homogeneous system, but this is not a method based on queuing theory techniques. Muduli and Yegulalp address the problem using a closed queuing network with multiple classes of customers. This allows for different classes of trucks with different capacities and operating characteristics to be included (Muduli & Yegulalp, 1996). In queuing theory, a chain consists of a permanent categorization of jobs. As it applies to mining, a job (truck) which is part of one chain cannot switch to another. Different types of trucks can be sorted into different classes depending on their size and productivity. For this model, it is assumed that there is a single class of trucks per chain. Different classes of trucks can be given different characteristics by assigning different general service-time distributions to each one (Muduli & Yegulalp, 1996). Often in truck-shovel modeling all trucks within the system are assumed to be identical for analytical purposes, even when it is recognized that multiple types and sizes of trucks are present in the system. This is done to simplify calculations. To calculate performance characteristics of these multiple chain queuing systems involving multiple classes of trucks a Mean Value Analysis (MVA) approach is used for conditions when all trucks of different classes have identical exponential service time distributions. For situations with generally distributed service times a method called Extended MVA can be used for multiple classes of trucks and service times (Muduli & Yegulalp, 1996). This study compares results found using multiple chain queuing networks to the results of evaluating a system with multiple classes of trucks by assuming all trucks are identical. It is found that the maximum production rate calculated using an equivalent single-class model underestimates the maximum production rate that is possible using multiple classes of trucks by as much as 14% when two different classes of trucks are present. The relative error of maximum truck production found using equivalent single-class models increases as the number of trucks and the number of different classes of trucks involved increase. It is clear that a modeling system that accounts for different classes of trucks is essential to determine the optimal number of different sizes of trucks to maximize a mine’s production output (Muduli & Yegulalp, 1996). 9
Virginia Tech
In 2002 Khalil El-Moslmani created a computer model based on queuing theory to model multi- loader truck systems assuming trip times have a negative exponential distribution and service times follow an Erlang distribution with three or fewer servers. For cases with multiple types of haulers, unlike Muduli and Yegulalp’s method involving multiple chain queuing systems, an approximation based on weighted averages is used to convert the heterogeneous system into a homogeneous one. This is similar to Carmichael’s method of converting heterogeneous systems into homogeneous ones (Carmichael, 1987). El-Moslmani’s queuing model is solved to obtain values such as server utilization to be used in the calculation of system production. The computer module, called FLSELECTOR, is used to assist in choosing proper fleet size. FLSELECTOR is implemented using Visual Basic for Application (VBA) and Microsoft Excel and allows for an optimum fleet to be selected based on least cost, maximum production, or minimum project duration (El-Moslmani, 2002). FLSELECTOR also allows the user to compare the different production outputs that would be achieved using different haul routes from the loading area to the dumping area (Alkass, El- Moslmani, & AlHussein, 2003). Charts for the ten best fleets for a particular set of requirements can be viewed and printed. Arrival rate, service rate, utilization, production, cost, duration, and cost per unit are calculated for each fleet. Calculation may take only a few seconds for situations with one server and one type of truck or as long as ten minutes for more complex systems such as those with three servers with more than two types of haulers (El-Moslmani, 2002). The performance of FLSELECTOR is compared to the results of simulation and deterministic methods. When comparing results to those from deterministic models, FLSELECTOR gives smaller production values than the deterministic model does. This is consistent with studies which have found that deterministic models tend to overestimate production values. FLSELECTOR gives output relatively in line with that of the simulation system SimEarth. Comparison indicates that the two methods’ outputs differ by an average of 14% (El-Moslmani, 2002). Limitations of FLSELECTOR include the fact that it can only handle a maximum of three servers and its assumption that no queues will form at the dumping point. Despite this, FLSELECTOR provides a user-friendly method of applying queuing theory to fleet selection and 10
Virginia Tech
offers multiple configurations of fleet components that can meet the needs of individual project requirements. The paper does not specify whether predicted FLSELECTOR output has been compared to the data obtained from actual fleet performances (El-Moslmani, 2002). Najor and Hagan present an approach to mine scheduling that incorporates a heuristic model based on queuing theory. The goal in developing this model is to reduce financial expenditure in the mine production system by efficiently managing the fleet, maximizing the use of equipment while minimizing the resources necessary to support this equipment, and ensuring that fleet size matches targets for material movement. To develop this model, queuing theory is applied to a capacity-constrained model based on truck productivity (Najor & Hagan, 2004). Queuing formulas for values such as expected wait time and expected number of trucks being serviced are incorporated into a spreadsheet which calculates production values and the estimated cost per tonne of material moved. Comparison between the capacity constrained model and a conventional, mechanistic approach shows that the capacity-constrained model offers more conservative production values than the conventional approach, which tends to overestimate mining capacity. On average, the conventional approach underestimates the amount of time it would take to complete a project by 8% compared to the amount of time found using the capacity-constrained method (Najor & Hagan, 2004). It is recommended that the capacity constrained method be used in mines with relatively short haul distances. As haul distance increases the productivity values found for haul trucks become very similar regardless of what method is used to calculate them. In this study, the capacity- constrained, queuing theory based model is applied to a situation requiring relatively few trucks to meet production needs. The optimum fleet size found to minimize the cost per tonne of material moved for the model in question consists of only three or four trucks (Najor & Hagan, 2004). This is significantly smaller than fleet sizes for large open-pit mines which can require more than 100 trucks to meet production needs. Krause and Musingwini demonstrate that a modified Machine Repair Model, an example of a finite source queuing model, can be applied to mining projects to accurately estimate required fleet size. Based on the Machine Repair Model, a truck is sent for loading (repair) every cycle 11
Virginia Tech
and there is a set number of shovels (repair bays). Interarrival time and service time are both assumed to be exponentially distributed. Since trucks are drawn from a finite population, their arrival pattern depends on the state of the system. Equations for situations in the Machine Repair Model are easily adjusted to fit loading and hauling situations. For example, the average time a truck spends waiting for repair becomes the average amount of time a truck queues at the loading unit or dump site (Krause & Musingwini, 2007). The modified Machine Repair Model and four common methods of analyzing shovel-truck systems are applied to a virtual mine. These common methods include Elbrond’s cyclic queuing model, a regressive model developed by Caterpillar called Fleet Production and Cost model (FPC), Talpac, and a stochastic simulation model called Arena. Loading cycle times of three, four, and five minutes are simulated and dumping and maneuvering times are kept constant, assuming consistent operator ability. Using these assumptions, the five models are run to produce estimates of achievable shift production. The Arena model is used as a benchmark for comparing the accuracy of the other estimation methods. The Arena model is used as a benchmark because its ability to be programmed with any number of probability distribution models fitted to an unlimited number of cycles makes it very flexible and capable of closely imitating real mining systems (Krause & Musingwini, 2007). All of the models used produce estimates of loads per shift that are within 97%-99.7% of the Arena estimates. Arena reports slightly more loads per shift than the other models do, which can indicate that the other models are slightly more conservative. Overall, the results indicate that the modified Machine Repair Model is capable of producing productivity estimates that closely resemble those of other common truck-shovel analysis methods. When used to calculate fleet size necessary to meet increased production requirements at a surface coal mine in South Africa, the modified Machine Repair Model again produces results that are comparable to the other models. Arena, the modified Machine Repair Model, and Elbrond’s model all calculate an optimum fleet size of nine trucks. FPC and Talpac calculate that an additional truck is necessary, for a fleet size of ten trucks. Based on this, it is concluded that the modified Machine Repair Method produces production values and fleet sizes that are comparable to other commonly used models. The modified Machine Repair Model also has the advantage of being relatively 12
Virginia Tech
inexpensive, since it can be modeled using Microsoft Excel, a program which most mining companies already use (Krause & Musingwini, 2007). Czaplicki’s goal in his 2009 book is to allow operations to get the maximum profit from their loading and hauling systems by reducing losses in production time and having high utilization of the machines involved. Czaplicki applies queuing theory to shovel-truck systems using a modification of the Maryanovitch queuing model for truck reliability and repair. This involves using cyclic queues with two phases, service and travel, where service consists of loading the trucks and travel consists of haulage, dumping, and returning. Normal distributions are used to represent service and travel times and it is assumed that no queuing occurs at the dump site. Czaplicki presents formulas determining parameters such as truck fleet size, reserve fleet size, probability distributions for numbers of trucks and shovels in work state, and system productivity based on equipment reliability, the numbers of various pieces of equipment involved, and cycle time distributions (Czaplicki, 2009). Czaplicki applies his formulas to two case studies to see how accurately an example machinery system can be modeled. One case study involves five loaders and trucks with a high availability, and the other involves seven loaders and trucks with low availability that will require repair more frequently and thus have less time available for haulage. For both system parameters, the equations determine an appropriate number of trucks and repair stands. Both systems yield an average queue length of approximately 1.4 trucks per loader. This means that the loader is able to achieve near-continuous production and relatively little truck cycle time is lost due to waiting (Czaplicki, 2009). Ercelebi and Bascetin present a method of assigning trucks to shovels using closed queuing network theory for systems using only one type of truck. For truck-shovel systems where minimizing cost per amount of material moved is the primary goal, a balance must be achieved between the cost of idle time for the shovel and the cost associated with providing extra trucks. Loading, hauling, and dumping times are assumed to fit exponential distributions. Production costs are determined by incorporating the hourly cost to run each piece of equipment into the equations calculating the number of trucks to be used. Cost predictions for the system found using queuing theory are compared to the results found using a linear programming model and a 13
Virginia Tech
case study for overburden removal at an open pit coal mine. Queuing theory provides the minimum loading and hauling costs for the system, along with an optimal number of trucks assigned to the shovels. When this system is implemented on the mine in question, the overburden removal target for the year is exceeded and average production costs are reduced (Ercelebi & Bascetin, 2009). Ta, Ingolfsson, and Doucette present a paper based on truck and shovel behavior in oil sands mining. Their goal is to use queuing theory to capture the nonlinear relationship between average mine throughput and the number of trucks in use and then develop this relationship into a manageable optimization model. The model includes options for only a single truck size or multiple truck sizes, and individual trucks are assigned a readiness parameter so that the model can indicate both how many trucks are necessary and which individual trucks ought to be used. Shovel service times and truck back-cycle times are represented with an Erlang distribution. The probability that a shovel is idle is linearized so that shovel throughput can be expressed as a linear function. This model is compared to simulation results and it is shown that the optimization model accurately predicts shovel utilization and idle time. Information about truck utilization and idle time is not calculated, but the optimization model provides valuable information about how many trucks should be used to meet necessary production targets (Ta, Ingolfsson, & Doucette, 2010). 2.3 Conclusion Most surface mines use truck and shovel systems to transport ore and waste material. It can be difficult to determine the proper number of trucks that should be used in these systems due to the dynamic nature of fleets of equipment and the fact that the length of the haul road is continually increasing as mining progresses. There are many different methods to model and simulate truck and shovel behavior, and companies are constantly looking for ways to quickly and more accurately predict equipment performance. Queuing theory presents a promising method to account for idle time caused by trucks waiting to be serviced at either the loading or dumping point. When trucks and shovels are represented as servers and customers in a queuing network, the proper number of machines that should be implemented in a mine can be determined, ensuring that production needs can be met while still maintaining efficient use of equipment. 14
Virginia Tech
Chapter 3: Applications of Queuing Theory for Open-Pit Truck/Shovel Haulage Systems 3.1 Abstract Surface mining is the most common mining method worldwide, and open pit mining accounts for more than 60% of all surface output. Haulage costs account for as much as 60% of the total operating cost for these types of mines, so it is desirable to maintain an efficient haulage system. As the size of the haulage fleet being used increases, shovel productivity increases and truck productivity decreases, so an effective fleet size must be chosen that will effectively utilize all pieces of equipment. One method of fleet selection involves the application of queuing theory to the haul cycle. Queuing theory was developed to model systems that provide service for randomly arising demands and predict the behavior of such systems. A queuing system is one in which customers arrive for service, wait for service if it is not immediately available, and move on to the next server or exit the system once they have been serviced. Most mining haul routes consist of four main components: loading, loaded hauling, dumping, and unloaded hauling to return to the loader. These components can be modeled together as servers in one cyclic queuing network, or independently as individual service channels. Data from a large open pit gold mine are analyzed and applied to a multichannel queuing model representative of the loading process of the haul cycle. The outputs of the model are compared against the actual truck data to evaluate the validity of the queuing model developed. 3.2 Introduction Surface mining is the most common mining method worldwide, and open pit mining accounts for more than 60% of all surface output (Hartman & Mutmansky, 2002). For most surface mines, truck haulage represents as much as 60% of their total operating cost, so it is desirable to maintain an efficient haulage system (Ercelebi & Bascetin, 2009). As the size of the haulage fleet being used increases, shovel productivity increases and truck productivity decreases, so an 16
Virginia Tech
effective fleet size must be chosen that will efficiently utilize all pieces of equipment (Najor & Hagan, 2004). Having more trucks in service than necessary wastes fuel, as trucks must spend time idling while waiting for service, and the company must pay the vehicle operators to drive a truck that is not actually needed. Alternately, having too few trucks causes idle time for the loaders, which causes a drop in production. By applying queuing theory to mining haulage systems, the inherent stochastic nature of haul truck and loader behavior can be accounted for and the model created can be used to adjust fleet sizes to better serve loading needs. In this project a queuing model was generated that can be used to model truck and loader behavior in an open pit mine. The model is then applied to actual haulage data from an active mining operation. 3.3 Queuing Theory Background Queuing theory was developed to provide models capable of predicting the behavior of systems that provide service for randomly arising demands. A queuing system is defined as one in which customers arrive for service, wait for service if it is not immediately available, and move on to the next server or exit the system once service is complete. Queuing theory was originally developed to model telephone traffic. Randomly arising calls would arrive and need to be handled by the switchboard, which had a finite maximum capacity. There are six basic characteristics that are used to describe a queuing system: arrival distribution of customers, service distribution of servers, queue discipline, system capacity, number of service channels, and number of service stages (Gross & Harris, 1998). 3.3.1 Customer Arrivals In most queuing situations the arrival process of new customers to the system is stochastic. In these cases it is necessary to know the distribution of the times between successive customer arrivals, or the interarrival times. It is also important to understand the behavior of customers upon entering the system. Some customers may wait for service no matter how long the queue is, while others may see that a queue is too long and decide not to enter the system. When this happens the customer is described as having balked. Other customers may enter the system, but lose patience after waiting in the queue and decide to leave the system. These customers are said 17
Virginia Tech
to have reneged. In situations with two or more parallel waiting lines a customer who switches from one line to the other is said to have jockeyed for position. Any or all of these behaviors may be present when a queuing system has what are classified as impatient customers. Impatient customers cause state-dependent arrival distributions, since the arrival pattern of new customers depends on the amount of congestion in the system at the time of their entry. 3.3.2 Service Distributions A probability distribution is also necessary to describe customer service times, since it will not always take the same amount of time for each customer to receive service. Single service, where one customer is serviced at a time, or batch service, where multiple customers receive simultaneous service from a single server are both service options. A common example of a queuing system utilizing batch service involves waiting in line for a roller coaster. In this scenario, the people waiting in line are the customers and the roller coaster car is the server. A single line is formed to wait, and when the roller coaster car arrives the first four people in line who get into the car receive simultaneous batch service. In some cases the service process may be dependent upon the number of customers waiting in the queue. The server may work more quickly due to the lengthening queue, or alternately the server may become flustered by the large number of customers waiting and the service rate may slow as a result. Situations in which the service rate depends on the number of customers in the queue for service are referred to as state-dependent services. 3.3.3 Queue Discipline The manner in which customers in a queue are selected for service is referred to as the queue discipline. The most common queue discipline is first come, first served, or FCFS, where customers receive service in the order in which they arrived. This discipline is also commonly referred to as FIFO, or first in, first out. Another common queue discipline is LCFS, or last come, first served. This is commonly used in inventory situations where the most recently placed items waiting to be used are the most easily reached to be selected. RSS is a service discipline in which customers are selected for service in random order, independent of their order arriving to the queue. 18
Virginia Tech
There are a variety of different priority queue disciplines where different classes of customers are given higher priorities than other classes. In these disciplines the customer with the highest priority will be selected for service ahead of lower priority customers, regardless of how long each customer has been in the queue. If the queue discipline is preemptive, a customer with the highest priority is allowed to receive service immediately upon arrival at the server, even if a lower priority customer is already in service. The lower priority customer whose service is preempted resumes service after the higher priority customer has left. In nonpreemptive cases the highest priority customer that arrives at the server moves to the head of the queue, but must wait until the customer currently being serviced has left (Cooper, 1972). 3.3.4 System Capacity If a queue has a physical limitation to the number of customers that can be waiting in the system at one time, the maximum number of customers who can be receiving service and waiting is referred to as the system capacity. These are called finite queues since there is a finite limit to the maximum system size. If capacity is reached, no additional customers are allowed to enter the system. 3.3.5 Number of Service Stations The number of service stations in a queuing system refers to the number of servers operating in parallel that can service customers simultaneously. In a single channel service station, there is only one path that customers can take through the system. Figure 3.1 below shows the path customers, represented by circles, take through a single service channel queuing network. The customers arrive at the server, represented by the rectangle, and form a queue to wait for service if it is not immediately available, and then proceed through the system once service has been completed. Figure 3.1: Single Channel Queuing System When there are multiple servers available operating in parallel, incoming customers can either wait for service by forming multiple queues at each server, as shown in (a) of Figure 3.2, or they 19
Virginia Tech
can form a single queue where the first customer in line goes to the next available server, depicted in (b). Both of these types of queues are commonly found in day-to-day life. At the grocery store individual lines are formed at each cashier, but a single line is generally formed when customers are waiting in line at the bank. The first customer in line then proceeds to the next available teller. A single queue waiting for multiple servers is generally the preferred method, as it is more efficient at providing service to the incoming customers. Figure 3.2 Multichannel Queuing Systems 3.4 Notation Queuing processes are frequently referred to by using a set of shorthand notation in the form of (a/b/c/):(d/e/f) where the symbols a through f stand for the characteristics shown below in Table 3.1. Table 3.1: Queuing Notation Abbreviations Symbol Characteristic a arrival distribution b service distribution c number of parallel servers d service discipline e maximum number of units that can be in the system at one time f source population size The symbols a through f will take different abbreviations depending on what type of queuing process is being described. Symbols a and b both represent types of distributions, and may contain codes representing any of the common distributions listed in Table 3.2. 20
Virginia Tech
Table 3.2: Distribution Abbreviations Symbol Explanation M Markovian: exponentially distributed interarrival or service times D Deterministic: constant distribution E Erlang distribution with parameter l l G General Distribution Symbols c, e, and f all represent discrete values and are represented with the appropriate number or ∞ if there is no limit to the system size or population source. The service discipline, d, may be represented by any of the abbreviations explained below in Table 3.3. Table 3.3: Service Disciplines Symbol Explanation FCFS First come, first served FIFO First in, first out (same as FCFS) LCFS Last come, first served RSS Random selection for service PR Priority SIRO Service in random order The (d/e/f) term is often omitted, and in such cases the default assumptions are (FCFS/∞/∞). For example, an (M/D/3) queue would have exponential interarrival times, deterministic service rates, and three servers working in parallel. While not explicitly stated, a service discipline of first come, first served and infinite queue capacity and an infinite calling population are generally implied. 3.5 Queuing Systems in Mining In mining operations, queues frequently form during the haulage process as trucks arrive at loaders, crushers, and dump locations and have to wait their turn in line. This process can be represented using queuing networks where the haul trucks represent the customers in the system and the servers are the loaders or crushers that the trucks are waiting for. When representing loading operations with queuing systems, the time a truck spends positioning and spotting at the loader can be included either as part of the loading cycle time or as part of the time the truck was waiting in the queue for service. Figure 3.3 below depicts a basic mining queuing system composed of haul trucks and excavators. 21
Virginia Tech
The above cyclic queuing model can be adjusted to include multiple loaders, operating in parallel. Figure 3.5 below shows a possible configuration with three loaders with a single queue formed for trucks to wait to be loaded, but any number of loaders could be used. Figure 3.5: Cyclic Queuing System with Parallel Loaders The cyclic queues represented above model the haulage systems for basic mine layouts. As the complexity of mining operations increases more intricate queuing systems must be used to represent operations. A network queue, such as the one depicted below in Figure 3.6 can be used when there are multiple paths available to the haul trucks. For this type of queuing model to work, metrics are necessary to determine the likelihood of each path being taken throughout the haul cycle. This could depend on the congestion of part of the system, the characteristics of each individual server, the contents of the truck’s load, or a myriad of other factors. 23
Virginia Tech
Figure 3.7: Queuing Schematic with Multiple Pits 3.6 Recent Applications of Queuing Theory to Mining One recent mining application of queuing theory involves a closed queuing theory network assuming exponential distributions for loading, hauling, and dumping times. This model was developed to minimize production costs per amount of material moved. Production costs are incorporated by applying hourly costs to run each piece of equipment. Cost predictions for the system found using queuing theory were compared to the results found using a linear programming model and a case study for overburden removal at an open pit coal mine. Queuing theory provides the minimum loading and hauling costs for the system, along with an optimal number of trucks assigned to the shovels. When this system is implemented on the mine in question, the overburden removal target for the year is exceeded and average production costs are reduced (Ercelebi & Bascetin, 2009). Another recent queuing mining project uses queuing theory to capture the nonlinear relationship between average mine throughput and the number of trucks in use, and then develops this 25
Virginia Tech
relationship into an optimization model. The model includes options for single truck sizes or multiple truck sizes, and individual trucks are assigned a readiness parameter so that the model can indicate both how many trucks are necessary and which individual trucks ought to be used. Shovel service times and truck back-cycle times are represented with an Erlang distribution. The probability that a shovel is idle is linearized so that shovel throughput can be expressed as a linear function. This model is compared to simulation results and it is shown that the optimization model accurately predicts shovel utilization and idle time. Information about truck utilization and idle time is not calculated, but the optimization model provides valuable information about how many trucks should be used to meet necessary production targets (Ta, Ingolfsson, & Doucette, 2010). 3.7 Queuing Model A model of a truck and shovel system for an open pit mine with multiple loaders operating within the pit was constructed using Microsoft Excel. This was done with the goal of providing a middle ground between very simplistic deterministic methods of analyzing haul truck fleet performance and complex, full-blown simulations that incorporate every aspect of mine activity. The rate of new haul truck arrivals and the loading rates of the excavators were both assumed to be exponential. An (M/M/c) queuing model was selected to follow this assumption of exponential service and interarrival times and to allow for various numbers of loaders to be selected. An (M/M/c) model is one in which each server has an independent and identically distributed exponential service-time distribution and an exponential arrival process. This model of pit behavior is versatile and can be used to model pit behavior for a variety of different haulage configurations and mine layouts. The service discipline used is first come first served, with the assumption that there are no special classes of trucks. 3.7.1 Inputs To use this model, the values for the number of loaders operating, the arrival rate of new trucks, and the service rate per loader must be known to be used as inputs to the model. The necessary inputs are outlined on the following page in Table 3.4. 26
Virginia Tech
Table 3.4: Queuing Model Inputs Symbol Explanation λ Average arrival rate of new trucks μ Average service rate per loader c Number of loaders operating in parallel The arrival rate, λ, is the average rate at which new trucks arrive at the loader. The service rate, μ, is the service rate of an individual loader. In cases with more than one loader in operation, all loaders are assumed to be equivalent, so μ would be the average service rate of the loaders. The arrival rate, λ, and service rate, μ, should both be input in the form of trucks per hour. Both the arrival rate and the service rate are independent of queue length. The queue will not have impatient customers, since it would be unrealistic for haul trucks to not join the line to be loaded, regardless of how many trucks are already waiting. There would also be no jockeying for position since trucks form a single line to wait to be loaded, with the first truck going to the next available loader. The model uses this information to calculate a variety of outputs about the truck and shovel system. 3.7.2 Equations Based on this queuing system and input variables, the variables r and ρ are defined as, r = λ/μ Equation 3.1 and ρ = r/c = λ/cμ Equation 3.2 Where r is the expected number of trucks in service, or the offered workload rate, and ρ is defined as the traffic intensity or the service rate factor (Giffin, 1978). This is a measure of traffic congestion. When ρ > 1, or alternately λ > cμ where c is the number of loaders, the average number of truck arrivals into the system exceeds the maximum average service rate of the system and traffic will continue back up. For situations when ρ > 1, , the probability that there are zero trucks in the queuing system is defined as 27
Virginia Tech
(∑ ) Equation 3.3 Where n is the number of trucks available in the haulage system. Even in situations with high loading rates, it is extremely likely that trucks will be delayed by waiting in line to be loaded. The queue length will have no definitive pattern when arrival and service rates are not deterministic, so the probability distribution of queue length is based on both the arrival rate and the loading rate (Gross & Harris, 1998). The expected number of trucks waiting to be loaded, , can be calculated based on using the following equation. Equation 3.4 = ( ) The average number of trucks in the queuing system, L, and the average time a truck spends waiting in line, , can be found by applying Little’s formula which states that the long term average number of customers in a stable system, L, is equal to the long term average effective arrival rate, λ, multiplied by the average time a customer spends in the system, W (Gross & Harris, 1998). Algebraically, this is expressed as L = λW Equation 3.5 and can also be applied in the form = λ Equation 3.6 Using these equations, the average time a truck spends waiting to be loaded, can be calculated as follows. = = ( ) Equation 3.7 The average time a truck spends in the system, W, is defined as 28
Virginia Tech
Equation 3.8 W = + = + ( ) The model currently supports up to seven loaders operating in parallel, but could easily be adjusted to include more. There is no limit on haul truck fleet size, provided the arrival rate of trucks to the loading system does not increase to the point of overwhelming the loading capacity. This model is only valid for values of ρ, the traffic intensity per server, that are less than one. If ρ were to increase above one, the system would back up indefinitely, as the arrival rate of empty trucks would be greater than the loaders are capable of handling. 3.7.3 Outputs When given the appropriate inputs, the model calculates and outputs values for various aspects of pit activity. These include loader utilization, the average time a truck spends in the system, the average time a truck spends waiting to be loaded, the average number of trucks waiting in line, the average number of trucks in the system, and the system output in trucks per hour. Table 3.5 below lists the outputs created by the model and the appropriate units for each variable. Table 3.5: Queuing Model Outputs Variable Units Description ρ % Loader Utilization W hours Time spent in system W hours Time spent in queue q L Number of trucks Number of trucks in system L Number of trucks Number of trucks in queue q θ Trucks per hour System output Figure 3.8 on the following page shows a screenshot of the model. The values the user inputs are highlighted in yellow, and the intermediate calculations and final outputs are highlighted in green. 29
Virginia Tech
Figure 3.8: Screenshot of Model 3.8 Example Application While this queuing model provides information about the system being modeled that is correct based on the equations of queuing theory, it is necessary to see if the actual behavior of trucks in a mine are consistent with the model. Haul truck data were obtained from a large surface gold mine located outside of the United States. Information about the haul trucks in this mine was obtained in the form of Global Positioning System (GPS) data. Each truck is equipped with a GPS unit that records the easting, northing, elevation, and speed at regular time intervals. This information, combined with the contour map of the mine, allows the complete haul route to be examined. 3.8.1 Data Haul truck GPS information was obtained in the form of .dat files containing thousands of data points, each with a time stamp, truck number, truck speed, and location based on easting northing and elevation. Truck speed is reported in kilometers per hour, and all of the time stamps are in the format of seconds beginning January 1, 1970. When this information is imported into AutoCad along with the mine map it is possible to determine information about loading locations, haul routes, dumping locations, and areas where trucks are waiting. The data files were formatted so that AutoCAD Civil 3D could plot each haul truck location on a contour map of the mine property and store the truck ID number, time stamp, and corresponding velocity for each point. 30
Virginia Tech
3.8.3 Loading Loading areas are identified based on the locations where haul trucks are stopped in the pit. This was accomplished by importing the data from a particular shift into Microsoft Excel and filtering the points based on truck velocity. Points where trucks had a velocity of zero were selected and imported onto an AutoCAD contour drawing of the mine to show locations where vehicles were stopped. The trucks could be stopped either to wait for service or while receiving service at the loaders or dumping locations. As shown below in Figure 3.14 with points representing locations where haul trucks are stopped, the locations where the three loaders were operating are clearly identifiable by the clusters of points representing stopped trucks throughout the shift. Figure 3.14: South Pit Loading Locations The data points of haul trucks stopped in the loading areas were isolated from the rest of the data. These points were sorted based on truck number, and for each truck the time stamp for when a new loading cycle began was recorded. This was determined based on the amount of time that had passed between data points for an individual truck. Since only data points located within the 35
Virginia Tech
loading area were being considered, a large time gap meant that the truck had left the loading area during that interval, so the next data point represents a new arrival. Once the new arrival time stamps for all of the trucks active during this time period had been recorded they were combined to form a list of all of the new truck arrivals for that shift. These times were then used to calculate the distribution of arrival times of haul trucks to be loaded. The amount of time between each new arrival was calculated by subtracting the difference between each successive time stamp of arriving haul trucks. For these purposes, a new arrival is defined as when the haul truck first comes to a stop within the pit limits. The times between arrivals were sorted into bins and used to create a graph of frequency vs. time between new arrivals. Frequency is represented as a percentage of the total number of arrivals that occurred during the shift. Figure 3.15 below shows an example of this type of plot, created using data from twelve hours of production in the south pit with twenty two trucks in operation. 20 ) s 18 l a y = 13.057e-0.007x v 16 i r R² = 0.8759 r a 14 l a t 12 o t f 10 o % 8 ( y c 6 n e u 4 q e r 2 F 0 0 100 200 300 400 500 600 Time Between Truck Arrivals (sec) Figure 3.15: South Pit Arrival Distribution Various equations were applied to the data and it was found that the exponential equation is an adequate fit for the interarrival times of haul trucks in the south pit. The same process was applied to trucks operating in the north pit, but there were not enough trucks operating in that pit to yield any discernible distribution of arrival times. Figure 3.16 on the following page shows the frequency of interarrival times for that pit over a full shift. It is clear that the data do not form a 36
Virginia Tech
distribution. Haulage operations such as this one cannot be modeled using queuing theory, since a distribution could not adequately represent interarrival times in the system. 10 ) s l 9 a v i r 8 r A 7 l a t 6 o T f 5 o % 4 ( y 3 c n e 2 u q e 1 r F 0 0 200 400 600 800 1000 Time Between Truck Arrivals (sec) Figure 3.16: North Pit Interarrival Times 3.8.4 Service Times The loading service time distributions were more difficult to obtain, since the GPS information does not differentiate between times when a truck is stopped because it is waiting to be loaded and times when a truck is stopped while being loaded. The service times for individual loaders were determined by isolating the data points corresponding to each loader operating in the pit and identifying the time stamp that corresponds to each time the truck left that specific loading area. Similar to how arrival times were determined, the departure times were identified as the last time a particular truck was in the loading area before a large time gap. Once all of the time stamps corresponding to trucks departing from the loader had been recorded, they were combined to form a list of all of the truck departures for that loader during that work shift. These times were then used to calculate the distribution of service times for the loader. The amount of time between each departure was calculated by subtracting the difference between each successive time stamp of departing loaded haul trucks. This difference in times between successive truck departures represents the amount of time it takes for a loader to service one haul truck. This method includes the truck’s spotting time as part of the service time. The times 37
Virginia Tech
between departures were sorted into bins and used to create a graph of frequency vs. time between new arrivals. Frequency is represented as a percentage of the total number of departure times calculated for the shift. Figure 3.17 below shows an example of this type of plot for one loader, created using data from twelve hours of production in the south pit with twenty two trucks in operation. 25 ) s e m 20 i T l y = 34.43e-0.007x a t R² = 0.839 o T 15 f o % 10 ( y c n e u 5 q e r F 0 0 100 200 300 400 500 600 Time Between Departures (sec) Figure 3.17: Service Distribution for a Single Loader 3.8.5 Validation of Model and Results The mining operations in the north pit do not fit any distribution, and cannot be represented using mathematical equations. In the south pit, both the interarrival times of new trucks to the pit and the service rates of the loaders fit exponential distributions. Data from the mining operations in the south pit can be used as inputs for the queuing model created, since it fulfills the requirements of exponential arrival distributions and service rates. Not all mining operations will be able to be applied to the model, since they will not all have similarly distributed loading and interarrival rates, as evidenced by the north pit, which clearly does not meet these requirements. The south pit of the mine described operates with either two or three loaders in the pit depending on the shift and the haul trucks dump ore at the crusher and waste material at the dump site as 38
Virginia Tech
previously described. Figure 3.18 below is a queuing schematic of the haulage operations for the south pit. Figure 3.18: Queuing Schematic of Mine Haulage Route The queuing model developed can be applied to the pit operations of this mine, represented by the top half of the above schematic. The arrival and service distributions for the south pit operations have been confirmed to fit exponential distributions, so an (M/M/3) queuing model is appropriate for this application. Loaded haul trucks exiting the queuing system of the pit will either travel to the crusher or the waste dump before returning to the pit to be loaded again. Which dumping location a truck will utilize is dependent upon whether the loader filled the truck with ore or waste material, and varies according to the geology of the ore body in the pit and the cutoff grade the mine is using. A metric that includes this information would be necessary to expand the current queuing model to apply to the entire haulage system, and is beyond the scope of this project. 39
Virginia Tech
The loading rate and average arrival rates for each hour segment were entered into the queuing model, using an (M/M/3) model for the first five hours of the shift and an (M/M/2) model for the remainder, since the number of loaders in operation changed during the shift. Table 3.7 below contains the outputs generated by the queuing model, based on the inputs from Table 3.6. The model calculated the average number of trucks in the pit system (L), the number of trucks waiting for service (L ), the average amount of time trucks spent in the pit system (W), the q average amount of time trucks spent waiting for service (W ), and server utilization (ρ). q Table 3.7: Queuing Model Outputs for Hourly Data W W q Hour L L (hours) (hours) ρ (%) q 1 3.187 0.888 0.103 0.029 76.6 2 3.187 0.888 0.103 0.029 76.6 3 2.201 0.348 0.088 0.014 61.8 4 2.474 0.472 0.091 0.018 66.7 5 2.793 0.643 0.096 0.022 71.7 6 3.5 1.869 0.159 0.085 81.6 7 3.5 1.869 0.159 0.085 81.6 8 4.248 2.543 0.185 0.111 85.3 9 14.87 12.94 0.572 0.498 96.4 10 4.248 2.543 0.185 0.111 85.3 11 4.248 2.543 0.185 0.111 85.3 The shift was also analyzed as a whole, broken down into the segments with 3 and 2 loaders. The average arrival rates and service rates were calculated and used as inputs for the model. These results are shown below in Table 3.8. Table 3.8: Queuing Model Outputs for Entire Shift L L W W ρ θ q q 3 loaders 2.724 0.604 0.095 0.021 70.7 39 2 loaders 4.408 2.69 0.19 0.116 85.9 26.4 To see if the model’s outputs match the actual results, the expected number of trucks in the system, L, was compared to the actual number of trucks in the system for these timeframes. The predicted results were plotted vs. the actual results, as shown in Figure 3.19. 41
Virginia Tech
The line of best fit created in the previous graph was modified to force the line through the origin, since there can never be a negative number of trucks in the system. The resulting modified graph is shown below in Figure 3.21. 6 n y = 1.0177x i s k 5 R² = 0.6035 c u rr Tu 4 o f oH r r e be p 3 m m u Ne t ds y 2 eS t c i d 1 e r P 0 0 1 2 3 4 5 6 Actual Number of Trucks in System per Hour Figure 3.21: Predicted vs. Actual Number of Trucks in System, Modified The relationship between the predicted number of trucks in the system and the actual number of trucks in the system is very close to 1 to 1, indicating that the outputs of the (M/M/3) queuing model can accurately describe the state of the haulage system being modeled. 3.9 Analysis This queuing model is useful for analyzing the efficiency of mining haulage and loading operations for the configurations in which they are currently operating. The amount of time trucks spend waiting to be loaded, W , and the server utilization, ρ, are both indicators of how q efficiently the system is operating. The larger the values of W , the longer trucks are spending q idling waiting at the loaders, burning fuel without contributing to the haulage process. The server utilization indicates what proportion of operational time loaders are actually in use. Both of these values can be combined with costing data for the equipment in use to find out how much money is being spent on idling equipment. 43
Virginia Tech
For example, a pit system operating with two loaders, an arrival rate of 16 trucks per hour, and a service rate of 12 trucks per hour per loader is found to have a loader utilization of 66.7%, a system output of 23.5 trucks per hour, and an average of 0.0435 hours spent waiting in the queue per truck for each loading cycle. Since each truck passing through the system would potentially have to spend time waiting at the loader, the system output multiplied by the average time spent waiting in the queue is the average amount of time trucks are idling in the pit per hour. Over an eight hour shift, this comes to a combined total of 8.18 hours of truck idling time. Based on the loader utilization, each loader was not in use for 33.3% of the shift. This comes to a total of 5.34 hours of idle time between the two loaders for the eight hour period. This mine could be operating a pair of EX2600 hydraulic shovels with a fleet of CAT 793D haul trucks, which cost $421 per hour and $356 per hour respectively to operate (InfoMine). This comes to a total of $5,158.54 spent on idling equipment during one eight-hour shift. If the haulage operations were adjusted, either by changing the number of loaders operating or adjusting the fleet size, the new arrival rate that results can be used to run the model again, and see whether the changes made would be valuable to the system in terms of the cost to operate unnecessary equipment. If there are usually multiple trucks waiting for the loaders, as indicated by L , it would likely be q beneficial to decrease the fleet size to reduce the amount of time trucks are spending waiting to be loaded. Changes to the queuing model can be made by adjusting the arrival rate of new trucks to the system to see how the system would react to trucks arriving more or less frequently. While this is similar to comparing the effects of adding or removing trucks to the system, the amount of change in arrival rate caused by changing the fleet size will vary depending on the specific characteristics and layout of each mine. As the model currently exists, the effects of changes to fleet size can only be examined if the changes are actually made in the pit, the new inputs are determined, and the model is run again. This is due to the fact that the arrival rate, which is a necessary queuing input, is dependent upon more than just the number of trucks in the system. To determine an optimal fleet size for a given mine layout and loading configuration without running a full simulation, it may be more useful to use models involving stochastic simulation, such as Monte Carlo simulation to incorporate haul routes, travel times, and fleet sizes. This would allow various fleet sizes and configurations to be compared without having to make real world changes to acquire additional inputs for the 44
Virginia Tech
Chapter 4: Summary and Conclusion 4.1 Summary The haulage process undertaken by haul trucks in open pit mines can be represented as cyclic or network queues, or broken down into individual components which can each be treated as single or multichannel queues. In queuing notation, trucks are treated as customers in a system where loaders are the servers. Trucks arrive to be loaded and form a queue if the loaders are busy. An (M/M/c) queuing model was developed to model truck and shovel interactions within the pit. This model makes the assumption of exponentially distributed truck interarrival times and service times, and can be applied to operations with seven or fewer loaders. To apply this model the user must know the average arrival rate of new trucks to the system, λ, the number of loaders, and the average service rate per loader, μ. Based on these inputs, the model calculates several outputs describing system behavior. Table 4.1 below lists the outputs created by the model along with their associated units and descriptions. Table 4.1: Model Outputs Variable Units Description ρ % Loader Utilization W hours Time spent in system W hours Time spent in queue q L Number of trucks Number of trucks in system L Number of trucks Number of trucks in queue q θ Trucks per hour System output These outputs can be used to measure the efficiency of haulage operations based on their current configurations. If changes are made to the system, new values for the average interarrival times and service rates would need to be calculated so that the model could be run again to compare the efficiency of the new system to the values before changes were made. 46
Virginia Tech
4.2 Conclusion Queuing theory can be used to model truck and shovel behavior in open pit mines. The (M/M/c) model developed is consistent with the data from one open pit operation. Exponential interarrival times and exponential service times are consistent with the data from this mine, so the assumptions of the model are valid for some operations. The (M/M/c) model is capable of analyzing haulage systems as they currently exist and can be used to evaluate the efficiency of operations based on their current fleet sizes. This can also be combined with costing data for the equipment in use to find out how much money is being spent to operate idling equipment that is not directly contributing to production. As the model currently exists, the effects of changes to fleet size can only be examined if the changes are actually made in the pit, and the model is run again using new inputs, calculated after the changes had been made. This is due to the fact that the arrival rate, which is a necessary queuing input, is dependent upon more factors than just the number of trucks in the system. While queuing theory can be used to model haulage operations at some mine sites, it may not be the best or the easiest method to use for fleet analysis. Queuing theory can only be applied to mining operations where the arrival times of trucks to the pit and service times of the loaders can be fit to distributions. For operations that meet these requirements, inputs for the model must be obtained from active mining operations, and changes to the system can only be run through the model after these changes have been implemented in the field and used to obtain new inputs for the model. To determine an optimal fleet size for a given mine layout and loading configuration without running a full simulation, it may be more useful to use models involving stochastic simulation, such as Monte Carlo simulation, to incorporate haul routes, travel times, and fleet sizes. This would allow various fleet sizes and configurations to be compared without having to make real world changes to acquire additional inputs for the model, as would be necessary for the queuing model. This type of stochastic model could also be used in situations when queuing theory is not applicable, for example in mines where the loading operations do not fit the distributions necessary for queuing theory to be applied. The queuing model can analyze the efficiency of 47
Virginia Tech
Table A-5: Number of Trucks in System 1343073693 4 1343080167 5 Number 1343073843 1 1343080289 3 Time of Trucks 1343074143 3 1343080418 1 Stamp in System 1343074273 7 1343080590 2 1343067870 2 1343074408 4 1343080737 2 1343068012 5 1343074529 4 1343080887 3 1343068208 5 1343074663 3 1343081015 2 1343068337 5 1343074798 3 1343081045 4 1343068460 4 1343074927 4 1343081171 3 1343068587 4 1343075064 2 1343081309 4 1343068726 3 1343075187 3 1343081454 3 1343068872 2 1343075319 3 1343081591 3 1343069035 1 1343075448 2 1343081634 0 1343069181 3 1343075854 1 1343081907 3 1343069306 2 1343076032 3 1343082038 4 1343069451 4 1343076163 2 1343082180 3 1343069617 1 1343076299 2 1343082270 0 1343069762 1 1343076448 3 1343082300 0 1343069912 4 1343076598 3 1343082598 2 1343070038 4 1343076748 3 1343082721 2 1343070167 5 1343076888 4 1343082868 1 1343070297 4 1343077013 4 1343083011 3 1343070437 4 1343077136 3 1343083139 6 1343070568 3 1343077270 3 1343083263 6 1343070691 2 1343077339 0 1343083392 5 1343070956 2 1343077564 1 1343083524 5 1343071077 2 1343077654 0 1343083648 2 1343071307 2 1343077910 2 1343083780 2 1343071432 4 1343078043 3 1343083920 2 1343071555 4 1343078168 4 1343084049 2 1343071718 4 1343078309 4 1343084207 1 1343071839 4 1343078430 3 1343084357 1 1343071967 4 1343078699 2 1343084507 2 1343072103 2 1343078848 5 1343084641 2 1343072232 3 1343078969 5 1343084782 2 1343072358 3 1343079095 4 1343084996 5 1343072508 4 1343079239 2 1343085118 8 1343072637 3 1343079365 3 1343085243 5 1343072817 2 1343079490 1 1343085371 4 1343072938 2 1343079620 1 1343085498 5 1343073296 3 1343079770 2 1343085629 5 1343073429 3 1343079897 2 1343085751 3 1343073558 3 1343085880 2 1343080020 2 69
Virginia Tech
1343086007 3 1343091841 3 1343097553 5 1343086157 2 1343091965 4 1343097675 5 1343086300 1 1343092087 6 1343097801 5 1343086450 1 1343092227 4 1343097933 3 1343086600 2 1343092348 4 1343098063 2 1343086748 2 1343092472 1 1343098191 2 1343086888 5 1343092603 5 1343098333 1 1343087011 7 1343092729 5 1343098477 2 1343087142 7 1343092860 4 1343098558 3 1343087263 7 1343092982 3 1343098686 3 1343087385 7 1343093114 5 1343098817 3 1343087515 5 1343093250 3 1343098952 1 1343087636 5 1343093373 3 1343099078 3 1343087759 4 1343093504 4 1343099168 4 1343087905 3 1343093643 4 1343099289 3 1343088029 4 1343093767 4 1343099415 2 1343088158 7 1343093895 2 1343099538 2 1343088308 3 1343094045 2 1343099688 2 1343088438 4 1343094185 3 1343099782 2 1343088569 4 1343094387 3 1343099893 3 1343088699 5 1343094619 3 1343100019 3 1343088820 4 1343094766 4 1343100199 1 1343088959 4 1343094889 5 1343100289 3 1343089086 5 1343095011 6 1343100389 7 1343089212 3 1343095141 7 1343100509 7 1343089336 2 1343095263 6 1343100632 5 1343089486 1 1343095394 5 1343100768 6 1343089677 1 1343095514 4 1343100899 5 1343089814 3 1343095637 3 1343101022 2 1343089984 4 1343095761 2 1343101143 4 1343090126 4 1343095911 2 1343101264 5 1343090247 4 1343095955 0 1343101389 5 1343090396 5 1343096115 1 1343101516 4 1343090517 3 1343096247 2 1343101639 5 1343090679 4 1343096398 2 1343101762 3 1343090801 3 1343096535 3 1343101904 3 1343090981 1 1343096668 4 1343102002 2 1343091131 3 1343096807 3 1343102122 3 1343091260 2 1343096947 4 1343102270 4 1343091320 0 1343097077 4 1343102377 4 1343091452 1 1343097211 3 1343102498 4 1343091577 3 1343097301 3 1343102609 4 1343091704 4 1343097423 5 70
Virginia Tech
1343102870 5 1343102870 5 1343102738 4 1343102990 5 1343102990 5 1343108191 7 1343103110 4 1343103110 4 1343108315 6 1343103230 3 1343103230 3 1343108435 6 1343103359 2 1343103359 2 1343108561 5 1343103500 4 1343103500 4 1343108675 6 1343103603 4 1343103603 4 1343108801 5 1343103724 4 1343103724 4 1343108926 6 1343103843 5 1343103843 5 1343109047 5 1343103975 5 1343103975 5 1343109174 6 1343104084 4 1343104084 4 1343109294 5 1343104204 4 1343104204 4 1343109429 4 1343104330 3 1343104330 3 1343109550 4 1343104455 3 1343104455 3 1343109740 2 1343104576 3 1343104576 3 1343104696 3 1343104696 3 1343104817 3 1343104817 3 1343104927 3 1343104927 3 1343105047 4 1343105047 4 1343105178 3 1343105178 3 1343105294 5 1343105294 5 1343105414 4 1343105414 4 1343105571 2 1343105571 2 1343105684 5 1343105684 5 1343105794 4 1343105794 4 1343105915 4 1343105915 4 1343106040 5 1343106040 5 1343106165 5 1343106165 5 1343106305 4 1343106305 4 1343106433 4 1343106433 4 1343106564 4 1343106564 4 1343106701 3 1343106701 3 1343106834 3 1343106834 3 1343106969 2 1343106969 2 1343107089 1 1343107089 1 1343107220 2 1343107220 2 1343107329 2 1343107329 2 1343107449 5 1343107449 5 1343107564 6 1343107564 6 1343107688 6 1343107688 6 1343107818 4 1343107818 4 1343107938 5 1343107938 5 1343108071 5 71
Virginia Tech
DPM Monitoring in Underground Metal/Nonmetal Mines E. McCullough !, L. Rojas-Mendoza !, E. Sarver !,∗ ! Virginia Polytechnic Institute and State University, Department of Mining and Minerals, Blacksburg, VA 24060, USA The metal and nonmetal mining industries face increasingly stringent regulations regarding worker exposures to airborne particulates, including diesel particulate matter (DPM). Although significant progress has been achieved in reducing DPM exposures, mine operators still struggle to comply under a variety of conditions – particularly in large-opening mines where ventilation is challenging. One major issue in such environments is the inability to easily monitor DPM trends over long periods of time to determine factors influencing its buildup in areas of interest, as well as its response to mitigation strategies. At present, DPM measurements are limited to the NIOSH 5040 method (i.e., filter collection and external analysis) and the handheld Airtec DPM monitor (FLIR Systems, Inc., Albuquerque, NM), which provides quasi-real time data over relatively short time periods. To transform the Airtec device to an autonomous area-monitoring unit, its basic components were modified by Nomadics, Inc. under NIOSH contract number 200-2010-36901. This resulted in a prototyped unit called the Airwatch DPM monitor, which does not require frequent filter replacement or battery re-charging; networking capabilities to connect multiple monitors were also achieved. While the prototyped monitor was successfully lab tested, field-testing was limited to just a few days underground. Further testing is needed to fully evaluate the monitor and ready it for commercial availability. Under a new Capacity Building in Ventilation project at Virginia Tech (CDC/NIOSH contract no. 200-2014-59646), we aim to demonstrate the capability of the Airwatch DPM monitor in high-priority areas of a stone mine over relatively long-term periods – and then use the monitors to investigate DPM response to ventilation conditions. Keywords: Diesel Particular Matter, Metal/non-Metal, Monitoring 1. Introduction create synergies that are harmful to human health. DPM exposure in U.S. underground mines is regulated by the Diesel exhaust represents a ubiquitous occupational Mine Safety and Health Administration (MSHA). hazard in underground mine environments. The exhaust MSHA issued its Final Rule on DPM metal and is a highly complex mixture of diesel particulate matter nonmetal mine environments under 30 CFR Part 57 in (DPM) and hydrocarbon gasses [1]. Since there is no 2008, mandating that a miner’s personal exposure limit technologically proven way to measure DPM directly, it (PEL) to DPM cannot exceed 160 μg/m3 of TC during an is often quantified using elemental carbon (EC) eight-hour work shift. MSHA requires that the standard measurements. [2]. Elemental carbon accounts for 23- National Institute for Occupational Safety and Health 100% of DPM, and is not generally affected by (NIOSH) 5040 Method be used to measure DPM environmental interferences [3,4]. Historically, total exposures to determine compliance [4]. This method carbon (TC) analysis was used which typically employs a thermo-optical technique to analyze carbon comprises over 80% of DPM [1]. TC is defined as the particles in air samples collected on a 37 mm quartz summation of elemental carbon and organic carbon fiber filter. It should be noted that this technique (OC). However, cigarette smoke and mineral dust can quantitates TC (by direct quantitation of EC and OC) or interfere with TC readings, which has sometimes caused requires a site-specific conversion factor to convert EC DPM measurements to report artificially high values [3]. into a TC equivalent [6,7]. These values should then be DPM has a variable particulate size distribution. adjusted to an eight-hour time-weighted average. Particles are created within the micron and sub-micron scales [5]. Idealized size distribution is trimodal and related lognormally [1]. The smallest particulate mode is 1.1 DPM and Human Health called the nuclei mode, which has particles diameters Underground miners are disproportionally exposed ranging from about 0.005 to 0.05μm. This mode to DPM-related occupational hazards because heavy represents less than 20% of DPM by mass, but greater diesel-powered equipment runs regularly in tight spaces, than 90% of DPM by particle count [1]. Most DPM with variable ventilation conditions. In spaces where particulate mass is represented in the accumulation airflow is limited, DPM does not disperse well, and due mode, with particle diameters on the order of about 0.05 to its size can remain suspended in the air. Reported to 1.0μm. The coarse mode represents particles with DPM concentrations in underground mine settings can diameters greater than 1μm. All particles sizes are be on the order of ten times higher than levels found in capable of suspension in air, and DPM is prone to some other industrial settings, and more than 100 times clustering and reacting with other atmospheric higher than levels observed in urban areas [1]. NIOSH components while suspended [1]. Such reactions may _______________________________________________________________________________ 1 *Corresponding author: [email protected]
Virginia Tech
estimated in 2008 that 34,000 underground miners were carbon dioxide is reduced to methane, which is measured at risk of exposure to DPM [1].Human exposure to DPM by FID. Since some char is produced by the OC during presents many potential health complications. NIOSH the first phase, which will oxidize in the second phase, estimated in 2008 that 34,000 underground miners were the analyzer must also determine how much methane in at risk of exposure to DPM [1]. Approximately 60,000 the second phase is attributable to OC vs. EC. For this, it deaths in the United States per year are attributed to fine contains a pulsed diode laser and photodetector to particulate exposure. Of these deaths, 21,000 are monitor the sample for transmission of light. Effectively, believed to be from DPM in particular [5]. The Clean once the transmittance is seen to increase (i.e., char Air Task Force reports that the estimated annual production in first phase) and then decrease back to its economic cost of particulate-related illness and death in original value (i.e., char oxidation in the second phase), the USA was $139 billion [8]. Clearly, the social and all subsequent methane production is attributed to EC. economic impact caused by particulate-related illnesses For this optical analysis, the instrument requires a should not go unaddressed. portion of the sample filter wider than the diameter of the laser [10,11]. To collect DPM samples for analysis by the 5040 2. DPM Monitoring method, a field sampling apparatus is used which As noted above, for demonstrating compliance with consists of a small air pump, and a 37 mm quartz fiber DPM exposure limits in underground metal and filter that is held inside a plastic cassette. Often a device nonmetal mines, the NIOSH 5040 method must be used. for removing relatively large particles from the DPM- While this method provides an accurate measurement of laden airflow is also placed inline before the sample EC and OC concentrations (which can be translated into filter; generally, the oversized particles (i.e., > 0.8μm) TC as proxy for DPM) over the short duration of sample are removed via an impactor filter. By using a size- collection, it is intended for determining personal selective sampler, airborne dust (i.e., which may include exposures. Thus, it does not provide the ability to easily carbon-containing particles) is prevented from collecting monitor DPM over long periods of time. For on the DPM filter and creating a sample matrix understanding DPM trends in the context of mine interference for the analytical method [2]. When the operation, and therefore mitigating exposure risks, impactor becomes full, DPM capture is no longer monitoring capabilities are indeed critical. Recognizing efficient and the impactor must be replaced. SKC this fact, a handheld, quasi real-time DPM monitor manufactures an all-in-one DPM cassette, which called the Airtec (FLIR Systems, Inc., Albuquerque, contains an impactor and quartz fiber DPM filter [12]. In NM) was developed in collaboration with NIOSH. The very dusty environments, a cyclone may also be placed Airtec is now commercially available as an engineering inline before the sampling cassette to exclude relatively tool for mine operators. Another device, the Airwatch, large (i.e., > 5μm) particles before air reaches the has recently been prototyped. It is intended to meet the impactor. need for autonomous area monitoring, but is not yet In an earlier design, the SKC DPM cassette was ready for commercialization. observed by Noll et al. to be problematic [2]. The following sections describe these three DPM Specifically, DPM deposition on the filters was not monitoring options for underground metal and nonmetal uniform in regards to the surface area (i.e., surface areas mines, and their key characteristics are summarized in over which DPM deposited were irregular and varied Table 1. between cassettes.) Uniform deposition is critical for accurate calculation of aerosol EC, and then TC, concentrations since only a fraction of the filter is analyzed and must be assumed representative: the 5040- 2.1 NIOSH 5040 Method quantitated EC and TC masses are effectively converted The most up to date version of the NIOSH 5040 to concentration values based on the fraction of sample method was published in 2003 [6]. The method surface area analyzed, the sampling time and the incorporates thermo-optical analysis because of its flowrate [2]. Once modification was made to improve selectivity and flexibility (e.g. can run manually and is the cassette design, they were determined to provide programmable). The instrument was specifically reliable measurements in laboratory and field developed for analysis of carbon-based aerosols (e.g., environments [2]. DPM) and is manufactured by Sunset Laboratories, Inc. Following promulgation of DPM rules in (Tigard, OR). In general, the thermal analysis is underground mines, the NIOSH 5040 method has completed in two phases. First, the sample is placed in provided a means for gathering a wealth of information, an oven and heated to 850°C in inert atmosphere, particularly about personal exposures; and improvements causing the OC to become catalytically oxidized. This in the mine environment have undoubtedly resulted. forms carbon dioxide, which can then be reduced to However, this method, it is not a particularly practical methane. The methane is then measured using a flame engineering tool for mine operators aiming to conduct ionization detector (FID) [9]. Next, the sample is re- routine monitoring of DPM. Collected samples must be heated up to about 900°C in an oxygen-rich atmosphere, mailed to only a handful of equipped laboratories to such that the EC is also oxidized; again, the resulting 2
Virginia Tech
perform the required analysis, which makes collecting Functionally, the Airtec monitor has three main results quite time consuming [5] – not to mention parts: a small air pump, a plastic cassette that holds a expensive. One test costs approximately $100 for filter onto which DPM is collected, and a laser and supplies and analysis, and this figure does not include sensor pair. As the DPM is collected, the laser is directed mine labor [5]. Moreover, the lag period between sample toward the filter and the sensor detects how much of the collection and analysis makes it difficult to both laser becomes blocked by EC (a primary component of recognize the conditions leading to overexposures and to DPM). The laser becomes increasingly “extinct” as more gage the effectiveness of attempted DPM control DPM is collected, and thus an effective measurement of mechanisms. EC is obtained. As is often the case with filter samples collected for the 5040 method, the Airtec can also use an Beyond the issue with significant lag time between impactor to keep dust from entering the device and sample collection and result reporting, 5040 method depositing on the filter. (Previously, a “sharp cut” results are also limited because they are associated with cyclone was also commercially available that could bulk samples (i.e., the final result is a time-weighted effectively remove particles > 0.8μm, but this model of average concentration). This means that particular time cyclone is not being manufactured anymore.) segments within the sampling period cannot be isolated [5]. It would be helpful for mine operators to determine While the Airtec has afforded significant monitoring when peak exposures of DPM occur, ideally in real time, capabilities to mine operators, a new device developed so that they can adjust ventilation controls accordingly. under NIOSH contract number 200-2010-36901 called the Airwatch DPM Monitor may provide even more utility in the way of long-term area monitoring. The 2.2 In-mine DPM Monitoring Airwatch is currently in the prototype and demonstration phases. It is technologically similar to the Airtec, but To address the need for in-mine monitoring, the includes several modifications that allow the device to Airtec DPM Monitor was developed. It is a handheld operate autonomously over long periods of time. Most device and displays EC concentrations on a running 15- importantly, it can run on mine power (i.e., instead of minute average – quasi real-time. The instrument meets batteries) and does not require frequent user attention or NIOSH accuracy criteria and provides results with no maintenance. The latter is possible because the Airwatch statistical difference from the 5040 method [13]. It uses a self-advancing filter tape on which the DPM is measures EC using a laser extinction technique, which collected [14]. The tape is similar in form to an audio or works because EC concentrations are related to laser VHS cassette tape, wherein the clean filter media is absorption [13]. The laser extinction is measured directly rolled around one cylinder from one end and attached to on a filter as it collects DPM, which is ideal for a small, another cylinder on the other end. DPM is collected via portable device. an air pump and deposited on a small area of tape Mine operators may use the Airtec to “spot” check between the two cylinders. Here, a laser and sensor pair areas of interest in order to identify high DPM similar to those used in the Airtec units is employed to contributing sources, and also to evaluate personal track laser extinction, which can again be related to EC exposures to DPM. It has proven particularly useful for collected on the filter tape. When a given filter area is monitoring DPM in equipment cabs because it is not completely used (i.e., laser extinction is sufficiently influenced by instantaneous pressure changes, such as high), the tape progresses forward to expose a clean area those caused by opening and closing doors [7]. of filter to the laser and sensor. The exact life of this Researchers at NIOSH have observed that the Airtec is filter tape depends on the sampling environment and sensitive to cigarette smoke and will register it as a DPM monitoring setup (i.e., concentration of DPM in the air, reading [7], and so users should be aware of this and frequency at which the Airwatch is programmed to potential for false-positive readings and not smoke while collect data.) To avoid interference in laser extinction the monitor is being used. Being able to monitor DPM in from dust particles, a sharp-cut cyclone is employed to near real-time allows mine operators to identify when prevent dust particles from depositing on the filter. As levels are nearing compliance limits, as well as evaluate opposed to an impactor for this purpose, the cyclone the effectiveness of engineering controls to abate it. does not need frequent replacement 3
Virginia Tech
Table 1. DPM Monitoring Options Method Analytical Primary Availability Sampling Unit Technique Applications of Results 5040 Method Thermo-optical Personal Lag time Portable with FID exposures (days to (quantitates EC (required for weeks) and OC) compliance), short-term area monitoring Airtec Monitor Laser extinction Personal Quasi real- Portable exposures, time (quantitates EC) short-term area monitoring, spot-checking Airwatch Laser extinction Long-term, Quasi real- Stationary Monitor (quantitates EC) autonomous time area monitoring, networking capabilities In its current design, the Airwatch can be DPM control – certainly far from ideal. Some mines do programmed to transmit data to remote monitoring not even have forced-ventilation systems in place. cations via hardwires (i.e., Ethernet or 4-20mA). Since a Rather, they depend on natural ventilation, which is current-based signal is used, the signal transmitted does uncontrolled and unreliable due to seasonal variations in not degrade over distance. Where available, mining temperatures that drive the movement of air [16]. Only a operations could certainly benefit from real-time DPM few research studies have been conducted regarding information that can be transferred quickly over wireless DPM in large-opening mines (e.g., see 16-18), but it is networks, and this capability is also envisioned for the clear that effective, data-driven ventilation Airwatch monitor. Long-term, operators might be able to improvements require enhanced DPM monitoring centrally process data and automatically incorporate networks. them into other systems or decision-making schemes to alter mine parameters, such as ventilation [15]. Although the Airwatch has been successfully tested in the 3.1 Project and Task Description laboratory, extensive field testing has not been Two main objectives related to DPM monitoring conducted to date and ventilation have been established for this project: 1) to demonstrate the capability of the prototyped Airwatch devices to autonomously monitor DPM in high-priority 3. Research Approach areas of a study mine and 2) to determine DPM response Under a new Capacity Building in Ventilation to ventilation conditions in various areas of the mine. project sponsored by CDC/NIOSH through the Office of Work began during late 2014 and will be developed over Mine Safety and Health Research (contract no. 200- the remainder of the five-year project. Table 2 displays 2014-59646), the Airwatch technology will be the tasks that will be undertaken in order to fulfill the demonstrated in an underground mining environment, project objectives. and ultimately employed to monitor DPM under 3.3 Progress to Date different ventilation scenarios. Work is proceeding in cooperation with an industry The focus environment for this project is the large- partner (an underground stone mine) and to date, there opening mine. These mines experience airflow quantities has been progress towards Tasks 1 and 2. For Task 1, so low that they are sometimes immeasurable with due to the very low air velocities in the study mine, it conventional equipment. In many, ventilation techniques will be necessary to use an ultrasonic anemometer to are currently being employed to control DPM but they collect accurate data. A UA6 (TSI Incorporated, are still highly experimental, using trial-and-error Shoreview, MN) is currently being lab-tested and will be approaches to gage effectiveness [16]. These are notably employed for spot ventilation surveys. The ventilation costly, time-consuming, and less than optimal in terms of 4
Virginia Tech
data will be collected in concert with DPM data using 4. Impact the Airtec monitor. Survey points will be chosen Despite significant improvements over the past together with the mine operator. A customized DPM couple of decades, DPM is still a significant health cassette, designed and 3D-printed by NIOSH, will be concern for underground mine workers. Efforts to further used to reduce the DPM deposition area on the filters. reduce exposure risks require enhanced monitoring tools. This will effectively reduce the total surface area of the Demonstration of the efficacy and utility of the Airwatch DPM filter so that the Airtec unit is much more sensitive DPM monitor is expected to aid in progress toward its and can provide faster EC readings (versus the 15- commercial availability. Ultimately, this tool should minute minimum sampling time that is normally provide mine operators a means of tracking DPM with required). other environmental and operational conditions (e.g., For Task 2, upgraded Airwatch monitors have been ventilation) such that worker health can be adequately built (on a separate NIOSH contract). The new units protected while optimizing other factors (e.g., energy have been modified to make them more rugged and user usage, production, maintenance schedules, etc.). friendly. Comparative measurements are planned Beyond theses expected research outcomes of the whereby the Airwatch and Airtec units will be employed Capacity Building in Ventilation project described here, simultaneously. Moreover, work is currently underway development of expertise in the areas of mining to design self-contained monitoring stations that couple a engineering and occupational health is a primary 2-axis ultrasonic anemometer that logs data objective. The project team includes multiple student cooperatively with an Airwatch unit to track air velocity. researchers. Their current work will add to the scientific This future work will help determine how DPM responds literature surrounding DPM monitoring and control; and to ventilation controls. Due to environmental conditions, the knowledge and experience they gain during this the datalogger should be stowed inside some type of project will soon contribute to the broader mining moisture-proof enclosure to protect it from atmospheric community. conditions. Table 2: Work tasks related to DPM monitoring and ventilation response Task Description Initial Collection of Mine data • Become familiar with operation and environmental conditions at the mine of (Year 1) study. • Conduct ventilation and DPM surveys by using: o Airtec real Time Monitors o Ultrasonic Anemometers Receipt and lab resting of • Receipt of prototyped autonomous DPM monitoring units from NIOSH prototyped autonomous DPM • Becoming familiar with the units’ design and operational requirements. monitors (Years 1-2) • Units will be lab tested to confirm they are functioning properly o Capability to measure continually o Capability to log data o Accuracy and consistency amongst all units output. • Verification of autonomous DPM monitors’ readiness for use underground. Field-testing of autonomous • Determining installation locations together with the mine operator. DPM monitors (Years 2-4) o High priority areas for monitoring of DPM o Safe and reliable for the operation of the testing equipment. • Installation of the prototyped monitors at the field site • Ensuring proper functioning in the mine environment and capability to record DPM data for long periods of time Monitoring DPM responses to • Tracking DPM response to different ventilation scenarios. specific ventilation (Years 4-5) • Scenarios will be determined in conjunction with the mine operator 5
Virginia Tech
A M E A ETHOD FOR VALUATING THE PPLICATION V F D C OF ARIABLE REQUENCY RIVES WITH OAL M V F INE ENTILATION ANS Tyson M. Murphy ABSTRACT The adjustable-pitch setting on an axial-flow fan is the most common method of controlling airflow for primary coal mine ventilation. With this method, the fan operates at a constant speed dictated by its motor design. The angles of the blades are adjusted to change the amount of airflow and pressure to meet ventilation requirements. Typically, the fan does not operate at its optimum efficiency, which only occurs in a narrow band of air pressures and quantities. The use of variable frequency drives (VFDs), which control fan speed, provides a solution to this problem. VFDs are already used in various similar applications such as pumping and building ventilation. New technology now enables efficient VFD operation in medium voltage (2,300 – 6,900 V) fan applications. The primary benefit of a variable frequency drive is that it allows motors to operate at reduced speeds, and thus at a lower power, without a loss of torque. VFDs also allow for efficient operation over the entire life of the fan. The technical considerations of using a VFD are presented in this work, along with a method for choosing and modeling a variable speed fan to achieve maximum energy savings. As a part of this research, a spreadsheet program was developed that will calculate the optimum fan operating speed based on given fan data and specified operating conditions. A representative room and pillar coal mine is modeled to illustrate the selection and modeling process and as an example of the economic implications of using a VFD. The use of VFDs is shown to potentially yield large energy savings by increasing the fan efficiency over the life of the mine. Although there are definite power savings while using variable speed fans, the magnitude of these savings is specific to an individual mine and the operating conditions encountered. The determination of whether the use of VFDs is economically feasible requires analysis for the specific mine and its operating conditions. This work provides the background and a method for such an evaluation.
Virginia Tech
CHAPTER 1: INTRODUCTION 1.1 Problem Statement Primary mine ventilation fans provide necessary airflow and pressure to properly circulate air in the working areas of the mine. During mining, as the size of the mine and mine resistance changes, ventilation requirements will vary as changing airflows are required to maintain a safe mining environment. Usually, the requirements are calculated for different points over the projected mine life, and a fan is chosen that is capable of operating at all of these points over the 15-20 year life of the fan. Missing in this process is a method for dealing with the decrease in fan efficiency at operating requirements that are lower than what the fan is optimally designed for. The most common primary mine fan is the axial flow type. This type of fan traditionally operates at a fixed speed based on motor design and power supplied to the fan. The power and speed are generally constant for a given fan design. Currently, the most common method of varying the airflow and head of an axial flow fan, in response to the changing conditions of the mine, is to change the pitch of the fan blades (Hartman, et al., 1997). Fan curves are created based on multiple pitch angles for each fan, and a fan is selected that allows for the highest efficiency at changing pitches for the life of the fan. This method of fan operation results in inefficiencies during the life of the mine. Most often, a mine will operate a fan at a higher airflow than necessary during early mining, simply because it is more efficient than operating the fan at a lower airflow. Nearing the end of mining operations, the fan may be operated near 100% of its capabilities to meet the requirements. In all but a narrow range of airflows and pressures, the fan does not operate at its optimum efficiency. In addition to the inefficiencies associated with providing adequate airflow, changing the airflow can be an inconvenience to mine operators. Older fans need to be shut down to perform pitch adjustments, while more modern fans can be changed during operation. Regulators are also used to restrict airflow by diverting intake air into exhaust airways before it reaches the faces. Invariably, this results in unused fresh air that is exhausted from the mine. 1
Virginia Tech
1.2 Proposed Solution Variable frequency drives (VFDs) are one solution to the inefficiencies of current fan operation. VFDs are already used in various similar applications such as pumping and building ventilation. In mining, VFDs have been used in belt haulage systems, continuous miners, and trams. The benefit of a variable frequency drive is that it can allow motors to run at various speeds, without a loss of torque. The speed of a motor is based on the frequency of the power supplied and the design of the motor. To change the speed, either a physical change in the motor construction or a change in electrical frequency is required. The torque of a motor is determined by both its voltage and frequency, and a motor is rated based on a fixed ratio of these two factors. A VFD can supply power with the proper frequency and voltage/frequency ratio to produce different speeds while maintaining a constant torque in the motor. The ability to change the speed of ventilation fans is advantageous in controlling the airflow and pressure in a mine. There are many advantages to this approach of controlling airflow. If a VFD is used to control fan speed, energy savings can be realized by operating a fan at a point that meets the ventilation requirements while maintaining high fan efficiency throughout the life of the fan. The use of VFDs also provides flexibility in mine operations by potentially allowing the fan to be adjusted as needed or “on the fly” during mining. 1.3 Scope of Research This research shows the possible benefits of using variable frequency drives in mine fan applications. Technical requirements of ventilation, VFDs, motors, and fans are reviewed to determine the feasibility of installing and using VFDs for mine fan applications. A simple coal mine was designed and modeled to perform a ventilation analysis that incorporates variable speed fans. It is then used to develop and illustrate a method for determining the appropriate reduced speed fan settings to achieve optimum operating conditions. Also of importance are the economic benefits of using a VFD to control fan speed. Although the economics are specific to a single mining operation and its operating conditions, the example mine is used to illustrate some of the trends and issues that are likely to be present. 2
Virginia Tech
CHAPTER 2: LITERATURE REVIEW 2.1 AC Motors and Drives 2.1.1 Induction Motor Principles AC squirrel-cage induction motors are the most commonly used motors in industry today because of their simple construction, durability, and low cost. As with all induction motors, the basic components of a squirrel-cage induction motor are the stator (stationary winding) and rotor (rotating winding). Instead of an actual winding, a squirrel-cage rotor is simply constructed of longitudinal copper bars connected at their ends by copper shorting rings, as shown in Figure 2.1, hence the name “squirrel-cage.” The entire copper cage is imbedded in a cylindrical magnetic core. Figure 2.1 – Simple Squirrel Cage Induction Rotor (Luttrell 2005) When balanced three phase voltages are applied to the windings of the stator, the resulting currents in the windings produce a magnetic field. The speed of this rotating field is referred to as the synchronous speed, n (rpm), and is a function of the electrical sync frequency of the applied voltage, f (Hz), and the number of poles in the stator, p, as e given by the following equation: 120f n = e (1) sync p Lines of flux, produced by the rotating magnetic field, cut the copper bars of the rotor, thus inducing current in the rotor bars. The interaction between the stator’s magnetic field and the rotor’s currents results in rotational torque. The rotor then accelerates, with its terminal speed approaching that of the magnetic field. However, the rotor speed can never reach the synchronous speed. If this occurred, the rotor would be traveling at the same speed as the magnetic field and the flux from the magnetic field would not cut the rotor bars. Therefore, no currents would be induced in the rotor, and no rotational torque 3
Virginia Tech
would be developed. Because of these effects, the mechanical (rotor) speed of the motor must always be less than the synchronous speed of the magnetic field to maintain rotational torque. The speed differential between the synchronous speed, n , and the mechanical speed, sync n , is defined as a percentage of the synchronous speed, and is referred to as slip, s, given m by the following equation: n −n s = sync m ×100% (2) n sysc As an example, consider an eight-pole motor operating with a rated slip of 2%. Assuming a power line frequency of 60 Hz, the synchronous speed of the motor is 120f 120×60 n = e = =900rpm sync P 8 The mechanical speed of this motor is n = n (1−s)=900(1−0.02)=882rpm m sync An induction motor operates at relatively constant speed. A typical speed-torque characteristic for an induction motor, along with the load torque for a mine ventilation fan is shown in Figure 2.2(a). As long as the motor torque exceeds the load torque of the fan, the fan will accelerate until the two curves intersect. This point of intersection becomes the operating point of the motor. Induction motors operate at a relatively constant speed with slight variations depending on the load torque, which is a desirable characteristic for a ventilation fan. A significant increase in torque will result in increased slip, and thus a small change in speed (Figure 2.2(b)). If for some reason the load increases, the motor only slows slightly. Since the synchronous speed of the magnetic field remains constant, more lines of flux cut the rotor bars and increase the motor current to accommodate the required increase in torque. An increase in slip thus causes increased current as well as increased torque. It is because of this relationship that high startup currents are present when starting a large motor, from zero rpm to rated speed, and are sometimes as high as 6 to 10 times the operating current (Beaty and Fink 1987). 4
Virginia Tech
Motor Profile Fan Load Profile euqroT Motor Profile Operating Torque Speed n m n sync euqroT ΔT Speed Δn (a) (b) Figure 2.2 – Speed-Torque Profiles In order to change the speed of an induction motor, it is necessary to either change the electrical frequency or the number of poles in the motor (Equation 1). Motors require special types of windings with a set of external relays for changing poles. Also, only discrete changes in speed can be achieved with this method. For example, a motor with a synchronous speed of 1200 rpm can be slowed to 900 rpm if the number of poles is increased from six to eight, but speeds between these values can not be achieved. As a result, the technique of changing the number of poles (and thus how the motor is wound) is now obsolete (Chapman 2002), and changing the electrical frequency is the preferred method for varying speed. An important consideration when varying the speed of a motor is to maintain the same torque characteristics of the motor. Torque is proportional to the magnetic flux density in the motor air gap, which is proportional to the ratio of voltage and frequency, and is determined by the motor design. To maintain a constant flux, and thus constant torque characteristics at varying speed, voltage must also be varied to maintain a constant ratio of voltage and frequency. If the voltage is not de-rated as frequency drops, the steel in the core of the motor will saturate, and the magnetization current in the motor will increase and become excessive (Chapman 2002). Equation 3 describes this relationship where V is in Volts, and f is in Hz. Figure 2.3 shows the voltage and frequency ratios for different motor voltage ratings. V =c (3) f 5
Virginia Tech
2.1.2 Variable Frequency Drive Principles Variable frequency drives (VFDs), also referred to as variable speed drives and adjustable speed drives, input line power and output a reduced voltage and frequency supply to the motor. VFDs consist of three major components, as shown in Figure 2.4 – a rectifier/converter to convert AC to DC voltage, an intermediate DC link, and an inverter that outputs a simulated sinusoidal AC voltage from the controlled DC voltage. VFDs use a non-alternating DC voltage internally because it is easier to generate an output waveform (Turkel 1995). Additional input transformers and output filters can be included depending on the drive configuration and design. There are a variety of different ways that these functions are accomplished, but the same basic configuration is used. M DC Link Rectifier Inverter Figure 2.4 – VFD Components The technology used in VFDs has changed greatly over the past 30-40 years, and is now at a point where the advantages outweigh the disadvantages for use in medium voltage applications. High cost and reliability problems, as well as issues of input and output power quality that have prevented the widespread use of medium voltage drives have been resolved (Giesecke and Osman 1999). Giesecke and Osman (1999) also provide what they refer to as the systematic evolution of VFDs and the changing technology that has made VFDs feasible. Advances in the areas of semiconductor switching devices have, in particular, made the use of these drives possible in medium voltage applications. Manufacturers have also embraced this technology, evolving from the approach in the early 1990’s that the drive had to be perfectly matched to the motor by the same manufacturer (Huffman 1990) to manufacturers that will now make VFDs that are capable of retrofit on any AC motor. A listing of VFD topologies is shown below (Morris and Armitage), with a brief listing of advantages and disadvantages with regard to medium voltage applications. The topology of a VFD is the electrical configuration of the drive, which ultimately determines the overall function of the drive. Motor control platforms, which are a part of the converter 7
Virginia Tech
section of the drive, determine how energy is delivered to the motor, and control the speed and torque delivered (Morris and Armitage). Emphasis is placed on topologies and motor control of medium voltage systems for fan and pump applications, since that is the focus of this research. Examples of Drive Topologies: - Voltage Source Inverter (VSI) – Advantages: Can retrofit on existing motors without derating, full torque at low speeds, input power factor near unity, low network harmonics, and high efficiency. - Current Source Inverter (CSI) – Advantages: Cost effective, four quadrant operation. Disadvantages: Continuous low speed operation not possible, inconsistent power factor over operating range, higher cost, larger drive, and additional losses. - Load Commutated Inverter (LCI) – Advantages: Single Motor Drive for medium and high power ratings, wide speed and power range, inherent 4- quadrant operation. Disadvantages: Not for use on squirrel cage induction motors. There are two primary motor control platforms used in VFD applications. The first is Pulse Width Modulation (PWM). This platform uses a pulse width modulator to simulate a sine wave, with the voltage and frequency determining the torque and speed. The output is a series of pulses of varying widths. The width of each pulse controls the magnitude of the voltage and the frequency of the changing polarity of the pulses control the frequency of the power delivered (Yaskawa Electric America). Figure 2.5 shows a PWM line diagram with the corresponding desired waveform. The ongoing development of power devices and increased use has made PWM VSI converters relatively inexpensive (Shakweh 2000). 8
Virginia Tech
time egatloV Desired waveform PWM waveform Figure 2.5 – PWM waveform A few semi-conductor switching technologies that exist in VFD applications are: - GTO – Gate Turn Off Thyristor - IGBT – Insulated Gate Bipolar Transistor - SGCT – Symmetrical Gate Commutated Thyristor - IGCT – Integrated Gate Commutated Thyristor GTOs were initially used in VFDs, but were not successful due to their expense and complexity. IGBT technology has been significantly improved for use in medium voltage applications and is a popular choice of technology for VFD manufacturers. According to ABB, who pioneered the IGCT, their technology is ideal for medium voltage drives primarily due to faster switching and lower power dissipation, resulting in its high efficiency and reliability, and reduced size and cost compared to IGBTs (ABB). Regardless of manufacturers’ claims that their technology is superior to the competition, both IGBTs and IGCTs are viable technologies and are both being continually improved. Direct torque control (DTC) is a more recently developed motor control platform, especially for medium voltage drives. DTC controls speed and torque directly, without the use of a modulator. DTC can catch a load already in motion, providing the ability to resume fan operation after an interruption in power without waiting for the fan to come to a stop (Morris and Armitage). DTC accomplishes this by using motor flux and torque as primary control variables that are compared to values from an internal motor model. Adjustments are made to the voltage and frequency accordingly. This process does not 9
Virginia Tech
require an actual speed measurement to be taken, thus requiring no feedback and eliminating any feedback encoder failure (ABB). The actual operation of DTC is beyond the scope of this research, but Buja and Kazmierkowski present a review of DTC techniques and their operation (Buja and Kazmierkowski 2004). VFDs that are based on the VSI PWM technology inherently have four disadvantages that require additional motor considerations – internal temperature increases, breakdown of the insulation in the windings, bearing currents, and harmonics and electromagnetic interference (deAlmeida et al. 2004). A solution to these problems is to use a sine wave output filter. The filter is located between the drive and the motor, and has the following benefits: no extra motor stress, no insulation stresses or cable resonances, minimal currents to ground or bearings, minimal noise, and can utilize standard motors (Shakweh 2000). This last point is especially important, as it allows VFDs to be installed on existing motors without modifications or additional costs. Another option is a VFD incorporating IGCT technologies with output filters, which offers nearly sinusoidal output and a rapid response to torque variations, resulting in no motor derating, and no additional winding insulation (Steinke et al. 1999). By utilizing DTC, the starting torque is maximized and fluctuations in load are compensated for with a quick response. These features also allow the drive to be used on nearly any motor, including retrofitting motors in existing applications. An example of the topology of a modern VFD is shown in Figure 2.6 below, and a photograph of the same drive is pictured in Figure 2.7. This drive is ABB’s ACS1000 medium voltage drive. © 2005 ABB MV Drives Figure 2.6 - ABB’s ACS 1000 Variable Frequency Drive topology (ABB) 10
Virginia Tech
© 2005 ABB MV Drives Figure 2.7 – Photograph of ABB’s ACS 1000 Drive (ABB) 2.1.3 Applications of VFDs Variable frequency drives are common in many different industries today. The benefits of a VFD are widely utilized in various applications. In the mining and mineral processing industry, VFDs are used for operating belt conveyors, mills, and pumping, as well as trams and continuous miners. There are three basic categories of motor load which are classified based on how torque requirements vary with speed (Allen-Bradley). 1) Constant torque load – The torque is constant at all speed ranges, and the horsepower is directly proportional to speed. These applications are essentially friction loads, such as conveyors and extruders, high inertia loads, and positive displacement pumps. 2) Variable torque load – The torque is low at low speeds, and high at high speeds. Usually the torque is a function of speed squared. Applications with this load profile are fans, pumps, and blowers. 3) Constant horsepower load – Speed and torque are inversely proportional: high torque at low speeds and low torque at high speeds. This load is a function of the 11
Virginia Tech
2.2 Mine Ventilation 2.2.1 Introduction The purpose of mine ventilation is to help maintain a safe and healthy environment underground that provides a reasonable comfort level (McPherson 1993). Adequate airflow is necessary to provide fresh air for miners to breathe and to remove harmful gases and dust. In coal mines especially, there are many federal and state regulations that govern exactly how this is to be accomplished. There are maximum dust and gas concentrations that must be maintained in the mine, thereby creating specific airflow requirements in certain areas. Fans located in either the mine or on the surface, provide this necessary airflow and are an essential part of this ventilation system. As the mine is developed and the expanses underground increase, the ventilation system must also be able to adapt over time to the changing conditions. A great deal of engineering goes into developing a mine ventilation system to incorporate all of these factors. Behind meeting all safety and regulatory standards, economics also play a large role in how a ventilation system is created. There has been much research on the principles and methods of mine ventilation. Below is a brief overview of the components of a simple room and pillar mine ventilation system, and how one is developed. 2.2.2 Components Airflow is generated by large mine fans and travels through the mine workings, usually from an intake shaft to an exhaust shaft. In the mine, air direction and quantity are controlled by a variety of devices. Permanent and temporary stoppings are used to block passages, regulators reduce the flow of air by partially blocking an airway and creating a shock loss, and over- or under-casts allow air to cross at intersections without mixing. These devices are used below in a description of a simple room and pillar coal mine. In room and pillar mining, the mains and panels are separated into parallel airways by the placement of stoppings. These stoppings are physical barriers used to prevent mixing of air, and are either temporary or permanent (Hartman et al. 1997). These airways are used for intake, return, or neutral airflow, depending on the number of entries in the section. An example is illustrated with further detail in the Chapter 3. Air flows from the intake shaft into the mains. From the mains the air is split to travel through each panel to the working face. In Figure 2.4, the layout employs a double split method where the intake air flows through the center entries, is split at the face, and is 13
Virginia Tech
2 2 H ⎛n ⎞ ⎛D ⎞ w H ∝n2D2w, or 2 = ⎜ 2 ⎟ ⎜ 2 ⎟ 2 (5) ⎜ ⎟ ⎜ ⎟ H n D w ⎝ ⎠ ⎝ ⎠ 1 1 1 1 3 5 P ⎛n ⎞ ⎛D ⎞ w P∝n3D5w, or 2 = ⎜ 2 ⎟ ⎜ 2 ⎟ 2 (6) ⎜ ⎟ ⎜ ⎟ P n D w ⎝ ⎠ ⎝ ⎠ 1 1 1 1 where, Q = airflow H = head/pressure P = motor power D = fan diameter n = fan speed w = air specific weight subscript 1 = values with initial parameters/conditions subscript 2 = values at changed parameters/conditions Measuring fan performance as a function of power results in an expression of fan efficiency. The mechanical efficiency, η, is expressed as Equation 7, where P is the air a power, and P is the brake power. m P η= a ×100% (7) P m Air power can be calculated from the head, H, and quantity, Q. In English units (H in in. WG and Q in cfm), the formula is Equation 8. Brake power is the power that must be supplied to the fan, and is found by multiplying the fan efficiency by the air power. Brake power can also be simply read from the manufacturer’s fan curves or calculated from the fan laws (Equation 6). HQ P = hp (8) a 6346 15
Virginia Tech
2.2.4 Ventilation Analysis In order to provide the necessary airflow, the fan must generate a high enough pressure to overcome the resistance of the mine airways. This pressure, or head loss, is a function of the airflow and the size, length, and friction factor of each airway section in the mine. Head loss can be related to airflow and these airway parameters by Atkinson’s equation, Equation 9. The total head loss for the mine is found by combining (in parallel or in series) all individual airway losses based on Kirchhoff’s laws. Hartman (1997) and McPherson (1993) describe this process in detail in their books. KO(L+ L )Q2 H = e (9) l 5.2A3 Where, H = Head loss, in. WG l K = Friction factor, lb·min2/ft4 O = Perimeter, ft L = Length, ft L = Equivalent length of shock losses, ft e Q = Airflow, ft3/min A = Area, ft2 Values for friction factors vary depending on the type of mine, how the airways are supported, and the airway condition. The head loss is directly proportional to the square of the quantity of air (Equation 9). If K, O, L, L , and A are held constant, they can be combined to form one single constant, e R, or the resistance of the airway (Hartman et al. 1997). Equation 9 can then be rewritten as: H = RQ2 (10) l Since the resistance is constant at given operating conditions, this equation can be used to define the characteristics of the mine over a range of pressures and airflows. The resulting graph of such a calculation (Figure 2.8) is known as the system or mine characteristic curve, which describes the head loss at any quantity of airflow. 16
Virginia Tech
3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 0 50 100 150 200 250 300 350 Airflow, kcfm GW .ni ,daeH 100 90 80 70 60 50 40 30 20 10 0 PH ,rewoP ekarB Power Curve Operating power Operating point System Curve Fan Curve Figure 2.9 – Determining the Fan Operating Point and Power 2.2.5 VnetPC Modeling VnetPC is a ventilation modeling program developed by Mine Ventilation Services, Inc. This software takes data that describes the mine airways (length, friction factor, geometry) and fan properties (H-Q characteristic) to generate a ventilation model that includes fan operating points, regulator/booster requirements, airway quantities and resistances, and power requirements. The branch data entered into the program is based on a ventilation network representation of the mine that consists of branches (mine airways) and nodes (intersections of airways). Branches are defined by their respective node endpoints. This topology represents a simplified layout of the actual mine. Each branch has properties associated with it, including length, resistance per unit length, parallel airway factor, type of airway, and surface state. Figure 2.10 shows a segment of mains and a panel from a mine plan. Figure 2.11 illustrates the corresponding ventilation network. The ventilation layout combines parallel airways into a single flow path and only includes nodes where airways combine or split. Stoppings are modeled as sets of parallel airway leakage paths, with a single high resistance corresponding to the number of stoppings modeled per path (Bruce and Koenning 1987). The ventilation network is not to scale because the lengths of branches between nodes are a property of each branch. 18
Virginia Tech
CHAPTER 3: MINE AND VENTILATION MODELING 3.1 Mine Model Development To simulate the effects of varying fan speed, a simple room and pillar coal mine was designed to serve as the basis for the ventilation analysis. The actual design is not critical to this research because only comparisons of fan configurations are studied. The design used for this model can be replaced with any mine plan, and the results should have similar trends. The mine design is simple and straightforward so that the changes in ventilation requirements are due to mine development and distance from the fan over time. Since the objective of this study is to simulate the effects of changing the fan speed, special configurations, multiple ventilation shafts, and multiple fans are avoided. The mine design results in ventilation requirements that increase with mine development over time. Although the coal mine modeled is not based on an actual mine, typical data were used for describing the ventilation characteristics. It is assumed that the coal seam is 6 ft thick and extends over a large area, at a depth of approximately 800 ft. An average coal density of 80 lb/ft3 was also assumed. The mine plan developed for this seam is a standard room and pillar layout. Pillar dimensions are 80 ft x 80 ft developed on 100 ft centers, with a 5 entry panel and 8 entry mains, illustrated in Figure 3.1. An 80 ft barrier between panels is maintained. Access to the mine will consist of 18 ft diameter intake and return shafts, as well as a 14 ft x 14 ft dual compartment slope at an angle of 17º. 21
Virginia Tech
Figure 3.1 – Pillar layout and dimensions To develop a reasonable timeline for mining this seam while simplifying the ventilation model, a few basic operating parameters had to be determined. For this room and pillar mine, two continuous miners will be used, each with an average production capability of 1,100 tons per shift. At two shifts per day, and 300 operating days per year, production totaled 1.3 M tons per year. Panel length was determined by an increment of the distance a continuous miner could cover in one year, including time for development of the mains ahead of the panels. Excluding the 1000 ft of mains ahead of the panels, each miner can cover approximately 15,600 linear feet of mining in a year. By using a panel length of 7,800 ft, each miner will mine two full panels per year. For simplicity, pillar extraction is not used, and after each panel is mined out, it is then sealed. The average operating life for a primary mine fan is between 15 and 20 years, therefore, the objective was to study the mine over a 15 year life. A portion of the resulting mine plan is shown below in Figure 3.2. 22
Virginia Tech
3.2 Ventilation Model Development Because of the simplicity of the mine layout, only one intake and one return shaft were used in this model. For the ventilation modeling, it was assumed that there would only be one continuous miner operating per panel, resulting in the design of two panels mined simultaneously. From a ventilation standpoint, the worst conditions result from having a miner at the end of each panel at the same time. At this point in time, the air must travel the farthest distance from the shaft to the last open crosscut in each active panel. The conditions at this point were the conditions assumed for the development of the ventilation model. Ventilation requirements in the model include: • Maintain a minimum airflow of 50,000 cfm at the last open crosscut at each panel. • Maintain a minimum airflow of 3,000 cfm at the tailpiece of each belt. • Maintain an average airflow of 5,000 cfm at the last open crosscut at the end of the mains when development is not occurring. • Velocity in the intake airways must fall within the recommended range of 600- 1150 fpm (Mutmansky and Greer 1984). Regulators are placed in the returns of each panel to control the airflow at the last open crosscut. Control devices are also placed at the belt tailpieces to limit the airflow. In VnetPC, these locations are modeled as branches with a fixed quantity, where regulators or booster fans are added as necessary to maintain the specified airflow. Values for the friction factor in each airway vary widely based on the conditions at each mine. These values have been researched by a number of people, and a recent study by Prosser and Wallace (1999) provided the values for coal mine airways, listed in Table 3.1 below, used in this research. The authors identify average values and standard deviations from a series of measurements, but to be conservative, the values used in this research represent their average values plus one half of the standard deviation, as is recommended by the authors. 24
Virginia Tech
Table 3.1 – Friction factors for coal mine airways (from Prosser and Wallace) Friction Factor Airway (lb·min2/ft x10-10) 4 Intake 46 Return 52 Belt 74 A dual split configuration is used in both the mains and the panels (Figure 3.3). Equalizers are located every 2000 ft along the mains to connect the returns along each side of the mains. This practice allows the airflows to balance in each return and offers an alternative path for airflow if a return becomes blocked. The belt is isolated from the intake and returns, and is considered a neutral airway. Since the panels are sealed after they are mined out, only the farthest panels along the mains have an effect on ventilation requirements. Figure 3.3 – General mine ventilation layout (Novak 2003) To compare and contrast fan and VFD configurations over the life of the mine, a yearly time interval was modeled. Any time increment could have been used, but since each time interval required separate models, a yearly increment was deemed sufficient to allow the effects of using VFDs to be perceptible. A separate ventilation model was created for 25
Virginia Tech
3.3 Determining the Optimum Operating Point To provide a standard for comparison, the optimum operating point was required for each model. This ‘optimum’ can be defined as the operating point which results in the lowest head and quantity produced by the fan to adequately supply each face with the required air quantity. There has been much research into determining this optimum point, and devising ways to calculate it. For example, there are methods that favor linear modeling and others that prefer using non-linear models to solve the ventilation network and determine the losses at each regulator and find the fan operating point to balance a network (Jacques 1991; Zhuyun and Yingmin 1991). Most of this research does not consider actual power costs though, and only attempts to optimize the ventilation network and fan conditions with regulator settings. A succinct explanation of how to find the optimum operating point is to “minimize the work performed by all fans in the ventilation network while minimizing energy losses at all regulators,” (Krzystanek and Wasilewski 1995). Although Krzystanek and Wasilewski do not propose a method to determine this, their process leads to the conclusion that reducing the overall amount of regulation results in an increase in the efficiency of the ventilation system, accompanied by a decrease in the required head and quantity of the fan. This increase in efficiency can be directly related to energy savings, as operating a fan at a lower head and quantity results in lower power consumption. For this research, it was not practical to develop a computer program that would account for variable speed fans or even to redesign current computer programs for the same effect, but it was feasible to use VnetPC to solve this problem in a slightly different manner. The program solves the ventilation model based on either a given fixed fan pressure or a fan curve, and sizes the regulators to ensure adequate ventilation. By iteratively varying the fan pressure and calculating the solution, the fixed quantity branches can be monitored, and the optimum operating point determined when a fan pressure yields a minimum sum of regulator resistance in these branches. Three iterations of this process can be seen in Figure 3.5. VnetPC replaces regulators with booster fans in the fixed quantity branches if the overall fan pressure is too low to supply the required airflow, shown in iteration 1. Thus, ideally, the fan pressure can be reduced until the regulators furthest from the intake shafts will behave like a free split, and have zero regulation. 27
Virginia Tech
CHAPTER 4: REDUCED SPEED FANS Once the ventilation model was created and the optimum operating points were found, the next stage of the research was to determine the speed at which to operate the fan to meet the ventilation requirements while maximizing the fan and motor efficiency. This was accomplished by first choosing an appropriate fan, and then creating reduced speed head-quantity, power, and efficiency curves. The following sections detail each of these steps. 4.1 Selecting an Appropriate Fan The choice of an appropriate fan is based on the manufacturer’s fan curve data. A fan is selected based on an available pitch setting that will satisfy the mine’s most extreme operating condition at an acceptable efficiency. In practice there is no single optimum fan for a given mine, but rather, many fans constructed by different manufacturers will meet the specifications determined by the mine. The definition of ‘optimum’ is also specific to the mining operation, but below are additional points to consider when choosing a fan for use with a VFD. Comments on fixed pitch fans are included, and refer to fans that can be manufactured without any provisions for adjusting the pitch setting of the fan blades. Although at this point in time, the cost of a fixed pitch fan is the same as an adjustable pitch fan (Spendrup 2005), there is the prospect that an increased demand for fixed pitch fans might be incentive for manufacturers to produce them for a lower cost. For fixed pitch fans: • The maximum efficiency that can be obtained at this fan setting will be the maximum efficiency achievable at any operating point while using a VFD as well. For fans with similar costs, choose the one that provides the highest efficiency. • In most cases, the best fan will meet the most extreme operating condition while operating near its maximum capabilities at an acceptable efficiency. • Depending on the lifetime operating conditions, it might be more economical to use a fan that will meet the maximum operating conditions at the center of its efficiency “bubble” (resulting in operation at a point well below its maximum capabilities), rather than one that meets the operating conditions at a lower efficiency. Choosing a fan that is larger than necessary to provide adequate 30
Virginia Tech
airflow might require higher capital expenses, but maintaining a high efficiency in each year will result in savings that might offset the additional expense. For adjustable pitch fans: • A fan that will meet the requirements for a fixed pitch fan can be the best option for adjustable pitch fans. • The limitations of the maximum achievable efficiency in each year are reduced, providing a greater range of operating conditions that fall within the larger efficiency zones. • Using the same size fan as with fixed pitch, it is usually possible to increase the fan efficiency for each operating point by adjusting the pitch. Ultimately, economics (capital costs) will determine whether an adjustable pitch or fixed pitch fan should be used. For the mine modeled in this research, a Spendrup Series 274-165-880 fan was found to provide adequate ventilation capabilities at an acceptable efficiency. This is a 108 in. diameter fan that operates at 880 rpm. The yearly operating points are shown with the manufacturer’s fan curves in Figure 4.1. 16 5 6 4 14 3 2 12 16 15 10 14 1500 8 13 12 1200 6 11 10 900 9 4 8 7 600 6 5 2 4 23 300 0 0 0 100 200 300 400 500 600 700 .g.w .ni ,erusserP latoT naF 1 85% 75% 80% 70% 6 5 4 3 2 1 Fan Flow Rate, kcfm PH ,rewopesroH ekarB Figure 4.1 – Spendrup 274-165-880 fan with yearly operating points 31
Virginia Tech
An additional Spendrup fan, model 305-183-880, also provides adequate ventilation, but at a lower overall fan utilization. This is evident from Figure 4.2 which shows that the maximum operating conditions only occur at approximately 50% of the fan’s capabilities. As noted in the suggestions for fan selection, above, this larger 120 in. fan meets the maximum ventilation requirements at a higher efficiency than the smaller Spendrup 274- 165-880 fan (84% vs. 78%). 20 6 5 18 4 3 16 2 14 12 16 3000 15 10 2500 14 8 13 2000 12 6 11 1500 10 9 4 8 1000 7 6 5 2 234 500 0 0 0 100 200 300 400 500 600 700 800 900 1000 .g.w .ni ,erusserP latoT naF 1 84% 80% 75% 70% 6 5 4 3 2 Fan Flow Rate, kcfm PH ,rewopesroH ekarB 1 Figure 4.2 – Spendrup 305-183-880 fan with yearly operating points 4.2 VFD and Fan Combinations Modeled To determine whether the size/capacity of the fan has an overall effect on the performance of fans with VFDs, multiple scenarios were modeled for the mine plan described in Chapter 3. For this analysis, six different fan and VFD scenarios were modeled. They will be referred to as options 1 through 6, and are described below. These options attempt to illustrate the performance results of using VFDs and/or adjustable pitch fans on the mine modeled in the previous sections. Even though actual 32
Virginia Tech
performance results are specific to the mine, trends and patterns can be illustrated by comparing the options relative to each other with this example. Options Modeled: 1. Use the Spendrup 274-165-880 fan as a standard adjustable pitch fan operating in a conventional manner. This option is likely to be similar to the typical choice of fan to meet the requirements of the example mine. 2. Use a larger Spendrup 305-183-880 fan as a standard adjustable pitch fan in a conventional manner. This option would not likely be chosen, as the fan is not fully utilized and costs are unnecessarily higher. 3. Use the Spendrup 274-165-880 as a fixed pitch fan with a VFD. This option was modeled to show performance differences if a fan were manufactured that had one fixed blade pitch setting. Costs could be lower if the fan did not require adjustable pitch settings. It was assumed that the pitch was fixed at setting number 6. 4. Use the Spendrup 305-183-880 as a fixed pitch fan with a VFD. This option is modeled for the same reasons described in option 3. This fan was assumed to be fixed at pitch setting number 4. 5. Use the Spendrup 274-165-880 fan as manufactured as an adjustable pitch fan and operating at reduced speeds with a VFD. 6. Use the Spendrup 305-183-880 fan as manufactured as an adjustable pitch fan and operating at reduced speeds with a VFD. 4.3 Methodology for Modeling Reduced Speed Fans 4.3.1 Fixed Pitch Fans For the analysis and plotting, tables of data points (or equivalent equations) of the fan curves are required. If standard manufacturer’s hard copy or digital (i.e. PDF) graphs are used, scanning and then digitizing the curves is necessary. Resulting data tables should include points along each of the fan curves, power curves, and any intersections of the fan curves and efficiency lines. If the fan has a fixed pitch, then only the curve for that pitch setting is useful. The general process for creating these reduced speed fan curves follows. The Spendrup series 274-165-880 fan was used in the example to describe the process throughout this 33
Virginia Tech
section. The same process was used for the Spendrup series 305-183-880 fan, with the values of fan performance changed. All of the results are presented collectively after the process is described. From the original fan curves, Figure 4.1, it was determined that pitch setting number 6 is required to meet the maximum operating conditions with a resulting efficiency between 75 and 80%. Using the fan laws for quantity, head, and power (Equations 4 through 6), a new fan curve and power curve can be calculated in a spreadsheet for any new speed from each data point on the original curve and the original design speed. Finding this appropriate speed for each operating point is an iterative process, requiring the equation of the mine resistance, and the equation of the fan curve. The mine resistance at the optimum operating point can be calculated from the mine head and total quantity by Equation 10. Using this resistance, an equation (of the same form) for the mine resistance can be created for head as a function of quantity. For example, if R = 0.354x10-10 in·min2/ft6, the resulting equation for mine head is: H = 0.354×10−10×Q2 The process to obtain the approximate equation of the fan curve involves general curve fitting. The data points along the curve are known from the digitized fan curve, and the form is approximately quadratic. The equation relating head, H, to quantity, Q, is: H = cQ2 +c Q+c (11) fit 1 2 3 Where, c , c , and c are constants 1 2 3 This curve fitting is performed using Microsoft’s Excel Solver add-in. The constants are adjusted automatically by the Solver algorithm until the sum of squares difference between the fit values of head and actual values of head is minimized. Using the previous two equations relating the head and quantity of the mine and the fan, an intersection point can be found by solving both equations simultaneously within the range of the fan’s operating quantity. This point indicates the operating point of the fan for the given mine resistance at the specified speed. The process of curve creation to finding the operating point was repeated iteratively using a binary search method until a speed was found that resulted in a difference between the 34
Virginia Tech
Table 4.1 – Yearly Speed Requirements Year Speed, rpm 1 350 2 350 3 375 4 400 5 425 6 450 7 480 8 515 9 550 10 590 11 625 12 670 13 715 14 765 15 815 16 875 It was also important to check the ventilation model’s branch results to verify the spreadsheet calculations are correct and ensure that the minimum airflow requirements are being met at the designated branches. At lower pressures, the fixed quantities of the regulators required only small adjustments to accomplish this. The process involved inputting the new reduced speed fan curve into VnetPC, and executing the model. If the quantities at the faces were inadequate, the regulators were adjusted and the model re- executed. The fan results were recorded, and the process repeated at each yearly interval. The significant results from this modeling were the fan quantity and head, as well as the air power required, and are summarized in Table 4.2 in the next section. 4.3.2 Calculating Power and Efficiency After the required speeds and resulting fan curves were determined, the brake power for each operating point was then found. There are two methods to find this value. First, the yearly operating points were plotted on a graph that included each reduced speed power curve. The value of power was then read from the graph at each yearly quantity. For example, at year 14, the brake power is approximately 875 hp, as read from the graph in Figure 4.4. However, this reading is only as accurate as the scale on the graph. For better accuracy, an equation was found for each reduced speed power curve by fitting a curve to the data points with power as a function of quantity. A second order polynomial of the form in Equation 12 is adequate to describe these curves. 36
Virginia Tech
P = cQ2 +c Q+c (12) fit 1 2 3 Where, c , c , and c are constants 1 2 3 The fitting process was done using Microsoft Excel’s Solver function, using the same methods described above to fit the fan curves, except measured and fit power values were used. From these equations, the quantity at the operating point can be used to calculate power. 16 1600 14 1400 16 12 1200 15 10 1000 14 8 13 800 12 6 11 600 10 9 4 8 400 7 6 5 4 2 3 200 2 0 0 0 100 200 300 400 500 600 700 .g.w .ni ,erusserP latoT naF 875 815 765 715 670 625 590 550 515 480 450 425 400 375 Fan Speed, RPM350 Fan Flow Rate, kcfm PH ,rewopesroH ekarB Figure 4.4 – Reading power from the reduced speed power curves Efficiency at each operating point was then found by dividing the air power resulting from the model by the brake power calculated above. It is also helpful to represent this information graphically to see the possible efficiency ranges of the fan at different speeds and pitch settings. The process used to illustrate the approximate efficiencies and possible efficiency ranges on a fan curve plot is described below. Head and quantity are read from the point of intersection of the fan curve and each efficiency line on the fan curve plot. For example, in Figure 4.5, points A, B, C, and D are the intersections of pitch setting number 6 fan curve with each efficiency line. Only 37
Virginia Tech
Table 4.3 – Results from adjustable pitch, reduced speed fan Fan Pitch Quantity, Head, in. Air Power, Brake Power, Calculated Year Speed, rpm Setting kcfm WG HP HP Efficiency, % 1 350 6 219 1.70 59 77 77 2 350 6 219 1.70 59 77 77 3 375 6 231 2.02 74 96 77 4 400 6 244 2.37 91 118 77 5 425 6 257 2.72 110 143 77 6 495 5 271 3.11 133 168 79 7 525 5 286 3.55 160 202 79 8 565 5 306 4.17 201 254 79 9 600 5 324 4.74 242 306 79 10 645 5 347 5.54 303 381 79 11 690 5 370 6.37 371 469 79 12 730 5 391 7.17 442 557 79 13 780 5 417 8.22 540 680 79 14 835 5 446 9.46 665 836 80 15 815 6 474 10.74 803 1046 77 16 875 6 509 12.41 994 1294 77 4.4 Summary of Modeling Results Considering the adjustable pitch- fixed speed fan of option 1 (Figure 4.1) the highest ventilation requirements occur at the higher end of the fan’s capabilities. Since this is an adjustable pitch fan, the fan can operate on all of the curves indicated (pitch settings 1 to 6) as well as at an infinite number of points between the specified curves at 880 rpm. In practice though, it is unlikely that the fan will be adjusted precisely between labeled settings. Limiting operation to the labeled pitch settings will result in the best case scenario of operation shown in Figure 4.9. For operation in years 1 through 9 the fan is far below 70% efficiency, and in practice, would not likely be operated at these points. If the fan of option 1 were operated at the points in Figure 4.9, the power consumption and calculated efficiencies are listed in Table 4.4 for each operating point. These calculated values are based on the air power requirement obtained from VnetPC simulations, and the brake power values as read from the fan curve graphs. These data are the result of what can be considered operating with current practices assuming the “best case scenario” ventilation requirements, and serve as the basis for comparison of the remaining options. In this situation, fan efficiency is not a factor in determining the operating point, only air power. For example, at point number 2, to draw a minimum 257 kcfm of air through the mine, the fan can be operated at curve number 1 at 38% efficiency, resulting in a brake power of 241 hp. Operating at curve number 2 will also 43
Virginia Tech
meet the minimum requirements, but achieving operation at 70% fan efficiency requires operation at 310 kcfm and 5.8 in. w.g., which results in an approximate brake power of 400 hp. Thus, the operating point which yielded the lowest power consumption was chosen regardless of fan efficiency. Figure 4.9 – Operating points at pitch settings Table 4.4 – Operating parameters for Spendrup 274-165-880 fan Fan Speed, Pitch Quantity, Head, in. Air Power, Brake Power, HP Calculated Year rpm Setting kcfm WG HP (Vnet) (from fan curves) Efficiency 1 880 1 257 2.28 92 241 38% 2 880 1 257 2.28 92 241 38% 3 880 1 256 2.39 96 246 39% 4 880 1 255 2.61 105 260 40% 5 880 2 323 3.70 189 331 57% 6 880 2 321 3.99 202 346 58% 7 880 2 318 4.29 215 356 60% 8 880 2 316 4.58 228 359 64% 9 880 3 377 5.84 347 494 70% 10 880 3 374 6.15 363 511 71% 11 880 3 372 6.33 372 516 72% 12 880 4 432 7.93 540 693 78% 13 880 4 428 8.38 563 707 80% 14 880 5 477 10.10 759 945 80% 15 880 6 526 11.90 986 1284 77% 16 880 6 514 12.43 1006 1310 77% 44