question
stringlengths 19
6.88k
| answer
stringlengths 38
33.3k
|
---|---|
Problem Statement: When I use the external Steel File and choose the galvanized finish option at either the project or area level, it does not appear to be using the steel price I entered in my Steel File. What is happening? | Solution: When you are using an external Steel File and you choose the galvanized finish option at either the project or area level, the system will use the price from the external Steel File as a basis and add a galvanized cost on top of the user specified cost. The cost addition depends upon the weight of steel items. For items > 40000lbs, in V7.2 we are adding 28.60 cents/lb and for weight less than 40000 lbs we are adding 42.9 cents/lb. (Note the cost addition will vary based on country base.)
We also increase the weight of the steel by 3-5% (based on what the steel item is).
Keywords:
References: None |
Problem Statement: How do I see my custom pipe specs in my exported Excel spreadsheet? | Solution: In V7.3.2 when a spreadsheet was created from Aspen Capital Cost Estimator (ACCE) using the spreadsheet export/import feature, the custom pipe specs drop down list was not available in the input fields in plant bulk and installation bulk pipe worksheets.
In V8 this has changed as follows:
A? When a custom pipe spec file is included in a project, the custom pipe spec symbols from this file will be available in the exported spreadsheets, thus allowing users to scroll-down and pick the desired custom pipe spec. If users manually enter the pipe spec symbol in Excel, it will be validated against the drop-down list. Thus an invalid entry will not be permitted (unless it is copied/pasted from elsewhere which eliminates the validation).
A? If no pipe spec file is included in a project, the exported spreadsheet will not have a drop-down list of custom pipe spec symbols and no validation will be made. This means the user can enter any pipe spec name in these fields.
Ultimately, if the correct pipe spec file is not attached to the project in which the spreadsheet will get imported or incorrect names are given, these will be flagged as usual when a project evaluation is performed.
Keywords: Custom Pipe Specs, drop-down, menu
References: None |
Problem Statement: Why do some of the process equipment pieces not show data on the Design Data Sheets? | Solution: Design data sheets are only generated for process equipment for which the equipment code begins with letter ?D?.
If you look in the components palette, each item has an equipment code (see image below). For process equipment, the equipment code begins with the letter ?D? or ?E?. For plant bulks, the code always begins with letter ?B? (for bulks). For site development, the code begins with ?SD?. Design data sheets are only generated for process equipment for which the equipment code begins with letter ?D?.
Keywords: Report, design data sheets, process equipment
References: None |
Problem Statement: Improvements in Aspen Process Economic Analyzer & Decision Analyzer | Solution: ? Process Modeling
Integrated Economics capabilities enhanced
Equipment and total weight reported in results
Selected Economic parameters reported in the results
Aspen Plus and HYSYS stream costing passed to APEA
HYSYS power utility mapped to electricity in APEA
Improved mappings of Aspen Plus tower internals to APEA (including auto-mapping of multiple tower sections to the new APEA multi-diameter tower model)
?Replace? function added to streamline equipment mappings
Design criteria for compressors revised
Data import support for 2nd level and lower HYSYS sub-flowsheets
Unique stream and unit op names are still required across all hierarchies
Decision Analyzer Improvements
ARM (Analyzer Relocation Module) review and update all 89 locations for costing and design specs
ASM (Analyzer Scaling Module) Error messages will be generated if min/max component limits are exceeded. Original value is retained as indicated in the error message.
Keywords: V7.3
References: None |
Problem Statement: How do I set delivery time by equipment class? | Solution: To set vendor fabrication and shipping times for equipment class:
1. In the Project Execution Schedule Settings subfolder, right-click on Equipment Classes Delivery Times and click Edit. The Schedule Equipment Classes specifications form appears in the main window.
2. For each equipment class, specify the number of weeks needed to fabricate and ship equipment after vendor data approval.
The default values of the fabrication and shipping times used for different equipment classes are documented in the Aspen Icarus reference manual Chapter 36 Icarus Technology.
Keywords: Fabrication and shipping time
References: None |
Problem Statement: How is Pipe Testing Calculated each Area? This figure is provided in the Area Bulk Report section (for each area) of the Capital Cost evaluation report. | Solution: Pipe Testing is a function of number of piping iso's and diameter x length. The number of fittings does not enter into this--except for the fact that number of fittings affects the calculation of number of piping iso's in some fashion.
COA 306 PIPING SYSTEM TESTING Hydrostatic testing PIPE TESTING (field only) Prepare for test (place blinds & blanks, open valves, support items, air purge, etc.); test (fill, pressurize and monitor lines, soap test joints); clean up after test (drain lines, remove temporary items, close valves, etc.)
The number of pipe testing man-hours is calculated by the system based on the estimated time to do the following.
Prepare for test (place blinds & blanks, open valves, support items, air purge, etc.)
Test (fill, pressurize and monitor lines, soap test joints)
Clean up after test (drain lines, remove temporary items, close valves, etc.)
The calculation is not simply a percentage of the pipe installation man-hours. Instead, the calculation models all of the procedures above for the pipe lines in each area.
Keywords: testing
pipe
calculated
calculation
COA
COA 306
test
References: None |
Problem Statement: How can I use COMPONENTS from one project in another project? | Solution: You can bring components ( or whole areas) from another project into your current project by doing the following:
1.) Open the project you want to import the items into
2.) Make sure you are in the Project View
3.) In the Projects tab on the Palette, double click on the project you want to import items from. It should expand the project where you will see the areas, and there will be plus signs under the areas where you can expand the areas to see the components.
4.) In the Palette, click on the component or area you want to import, and drag it over to the Project View in your current project. If it is an area, drop it on the Report Group you want it in. If it is a component, drop it in the area you want it in. Aspen Capital Cost Estimator will bring the item into the project.
5.) Repeat for additional items. Also, you can use the control and shift keys to drag multiple items at one time.
(The unit set should also be the same in the two projects)
Keywords:
References: None |
Problem Statement: When I index at an area level, does it compound the indexing done at the project level or replace the project level compounding with the area level compounding? | Solution: By default the system will use the area indexing and replace the project level indexing with the area level indexing. There is a new option that started in V7.0 which allows you to specify that the indexing will compound the project level indexing instead of replacing it.
Default Replace (R):
New Compound (C) option:
Keywords:
References: None |
Problem Statement: I do not what to use the power distribution and the process control features in Aspen Capital Cost Estimator (ACCE), so I unlinked the areas from the process control and power distribution form. When I evaluate the project the program closed with the following message: Aspen Icarus Cost Engine Application has encountered a problem and needs to close. | Solution: In ACCE, all areas are automatically linked to default control centers and unit substations. User can modify the control center and unit substation structures, but users have to make sure every area is linked to a control center and a unit substation, and every control center is linked to a unit substation. Otherwise the aforementioned crash could happen. Option ?M? under Project Basis View | General Project Data can be used to suppress default equipment/area/project bulks.
Keywords: Process control, power distribution
References: None |
Problem Statement: My company decided to move from Aspen ICARUS Project Manager (IPM) to Aspen Kbase. I know that I cannot just open up my IPM Project in Kbase because of contractor, process control and power distribution issues (there are no multiple contractors in IPM, where there are in KBase, and there is no Power and Process Distribution in IPM where it does exist in Aspen KBase). How to I take my IPM project file and convert it into a Kbase file so that I don't have to re-enter in all the data by hand again? | Solution: It's easy! Here are the steps to EXPORT your IPM file into an ICARUS 2000 specs file:
1. Open your IPM file in IPM.
2. Perform an estimate to make sure that there are NO ERRORS. If there are ERRORS, the ERRORS MUST BE FIXED. (This is important, as if there are ERRORS in the IPM project, the ERRORS will cause more problems when exported to the Kbase system.)
3. If there are no ERRORS, or you have fixed them, then go to the menu bar and select: FILE | EXPORT TO specs.
4. A Save As dialog box will appear. Place this file in an EMPTY folder, and make sure that you name the file SPECS (with no extension). Ex: specs
5. Now, your IPM file is exported to an ICARUS 2000 specs file which can be imported into Aspen Kbase.
6. Exit out of IPM.
Steps to IMPORT the ICARUS 2000 specs file into Aspen Kbase:
1. Open Aspen Kbase.
2. Go to the menu bar and select: FILE | NEW. The Create New Project dialog box will open.
3. Enter in a Project name and Scenario name and then click the IMPORT button.
4. The Select Import Type dialog box appears.
5. Select the radio button ICARUS 2000 9-10, and click the OK button.
6. The Browse for folder dialog box opens, and browse to the folder where you saved your specs file in step #4 above (when you exported the IPM file to a specs file). When you have found the folder, click the OK button.
7. The import will then begin. This can last several minutes to even an hour, depending on how many components the specs file has.
Once the import is finished, you now hae your IPM project CORRECTLY converted into an Aspen Kbase project.
Keywords: export
import
icarus 2000
ipm
project
specs
References: None |
Problem Statement: I have created a new P&ID using the new Aspen Kbase P&ID Editor tool. How do I use this P&ID with an Equipment Model Library Item? | Solution: 1. Open the P&ID library from the Libraries Tab.
2. Click on the Components Tab.
3. Right-click on the Equipment Model Library and select SET DEFAULT P&ID.
4. Click NEW.
5. Choose the Item Symbol using the browse button.
6. Choose the Item Type using the browse button.
7. Choose the P&ID file using the browse button.
8. Select the P&ID drawing and click OK. (If no drawings appear under the P&ID library, then there are no User-Created P&IDs to select from to create the default).
9. Click OK to save the new default.
10. Click OK again to exit out of the Set Default P&ID menu.
11. The next time that you add in your EML item, and select to attach the PID (Open Default), your drawing will then appear for that EML item.
Note: All user Equipment Model Library files (EML files) are located in the ...\Aspen Icarus xx.x\Data\EML\IP or Met
OtherSolution documents you might find helpful:
Tutorial and Best Practices for Using the Aspen Kbase P&ID Editor
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=112277
How to use the Line Size Equation Editor in Aspen Kbase
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=114149
How to make sure previously used line size equations are used in an imported Kbase project from an Icarus 2000 project
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=116489
How to customize or create your own equipment symbols to use with the KBase P&ID editor?
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=114137
How to Import a Custom Equipment Symbol
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=114424
Keywords: EML
Equipment Model Library
Library
References: None |
Problem Statement: What are the basic differences between different Aspen Economic Evaluation products like Aspen Capital Cost Estimator, Aspen In Plant Cost Estimator and Aspen Process Economic Analyzer? | Solution: Different products have different features with different capabilities. Aspen Process Economic Analyzer, Aspen Capital Cost Estimator, and Aspen In Plant Cost Estimator use the same cost engine and they are different in project basis.
The biggest difference between ACCE and Aspen Process Economic Analyzer is the functionality you have with ACCE and not with APEA and vice versa.
What ACCE allows you to control that APEA does not: Allows more than 1 contractor, control over process control and power distribution systems, allows pipeline areas, link with P3 5.0 (P3 v5.0 and Interface to be purchased directly from Primavera), allows control over Contractor Scope, Engineering Work force, Equipment rental, and custom codes of accounts.
What Aspen APEA allows you to import is different simulators, design criteria and investment analysis.
If you have a license for both ACCE and APEA, you can open ACCE along with using an APEA license as well, and then you will have the functionality of all the above.
When you open ACCE you get the option whether you would like to use the APEA inside ACCE environment. You select the option. It will use the additional license for the product. Now if you create or open an existing case you will see all the options usually appear in the project basis of APEA. You can load the simulator data in this environment just like the way we do it in APEA.
The biggest difference between AIPCE and APEA and/or ACCE is that with APEA and ACCE you can import your simulation whereas in AIPCE, you cannot.
Obviously though, there are differences in the PROJECT BASIS between AIPCE, APEA and ACCE.....thus the reason to have them as different products and different pricing between the products. For more detailed on price, you will probably want to speak with your salesperson so that they can give you a demonstration for the products.
There is a link to a document on our support web site that gives you information on the different cost estimation products so that you can do a comparison between the features that each product has:
http://support.aspentech.com/webteamcgi/SolutionDisplay_view.cgi?key=120373
You can transfer Aspen Basic Engineering data to and from ACCE. You can not exchange data between Aspen Basic Engineering (ABE) and AIPCE or APEA.
Keywords: Difference, ABE, APEA, ACCE and AIPCE estimating capabilities.
References: None |
Problem Statement: When I evaluate my project I see the following error:
ERROR> 'EN - 1' INVALID DISCIPLINE NO. IN COLM. 10-11
Then I don't see any cost in the indirect cost. How can I fix it? | Solution: The problem is in the Project Basis View / Engineering / By Discipline. If you don't specified the Discipline this error will appear, so if you select all Disciplines or the discipline you want to specified and re-evaluate the project, you will notice that the error: “ERROR 'EN - 1' INVALID DISCIPLINE NO. IN COLM. 10-11” does not appear anymore.
If you evaluate the project you will see now all the indirect costs.
Keywords: Indirect, error, discipline
References: None |
Problem Statement: If I do a project/area level evaluation and compare the results for the item versus a MaxiBlock result generated by an individual component evaluation, the results are different. Why? | Solution: This behavior can be observed on cases where you have equipment hanging from a structure. In such cases the system does not consider the structure in which the tower is hanging since only the component input is sent to the engine. Because of this assumptions there could be differences in the steel support and installation bulks.
Keywords: Maxiblock report item ladders clips mast lights foundation
References: None |
Problem Statement: What are the new reports added for version 7.0 ? | Solution: New standard area reports are included with this version: Component Listings with Equipment Cost (equipment cost was not previously included in the component listings reports). The new reports are located at:
1. Full Import_Other Reports_Area_Component Listings_Sorted by ID
2. Full Import_Other Reports_Area_Component Listings_Sorted by Name
Keywords: New report, new feature, reports, report
References: None |
Problem Statement: Running an Excel report closes any open instance of MS Word | Solution: This is as designed.
Defects in MS Office require this behavior, the user should raise this issue with Microsoft to correct the base issue.
Keywords:
References: None |
Problem Statement: Is there a way to get insulation calculated for all my pipe lines without visiting each individual pipe line and entering the insulation thickness? | Solution: You can use the Hot and Cold Insulation Schedules to get the insulation for the piping and equipment calculated for either the project or a specific area. If you check the Aspen Capital Cost Estimator (ACCE) User Guide (Defining the Project Basis), under Insulation Specs (for V8.2 it starts on page 107, it will be different for other versions), it discusses the use of the Insulation Schedule Tables. You can turn it on for the project (or a specific area). For the project it is under:
Project Basis View | Design Basis | Insulation Specs
Go there and choose the appropriate hot and/or cold table(s). Then when you run an evaluation the system will generate the appropriate insulation based on the process temperature
Keywords: insulation, insulation specs, hot insulation, cold insulation, hot, cold
References: None |
Problem Statement: What are the minimum disk files to install the Aspen ICARUS software and support files? | Solution: The minimum disk files to install the Aspen ICARUS software and support files are the following from the DVD set:
All files off the root(not subdirs) of the DVD 6
DVD 6\Browser
DVD 6\aes2004cd1\core
DVD 6\aes2004cd1\Aspen Icarus 2004
All files off the root(not subdirs) of the DVD 1
DVD 1\Browser
DVD 1\Atlanta2004InfDVD1\SLM
You should have a choice to install the SLM Client tools (including the commute manager) as the last item in the list from DVD 6; way below where you choose to install Aspen ICARUS.
The SLM client tools are needed to for licensing. HOWEVER, if you already have the previous version of Aspen ICARUS installed on your PC (v12.2.2003), you don't have to re-install the SLM client tools again, unless you wish to update your version of the SLM client tools.
For most installs you should not need anything from DVD 1, but it's best for safety and support if you have the SLM stuff available.
If you wish to install the Aspen ICARUS documentation, please use the Documentation DVD.
Keywords: install
installation
ICARUS
documentation
References: None |
Problem Statement: Equipment specs imported using Spreadsheet Import and Export in Aspen Capital Cost Estimator (ACCE), the user tag characters are overwritten with '?'. | Solution: The user tag field might have non ASCII characters (example Russian characters) that are not recognized in ACCE. TheSolution is to retype the fields with ASCII characters (A-Z, a-z and 0-9).
Keywords: Spreadsheet, import, export, user tag.
References: None |
Problem Statement: Why are my H Steel pile showing more concrete needed when compared to my Pipe (concrete filled piles); shouldn't the concrete filled piles require more concrete? | Solution: The reason the PIPE (concrete filled piles) are not requiring more concrete is because the concrete is considered part of the purchase of the PIPE. It is included with the PIPE pile cost.
Keywords: None
References: None |
Problem Statement: How does the Aspen Icarus software calculate the excavation quantity for Pipe Trenches? | Solution: The Aspen Icarus cost engine uses linear (rather than cubic) quantity. Usually, the pipe length (excavation length) is significant compared to the width, and this is the reason for using linear for excavation quantity.
We don't use a purely sloped excavation for pipe trenches. We assume width of excavation as Diameter + 2 feet (1 foot on each side) and the depth of excavation is depth to the top of the pipe + Diameter + 0.5 feet. Excavation Quantity = Length * Width * Depth.
We then increase the volume to account for the slope (fall-in-factor, which is based on the soil type/excavation slope).
We use a sloped excavation for the foundations (sloped from the bottom, which you can see in the drawing in Civil section of the Aspen Icarus
Keywords: excavation, pipe trench, pipe trenches
References: Guide - civil plant bulk - concrete).
We also assume one pipe in a trench that is why we didn't use the sloped excavation like the foundations. |
Problem Statement: When I run my estimate, I get a strange error message and then ICARUS locks up that I have to end the task...and when I end the task, I lose all my work! HELP!
Error message:
Black pop-up window says something about qnc.exe (it pops up and disappears rather quickly). | Solution: Do you use Lotus Notes by any chance? Quincy (qnc.exe) is a program installed with Lotus Notes that captures errors into a file called NOTES.RIP in the root directory of the hard drive.
Follow these steps to turn off Quincy:
Click the Start button, and click RUN, and then type in cmd (this will open an MS-DOS Prompt). When the DOS prompt loads, type
CD \NOTES
This will take you to the DOS prompt C:\NOTES, which is the default location for Lotus Notes; use your location if it is different. At the C:\NOTES prompt, type
QNC -U
making sure you have one blank space between QNC and the hyphen.
Press Enter to run the command.
Then, try running ICARUS again. This should solve the problem!
Keywords: qnc.exe
Quincy
References: None |
Problem Statement: Why am I not seeing my Civil volumetric model on my equipment item, when I added the Civil bulk form on the equipment item? | Solution: You must specify a V in the bulk requirement field so that you will get the Volumetric model.
Keywords: volumetric
civil
References: None |
Problem Statement: With the new directory structure for the Icarus software for v2006.5, I find that the space on my C: drive is getting tighter and tighter.
I would like to change the directory where the project files are cached and where the backups are stored, to save room on the C: drive.
What items do I change in Tools - Options - Preferences - Locations? | Solution: It is highly suggested to move both the ProjectsDir and ProjectBackupDir together. Do not move just one.
Open your Icarus software (Aspen Kbase, Aspen IPM, or Aspen IPE).
Go to Tools - Options - Preferences - Locations.
Go to the bottom of the screen where it says 'Other Location Specifications'.
Items to change:
1. ClipboardDir - This where temporary files are created. You can change this to a directory of your choosing. These files automatically get deleted when the project is closed.
2. ProjectBackupDir - This specification is where your projects are backed up when you first open your project.
3. ProjectsDir - This specification is the same as the ic_cache, where it is populated with all the files from the .izp and .szp files when you open your project. This is the working folder while you work on your project. Once the project is saved and closed, all these files get compressed back into the .izp and .szp files and are copied back to the Project Directory where the project was created (whether it be locally or on the network).
[HKEY_CURRENT_USER\Software\AspenTech\Aspen Icarus Products\16.0\Kbase 16.0\InstallDir]
[HKEY_CURRENT_USER\Software\AspenTech\Aspen Icarus Products\16.0\IPM 16.0\InstallDir]
[HKEY_CURRENT_USER\Software\AspenTech\Aspen Icarus Products\16.0\IPE 16.0\InstallDir]
'ProjectsDir' = 'C:\\Documents and Settings\\users_domain_login_name\\Local Settings\\Application Data\\AspenTech\\Aspen Icarus 2006.5\\Projects\\'
This 'ProjectsDir' specification is the same as the ic_cache folder in versions 2006 and prior. (Note above: the 'users_domain_login_name' is to be changed to the user's specific domain login on the PC.)
'ProjectBackupDir' = 'C:\\Documents and Settings\\users_domain_login_name\\Local Settings\\Application Data\\AspenTech\\Aspen Icarus 2006.5\\Backup\\Projects\\'
This 'ProjectBackupDir' specification is the project backup location.
If you want you could move your temporary files folder also:
Note that this one needs to use the old short filename specification (8.3 format).
'ClipboardDir' = 'C:\\DOCUME~1\\users_domain_login_name\\LOCALS~1\\Temp\\AspenTech\\Aspen Icarus 2006.5\\temp\\'.
This 'ClipboardDir' is where temporary files get created.
Keywords: cache, location, move,
References: None |
Problem Statement: I notice that when I run my Standard reports, some areas are not being included. Why is this happening? | Solution: Areas will not be reported in the Standard reports if there are no components in them.
The other reason that an area may not show up is due to the database not being updated completely.
You can either:
1. Re-number your areas, or
2. Create a new area, add one component, then run your estimate. Make sure to then run the Interactive reporter and run 2 reports. Once the report is complete, close out of the Word document. Delete the new component, then delete the new area.
Re-run your estimate, and re-run the Standard reports.
Keywords: area, standard report, reports
References: None |
Problem Statement: Is CFM (Cubic Feet per Minute) in Economic Evaluator Actual or Standard CFM? | Solution: It is Actual CFM.
Keywords: None
References: None |
Problem Statement: Aspen Capital Cost Estimator (ACCE) during a project evaluation does not create a CCP report but goes directly into the interactive reporter | Solution: Check under Project Basis View | General Project Data | Suppress default equipment/area/ project bulks and make sure you have not selected M. The field should be blank. Choosing M is basically telling ACCE to behave like Aspen In-Plant Estimator which does not generate a CCP report, but goes directly into the interactive reporter.
Keywords: AACE, Interactive, Reporter, ccp
References: None |
Problem Statement: What percent of Direct Field Labor (DFL) does Aspen Capital Cost Estimator use for Consumable and Small Tools? | Solution: Consumable and Small Tools can either be entered as a fixed number or as a percentage of DFL. If neither is entered, the default values are (according to country):
US 3%
UK 4%
EU 4%
JP 3%
ME 7%
Consumable and Small Tools costs or percentages can be entered under:
Project Basis View | Contracts | Contractors | (contractor name) | Consumable and Small Tools cost
or
Project Basis View | Contracts | Contractors | (contractor name) | Consumable and Small Tools percent DFL (Direct Field Labor).
Keywords: Consumable and Small Tools, Consumable, Tools, indirects, contracts, contractors, contract, direct field labor, DFL
References: None |
Problem Statement: When I evaluate my project this error appears. How can I fix it? | Solution: This error appears when the Item Remark contains a line break or a new line character. This feature is not supported by the software.
For example:
You will notice that the Item Remark contains a line break.
TheSolution is to remove the new line character from these remarks. To do this, the user will have to copy these remark to a text editor (like note pad) and remove the new line character so the remark look like:
These Remarks can cause an error in the reporting system. Due to these errors the Reported reports are not complete you might see that the cost of your project is lower than usual or you can see an item evaluated multiple times. Once you fix these error the reports look ok.
When you copy and paste Remarks into the component for other file please verified that there are no line breaks in the description to avoid this error in future projects.
Keywords: Error, Numerical, Remarks
References: None |
Problem Statement: When I compare the 'Tank Containment' and 'Above Grade Tank' components with equivalent dimensions, the costs results are different, why? | Solution: If we compare the ?Tank containment? component and ?Above grade concrete tank? component with the same geometrical basis, we can find a cost difference. Although both components are conceptually the same (i.e. concrete walls, concrete slab, and rebar), they have been developed with different methodologies.
The ?Above grade concrete tank? component is based on a very detailed calculation model and was developed based on detailed information. The datasheet for this model is very comprehensive and provides a good summary of the tank components.
The ?Tank containment? component is a simplified model based on the ?External civil data specification? (Defined under the Libraries Tab > Customer External Files > Civil Material). However, the user gains additional flexibility with this model because he/she can update the external civil material file with parameters suited to the current project. Specifically the ?Tank containment? component uses foundation type 3 for the area paving, and foundation type 13 for the wall and wall footing. Although the data sheet is not as comprehensive, the detailed bulks split this component into paving and wall categories that contain the detailed bulk item descriptions and associated quantities.
The quantity of formwork for the ?Tank containment? component is based on the volume of concrete in the paving and wall, and the user may adjust the multiplier by updating foundation types 3 and 13 in the external civil material file
Additionally, the ?Tank containment? component is not based on a cylindrical containment area. The user may effectively model any shape of his/her choosing by specifying the wall length and paving area. But, if the user does not specify a wall length, a square area will be assumed with the following wall length:
Length = 4 x SQRT(Paving Area) * 1.2
Keywords: BCIVCONTAINMNT BCIVABVGR TANK external civil formwork
References: None |
Problem Statement: What is the best way to specify a Motor Operated Valve in the Icarus software? | Solution: In the Icarus software, to be able to specify a motor operated valve, the valve must be an ON/OFF valve.
The options Icarus has are:
ON/OFF Globe
ON/OFF Ball
ON/OFF Butterfly
*** Please note that the ON/OFF slide gate is one that does not apply. ***
If none of these on/off valves work for you, you will have to enter the gate valve as a quoted item.
HOWEVER, if one of the above does work for you, then you can follow these steps:
1. The valve is typically attached to a piping line. If it is not, then it is attached directly to the piece of equipment itself. You need to know which one it will be. If it?s on a piping line, then follow all directions below. If the valve is directly on the equipment item (the equipment item HAS to be a PLANT BULK PIPE item), skip steps a-c below.
2. The remote control type is always specified on the instrumentation loop....you must specify M for motor operated valve in the remote control type field.
3. A motor operator valve, the valve HAS to be an ON/OFF valve
Ex: API 610 pump
a. Open it up and go to OPTIONS ? Pipe Item Details.
b. You have to give it a piping line number, description, length and diameter. I chose to use piping line number 1, description of line 1, length = 10 ft, diameter = 2 inches.
c. Then click the APPLY button.
d. Go to Options ? Instrumentation.
e. Indicate Loop number, and description.
f. You must enter an instrument process variable and instrument sensor type.
g. Specify control valve location. This is the piping line number that you have put the control valve on. In this example, the piping line number is 1. OR, you can place the control valve directly on the piece of equipment (remember, PLANT BULK PIPE ITEM ONLY). If that is what you want to do, then specify 0 for the control valve location.
h. Specify the control valve type?of either GLO, BUO, or BVO.
Run the estimate and you will see your MTO (motor operated valve) located on the piping line number you specified, under Code of Account 681.
Keywords: valve, motor operated, on/off, on, off
References: None |
Problem Statement: I ran a test case to see the results of what Aspen Icarus calculates for an Area compared to what my Area definition specs are.
The Area:
Length: 506 feet
Width: 300 feet
After running the estimate, the Aspen Icarus cost engine calculated a Length of 425 feet and Width of 236 feet.
However, it looks like the default on the Distance to Motor Control Center is now changing to 100 FEET with the system calculated L and W is too short. Half the area length being 212.5 FEET would have been much closer.
I thought the calculation should be based on (L+W)/2 when they have a system calculated area L & W which would have been 330.5 FEET.
100 foot distance to the motor control center would not even cover the runs if it was in the middle of the unit. | Solution: Since area size is calculated after all equipments are processed, the Icarus software needs to assume the distance to MCC and the piping envelope length to calculate electrical and piping bulks for the components.
When area length and width are blank, the system default distance to the MCC is100 feet.
After the first estimate, you should go back and enter the system calculated length and width in each area spec to get the MCC distance and piping envelope length calculated from the specified area size.
You may enter your desired area sizes, distance to MCC etc. in the specs.
Keywords: system, calculated, area, motor control center, distance
References: None |
Problem Statement: I have a project in which there are around 550 lines at different sizes. All of them carry a 0.75 (20mm) weld-o-let (WO). How do I add fittings that have different diameters than the parent line? | Solution: Weldolets are always estimated for the same size as the line on which they are specified. For sockolets and threadolets we limit the size to 2 inch. If weldolets are smaller than line size then user should specify them on the branch line to which they belong. If the branch line is not being specified, then user can specify all weldolets of the same size on a stub line (i.e. a line with very small length and no other fittings except the weldolets). Weldolets vary greatly in size so a diameter can?t be assumed for the weldolets.
Keywords: Piping data, weldolets, fittings
References: None |
Problem Statement: What is the buried depth for pipe in pipe item details? I can see that in the main Above Ground or Buried Pipe form, that there is a field where you can specify the 'Depth buried pipe', but I don't see that field in the Pipe - Item Details.
Is the buried depth for pipe the same as the default or what is input on the main form? | Solution: Default information on the Depth of Buried pipe is located in the Icarus
Keywords: depth, buried, pipe, item details,
References: Manual, in the Piping Chapter, under Plant Bulks.
[Yard Pipe] Depth buried pipe:
Below grade depth to top of pipe for buried pipe only.
This is the distance from grade level to the top of the buried pipe. The trench depth is determined by the below grade depth, the pipe diameter and sand bed (6 INCHES [150 MM] in depth).
Range: 24 - 120 INCHES [600 - 3,000 MM].
The default value will be taken as 36 INCHES [1,000 MM] minimally, or the depth of footings specified for general civil data.
[Above Grade or Buried Pipe] Depth buried pipe:
Min: 24.0 INCHES [600.0 MM]; Max: 120 INCHES [3000.0 MM]. Below grade depth to top of pipe.
Default depth for Pipe item details:
Default depth = Max: 36.0 INCHES, depth FROST
At this time, there is no option for the user to change or override this default it in the pipe item details installation bulk. |
Problem Statement: What is the definition of the conversion factor in Units of Measure Customization? | Solution: Economic evaluation products have two unit systems available, I-P and Metric. User can customize some of the units in each system under Units of Measure Specifications window.
For example, if a user wants to change the input flowrate unit in I-P system from GPM (gallons per minute) to L/S (liters per second), he/she can highlight Velocity and Flowrate and click on the Modify button in the screenshot above. In the coming window below, first enter L/S as the new unit name, and then enter the conversion factor. The conversion factor in this window is defined as:
1 [original unit] = conversion factor [new unit], namely, 1 GPM = 0.063 L/S.
Keywords: Unit, conversion
References: None |
Problem Statement: When running a project evaluation, I get a FATAL error message and I cannot continue with running the project evaluation.
What does this FATAL error refer to, and how do I fix it? | Solution: This error appears in a Pipeline project and refers to an incorrect project component being added to the Pipeline Area. The incorrect project component typically selected would be the ?Above grade or buried piping? component. This component is not allowed in a pipeline area.
What is supposed to be selected was the ?Above grade or buried pipeline segment? which is located at the very bottom of the Plant Bulks ? Piping list:
Add this component, fill out the form, and the error will go away.
Keywords: pipeline, pipeline segment, BP - 1, sequence, incomplete
References: None |
Problem Statement: What does V/F mean within the insulation account? For instance:
PIPE INSULATION CASIL V/F 3.0 IN TH 3.00 IN DI 244 FEET 1895 0 0 | Solution: The V/F stands for Valves/Fittings. The insulation is for the valves and fittings are estimated in terms of equivalent length of pipe. If there are no valves and fittings, then this line will not appear.
Keywords: V/F, fittings, valves, pipe, insulation
References: None |
Problem Statement: What percent of Direct Field Labor (DFL) does Aspen Capital Cost Estimator use for Travel? | Solution: Travel can either be entered as a fixed number or as a percentage of DFL. If neither is entered, the default values are (according to country):
US 0%
UK 8%
EU 8%
JP 0%
ME 0%
Travel costs or percentages can be entered under:
Project Basis View | Contracts | Contractors | (contractor name) | Travel cost
or
Project Basis View | Contracts | Contractors | (contractor name) | Travel percent DFL (Direct Field Labor).
Keywords: travel, indirects, contracts, contractors, contract, direct field labor, DFL
References: None |
Problem Statement: What are the definitions of the symbols used in the barchart schedule in Aspen Capital Cost Estimator? | Solution: The default symbols used in the bar are listed below:
S: Start construction
M: mechanical completion
Q: quotes
P: purchase order
V: vendor data
D: delivering
T: Testing
*: Scheduling bar symbol
_: Scheduling gap
C: Critical Path
The last three symbols in the listed can be modified by user in Project Basis View | Project Execution Schedule Settings | Adjust Schedule and Barcharts form.
Keywords: Barchart schedule
References: None |
Problem Statement: How are the hourly rates ($/MH) determined for the indirects (fringe benefits, burdens, etc) in the Direct Average Wage Rate Build-up? | Solution: The hourly rates are taken by dividing the total cost for the indirect by the total Direct Field Cost Man-Hours (
TDMH). So if you had a project where the Total Direct Field Cost Manhours were 196,390:
and your project Fringe Benefits were $1,088,000:
Then your indirect Fringe Benefits hourly wage for the wage build-up would be:
$1,088,000 divided by 196,300 hours = $5.54
Keywords: Direct Average Wage Rate Build-up, Direct Average Wage, Rate Build-up, Build-up
References: None |
Problem Statement: I would like to be able to use the reports.mdb database that is created when I run estimates for my ICARUS software. However, when I open the reports.mdb file in Microsoft Access, it asks me for a password.
What is the password? | Solution: The password is: icarus. It is case-sensitive....so icarus needs to be in all lower case letters.
Keywords: icarus
database
access
reports.mdb
References: None |
Problem Statement: What is the relationship between the Distributed Load per Level PSF and equipment in an area of the design? | Solution: The weights of the equipment on the structure are added together, then it is spread equally over the structure. After that the Distributed Load per level PSF is added and the resulting value is used for the design.
Keywords: Distributed Load, PSF
References: None |
Problem Statement: How to setup different voltages coming from different sources? | Solution: Add as multiple Main Substations. Right click on the project and click on Add Main Substation to add multiple Main Substations.
Keywords: Voltage, Voltages, Substation, Substations, Source, Power, Electrical
References: None |
Problem Statement: New in V8.2 - Addition of structure tag field to quoted equipment form to allow weight to be allocated to structures | Solution: The structure tag field has been added to quoted equipment. This tag in the quoted equipment item works the same as the structure tag on equipment components. The quoted equipment weight is allocated to a structure when the quoted equipment COA is specified as an equipment COA, a valid structure tag for the structure is specified, and a quoted equipment weight is specified. You can assign the quoted equipment weight to Open Areas, Plant Bulk Open Structures, Bargeable Modules, Truckable Modules, and Skid Modules. See the Icarus
Keywords: quoted equipment, structure tag, structure, tag
References: Guide for additional information about adding equipment to structures. |
Problem Statement: Is it possible to install piping and double the random lengths generated by Icarus? This should cut welding in half. If yes How is it done? | Solution: Yes, you can do this by adjusting the number of welds.
Consider a 2 inch diameter pipe line that has a length of 150 feet and 1 elbow fitting. For the fitting, Icarus will generate 1 field shop weld and 1 weld in field. The fitting will take 10 feet of pipe. From the left over length of 150-10=140 feet Icarus will generate the welding using 20-30 feet random lengths. In this case it generates 5 welds which will be used on 6 pieces of pipe. There random length will be 140 divided by 6 or approximately 23 feet. So altogether the welding in the field is 5+1(for fitting)=6 and 1 that is field shop fabricated. Total welds of 7.
Now if you want to adjust the random length you have to manipulate the weld number. With the previous specification (length 150 feet, diameter 2 inches, 1 elbow) if you specify the number of welds it will adjust the random length accordingly. Let's consider the number of welds as 4 in the pipe. Two welds will go for the fitting (1weld in the field and 1 for in field fabrication). The fitting will take 10 feet of pipe length. The left over pipe length is 150-10=140 feet.We specified 4 welds, and two have been used, so there are two welds left for the remaining 140 feet of pipe. These two welds will weld three pieces of pipe together. The random length will be 140 divided by 3 or approximately 47 feet and the total number of welds will be 4 ( 1 in field shop fabrication, 2 in field welds to weld the 3 random lengths together, and 1 in field weld to weld the 10 foot piece with the elbow). In the ccp report we will see the item as below:
Keywords: Random length, welding, fittings, flanges.
References: None |
Problem Statement: How do I specify quantity for quoted equipment items in V7.3? | Solution: A new quantity field has been added to Quoted Cost item form which allows real number specifications. If quantity adjustment option is specified as 'Y' or unit of measure is ITEMS, then total material cost = Material cost per unit * Quantity * Number of identical items. A similar calculation is done for labor hours and weight.
? In the equipment results section of the .ccp report, Quantity will be displayed in place of Number of identical items. As before, Number of identical items will be displayed as ITEMS in the left most column. Previously for quoted bulk item material cost and COA are not displayed in this block. From V7.3 these two values will also be displayed:
? Due to this addition, there will be significant changes when an old project having quoted item is opened in V7.3:
1. For old projects containing quoted items with Quantity Adjustment = N and no installation bulks specified, the following will occur when migrated to V7.3:
Number of identical items value will be migrated to the new Quantity field and Number of identical items will be set to 1.
2. For old projects containing quoted items with the Quantity Adjustment = Y and no installation bulks specified, the following will occur when migrated to V7.3:
Number of identical items value will be migrated to the new Quantity field and Number of identical items will be set to 1.
3. For old projects containing quoted items with Quantity Adjustment = Y and any installation bulks specified, the following will occur when migrated to V7.3:
Number of identical items value will be migrated to the new Quantity field and Number of identical items will be set to ???. This will alert user to specify Number of identical items since under these conditions, the system cannot interpret the intent of the specifications. This will alert users interaction is necessary to complete the evaluation.
4. Similar behavior will be observed when importing specs file.
Note: When migrating old projects containing Quoted Cost items into EE V7.3, it is recommended users review the results for these items after the upgrade. The inclusion of Quoted Cost items into the spreadsheet view can facilitate this review.
Note: The Number of Identical items field will continue to work the same way in V7.3/7.3.1 as prior versions. Consider the following examples:
Quoted Cost Item Case 1:
Number of Identical Items = 4
Quantity = 2
UOM = ITEMS (default)
Quantity Adjustment Option = blank (default) or Y
Material Cost per Unit = 100
Labor hours per Unit = 20
Results:
Material Cost = 4*2*100 = 800
Labor Hours = 4*2*20 = 160
Installation Bulks (Material and Labor) = 4*Material Cost & 4*Labor Hours
The quantity field does not affect installation bulks material costs or labor hours regardless of whether Y or N is specified for the Quantity Adjustment Option.
Quoted Cost Item Case 2:
Number of Identical Items = 4
Quantity = 2
UOM = ITEMS (default)
Quantity Adjustment Option = N
Material Cost per Unit = 100
Labor hours per Unit = 20
Results:
Material Cost = 1*100 = 100
Labor Hours = 1*20 = 20
Installation Bulks (Material and Labor) = 1*Material Cost & 1*Labor Hours
When N is specified for the Quantity Adjustment Option, the system will interpret both the Number of Identical Items and Quantity Field as 1. This is consistent with the way the Number of Identical Items field has worked in prior versions.
Quoted Cost Item Case 3:
Number of Identical Items = 1
Quantity = 2
UOM = ITEMS (default)
Quantity Adjustment Option = blank or Y
Material Cost per Unit = 100
Labor hours per Unit = 20
Results:
Material Cost = 2*100 = 200
Labor Hours = 2*20 = 40
Installation Bulks (Material and Labor) = 1*Material Cost & 1*Labor Hours
Quantity field only affects the material cost and labor hours and has no effect on the installation bulks.
In V7.3/7.3.1, since the Number of Identical Items specification may be migrated to the new Quantity field, for quoted items where bulks are specified and the Quantity Adjustment = Y (or blank), users may need to respecify the Number of Identical Items Field (= to the migrated value in the Quantity Field) and re-set the Quantity Field = 1. This will ensure the Number of Identical Items is multiplied across the installation bulks and provides consistent results with prior versions. The new Quoted Cost Spreadsheet view can aid in respecifying such values.
Keywords: Quoted equipment, number of Identical Items, quantity
References: None |
Problem Statement: I had a problem with my Kbase file, and in order to get the project back into a working order, I modified my INPUTF file so that it became a specs file. However, when I re-imported it back into Kbase, all my P&IDs that I had attached to my components, were missing.
How do I get my customized P&IDs re-attached to their components? | Solution: Attached is the PIDfixer custom model executable so that customized PIDs will be reattached to a component that you run this custom task on.
Please follow these directions on how to add in the custom task to Kbase:
1. UNZIP the attached file and copy to a location on your hard drive. The unzipped file is called PIDFixer.exe.
2. Open Kbase, and go to TOOLS - OPTIONS - CUSTOM TASKS.
3. Click the ADD button to create the new custom task.
4. Call the custom task PID Fixer.
5. For the Item drop-down, select : PROJECT COMPONENT.
6. For the path, click the ... browse button to move to the path and PIDFixer.exe file where it was unzipped to the hard drive.
Running the custom task:
**BEFORE RUNNING THE CUSTOM TASK ON YOUR COMPONENT, MAKE SURE THAT ALL THE XML FILES HAVE BEEN COPIED FROM THE OLD PROJECT'S .SZP FILE TO THE CACHE FOLDER LOCATION.
In v2006.0 and earlier that location is: 'c:\Program Files\AspenTech\Aspen Icarus x.x\ic_cache\Projects\[PROJECT NAME]'.
In v2006.5 and later that location is: 'C:\Documents and Settings\[user_login_name]\Local Settings\Application Data\AspenTech\Aspen Icarus xx.x\Projects'.
1. Right-click on the project component that you wish to re-attach your P&ID, and select Custom Tasks, and choose PID Fixer.
2. This will run, and when complete, it will give you a confirmation message: Reattached PID.
3. Open the project component, and click on the PID button, it will then open your P&ID that was lost.
Keywords: custom task
P&ID
PID
task
custom
re-attach
reattach
specs
References: None |
Problem Statement: How do I adjust pipe hydrotesting in Aspen Economic Evaluation? | Solution: There is not an input field to enter to adjust the amount of hydrotesting for piping, but you can use indexing. If you check the default COA's there is not a specific COA for pipe hydrotesting, but there is COA 306 which is PIPE TESTING. Currently, the only pipe testing reported under COA 306 is the pipe hydrotesting ( X-ray and other testing end up in accounts according to the pipe metallurgy). So you can index COA 306 and it will actually be indexing your pipe hydrotesting.
Keywords: hydrotesting, hydro, testing, pipe, COA 306
References: None |
Problem Statement: I am getting an error with Steel Structures in my estimate. What do I do to fix this error message?:
Too many open STL structures (for hanging eqpt) in an area. Please create another area and move the structure into it. | Solution: Typically, this error message appears when there is only one area in the project. But, if there are too many components and too many Steel Structures, error messages like this are more likely to occur.
The bestSolution is to create another area and place that structure and equipment items into it. Just remember, it is not the AREA SIZE that is the problem here?the problem is that there are just too many Open Steel Structures in the one area with hanging equipment, and the software cannot handle it.
AnotherSolution would be to create another project and place those Open Steel Structures and their equipment items into the project.
Keywords: STL, structure, hang, hanging, eqpt, R - 1
References: None |
Problem Statement: Fatal error while evaluating unlinked Process Control Centers created in earlier versions of Aspen Capital Cost Estimator (ACCE).
For example,
FATAL – ‘PC 1' CONTRACT SET NUMBER INVALID | Solution: In previous versions of ACCE, the control center and operator center could be unlinked from a conset and the project evaluation could proceed without a FATAL error in the same version. However when the same project was later opened in a newer version, the engine generated a FATAL error for the unlinked control centers. In V8.0 ACCE has been updated to be consistent with the expected behavior; that the users get FATAL errors for unlinked operator center or control center in the same version.
Keywords: Fatal error, contractor, control center.
References: None |
Problem Statement: Some of the components in the project are showing two lines of cost reported as equipment cost. What is the second line and why is it reported as a material cost only? | Solution: The reason for the additional line is that the equipment may have coating that is selected to be done in shop. If you specify the coating to be done in the shop it will be reported under the same code of account of the piece of equipment (e.g. for horizontal vessels would be COA 114). Like any other shop costs, all the labor and material gets lumped together into a material cost, since this would be the cost paid to the vendor (that is, no labor is required from your project contractors).
If you change the option to coat the equipment in the field (by one of your Project contractors), the costs will be reported under a painting COA (e.g. 921 or 911) and the costs for labor and material are reported separately.
To change the painting between shop and field you need to go to to the Project Basis View > Paint Specs and select the corresponding option under Equipment primer/finish coat option
Keywords: brush cleaning spray coating
References: None |
Problem Statement: Where are the Aspen Icarus Reporter Templates for the v2006.5 installation?
Where should I be saving my previous customized report template files to instead? | Solution: In version 2006.5, we have changed the directory structure for file locations. Please seeSolution document 121905 for this new directory structure.
The new directory location for v2006.5 is:
C:\Documents and Settings\All Users\Documents\AspenTech\Shared Aspen Icarus 2006.5 Files\Reporter\Templates
You can also find this Reporter\Templates location by going to Tools - Options - Preferences - Location tab and see the location of the CustomReportdir.
Keywords: templates, folder, missing, changed, moved, change, location
References: None |
Problem Statement: In custom spec file, I have a spec with the material specified as A53. But, when I run the piping component with the spec selected, the report editor shows the material as A106 instead of A53. | Solution: This is because the system internally always used A106 for the small bore pipe and A 53 for larger bore pipe. They have the same stress values and the same cost. For other materials there is not this interchange so it will only show up on with A106/A53 split.
For small diameter (< 2 inch) the engine always uses seamless pipe (A106) whenever a carbon steel material is specified (CS or A 53). This happens without a custom pipe spec as well. E.g. if you specify an above grade or buried pipe, 1.5 inch diameter, 30 ft length and A 53 as pipe material: In the detailed bulks, A106 is reported as material but in the design data sheet, A 53 is reported.
The inverse is not true because for larger diameter we are not switching to A 53 when A106 is specified. A106 is applicable up to 48 inch diameter.
Keywords: Piping material, custom pipe spec, A106, A53
References: None |
Problem Statement: When I am entering equipment instrumentation as an Instrument Bulk Item (F:Flow, 2:Flow Transmitter) and assigned to a piping line number, the result gives more flanges than expected. What could be happening? | Solution: This often happens if you are using external INPARTS and INASSEMBLY files where flanges are specified for the instrumentation assemblies. If you remove these external files from the project basis you will get the right number of flanges (2 flanges generated by the system) as shown by the screen shot below.
After removing the external file the corrected report will appear similar to below:
Keywords: Flange, reporting, more flange.
References: None |
Problem Statement: How do I use the new Chinese template on an existing project? | Solution: To use one of the new Chinese templates (or any template for that matter) on an existing project, you need to first create a new, separate project using the template. Once the new project is created, you can then import the areas and components from the existing project into the new project.
Keywords: template, chinese, import
References: None |
Problem Statement: How to add orifice plates and flanges to plant bulk pipes and installation bulk pipes? | Solution: Prior to version V7.3.2, orifice plates and unions can only be added to an Above ground or buried yard pipe component. In V7.3.2, a new option is added to the Valve or fitting type dropdown list: ?OP: Orifice plate and union?. This is available for both plant bulk pipe and installation bulk pipe. When users select this option and specify the quantity in the adjoining field, the appropriate number of orifice plates and orifice unions will be estimated for that pipe.
Keywords: Orifice plate and union
References: None |
Problem Statement: You will get an error message referring to specified Indirect Codes of Account contained your External Indirects file if you have specified Indirect Codes of Accounts that are not defined and allocated with your Custom Code of Account file:
ERROR> 'EXT- 1' ERROR(S) IN INDIRECT.DAT, LINE X
CODE OF ACCOUNT XX IS NOT DEFINED FOR USER
The estimate will be unable to continue until these errors are fixed. | Solution: This error message is telling you to open your External Indirects file and look at the Codes of Account that you have specified.
Make notes of these Codes of Account and then check to see if you have these Codes of Account specified in your Custom Code of Account file.
If you have Indirect Codes of Accounts that are not specified in your Custom Code of Account file, then you must specify those Codes of Accounts in your Custom Code of Account file.
Or, this message will occur if you have not attached your appropriate Custom Codes of Account file to your project to work with the External Indirects file. Check your Project Basis - Codes of Accounts to see if you have a specifications file selected.
If you do not have your unique Codes of Accounts file selected, please do so, save the project, and re-run your estimate. Your error messages will go away.
Keywords: code of account, defined, defined for user, external, indirects, not defined
References: None |
Problem Statement: When I evaluate my project, I get an error message that says:
UpdateICSFromD0.exe - Application Error. The instruction at 0x78012476 referenced memory at 0x00000041. The memory could not be read. Click on OKto terminate the program. Click on CANCEL to debug the program. | Solution: Is there an odd symbol in the project name or item description names in this project?
The ICARUS software does not allow the use of the % sign or decimals in the Item Description names or Project names or scenario names. Our excel form cannot handle them (this relates to the UpdateIcsFromD0.exe error message, which writes your data into a spreadsheet).
Keywords: UpdateICSFromD0.exe
instruction
application error
memory could not be read
References: None |
Problem Statement: When I use the external Steel File and choose the galvanized finish option at either the project or area level, it does not appear to be using the steel price I entered in my Steel File. What is happening? | Solution: When you are using an external Steel File and you choose the galvanized finish option at either the project or area level, the system will use the price from the external Steel File as a basis and add a galvanized cost on top of the user specified cost. The cost addition depends upon the weight of steel items. For items > 40000lbs, in V7.2 we are adding 28.60 cents/lb and for weight less than 40000 lbs we are adding 42.9 cents/lb. (Note the cost addition will vary based on country base.)
We also increase the weight of the steel by 3-5% (based on what the steel item is).
Keywords:
References: None |
Problem Statement: How do I see my custom pipe specs in my exported Excel spreadsheet? | Solution: In V7.3.2 when a spreadsheet was created from Aspen Capital Cost Estimator (ACCE) using the spreadsheet export/import feature, the custom pipe specs drop down list was not available in the input fields in plant bulk and installation bulk pipe worksheets.
In V8 this has changed as follows:
A? When a custom pipe spec file is included in a project, the custom pipe spec symbols from this file will be available in the exported spreadsheets, thus allowing users to scroll-down and pick the desired custom pipe spec. If users manually enter the pipe spec symbol in Excel, it will be validated against the drop-down list. Thus an invalid entry will not be permitted (unless it is copied/pasted from elsewhere which eliminates the validation).
A? If no pipe spec file is included in a project, the exported spreadsheet will not have a drop-down list of custom pipe spec symbols and no validation will be made. This means the user can enter any pipe spec name in these fields.
Ultimately, if the correct pipe spec file is not attached to the project in which the spreadsheet will get imported or incorrect names are given, these will be flagged as usual when a project evaluation is performed.
Keywords: Custom Pipe Specs, drop-down, menu
References: None |
Problem Statement: How do I get the latest cost database to update my older Economic Evaluation product? | Solution: A common misconception about the Economic Evaluation products and the annual costing updates is that the updates are a database which the products access. The updates are actually tightly integrated with each release. They are not an external database, and cannot be supplied and used by another Economic Evaluation product release.
Keywords: cost database, cost, database, update
References: None |
Problem Statement: Is there a filter for the list view window? | Solution: The list view in the main window of Aspen Capital Cost Estimator, Aspen In-Plant Cost Estimator and Aspen Process Economic Analyzer displays details on items selected in project explorer. When the list is too long, a filter can be used to only display items satisfying the filter criteria, including ?All components, Process equipment, Plant bulks, Site development, Buildings, Quoted equipment, Library items and incomplete items. Such filter can be applied to the whole project, to a report group or to an area.
Keywords: List view, filtering mechanism
References: None |
Problem Statement: What is Drawing No. 75? Why can't I find it in the P&ID documentation? What data entered in the component will trigger the ICARUS Cost Engine to use Drawing No. 75? | Solution: The reason why a user would see Drawing number 75 in the output report is because the Aspen Icarus cost engine is also designing a TEWAC motor for that pump (the TEWAC motor is a totally enclosed water cooled motor.)
Drawing 75 includes 3 more pipe lines (inlet, outlet, and relief) which are used for the TEWAC motor.
Typically, Drawing 75 is triggered when the HP is over and above the standard HP.
Keywords: TEWAC, drawing 75, pump, motor
References: None |
Problem Statement: Where can I go to get pricing information if I am interested in buying an Aspentech product? | Solution: You can get pricing information in a couple of ways:
1. Call the AspenTech e-sales hotline at: 1-281-584-1945.
2. Fill out our on-line form at: http://www.aspentech.com/contact.cfm
3. Go to the Aspentech support web site at: http://support.aspentech.com/SupportPublic/centers.html
where we have information regarding the esales hotline, the on-line form, and our Support Center Hours & Phone Numbers.
Keywords: product pricing, sales
References: None |
Problem Statement: Can I see the number of identical items in the list view window? | Solution: In V7.3.2, a new column ?No. Items?, has been added to list view in the Project Basis View. This column shows the number of identical items of each component in the project. The default position is after ?Model? column and can be moved to any location or made invisible by changing the list view settings.
Keywords: List view
References: None |
Problem Statement: What are the Cost Indices for Q1 2014 ? | Solution: The Cost Indices for Q1 2014 are listed below:
Material
Construction
Engineering
Construction Management
USA
2250
2090
1500
1810
UK
3220
5190
5330
5070
EU
2360
1940
1950
1810
JAPAN
1640
1300
2080
1950
ME
2310
2540
1620
2080
Keywords: Cost Basis, 1st Quarter 2014
References: None |
Problem Statement: How do I add a user code of account? | Solution: Icarus has a default set of 3-digit Code of Accounts (COA) to which costs and man-hours are allocated. Aspen Capital Cost Estimator allows users add their own COAs:
? First select a COA file by right clicking Project Basis View | Basis for Capital Costs | Codes of Accounts, then Select.
? Right click on Codes of Accounts form again, then Edit. The Code of Accounts Dialog box appears.
Click Definitions, then Modify. The Code of account definition dialog box appears:
? Click on the Add button, a new item is added at the bottom of the grid. Enter the account number, select a COA group and enter a description.
? Repeat the above step for each new COA in the set.
Keywords: Code of account
References: None |
Problem Statement: How do I have welded valves installed in the remote shop? | Solution: By default, non-flanged, welded valves are installed in field. To have them installed in the remote shop, select ?Y? for ?Welded valves in remote shop? in Project basis view | Basis for capital costs | Design Basis | Piping Specs | General form:
This applies only to:
? pipe less than 2 inch (50 mm) NPS with SW (socket welded) connection type.
pipe with 2 inch (50 mm) or more NPS and WW (Weld pipe/weld valves) connection type.
Note:
When you set the Welded valves in remote shop field to Y and when the pipe diameter is in the remote shop pipe diameter range:
? Non-flanged valves are counted as fittings to determine the length of pipe that is sent to remote shop.
The number of welds in remote shop is increased to account for welding of the valves in the pipe spool. The number of field welds is decreased appropriately.
Valve erection man-hours are also accounted in the remote shop; line items for valve erection in the field are not generated.
For SC, SB, VC, VS and PF connection types, even when the pipe diameter is in remote shop diameter range, the pipe is fabricated in the field. So these connection types are not affected by the Welded valves in remote shop field.
Keywords: Welded valves
References: None |
Problem Statement: Why does the Change command not give me the number of safety valves I enter on my 10 inch line? | Solution: Aspen Capital Cost Estimator sizes safety valves up to 8 inches. If your diameter is greater than 8 inches, it will calculate the equivalent number of 8 inch safety valves for each safety valve. When you apply a the Change command, and your pipe diameter is greater than 8 inches, it will multiply the Changed safety valve number by the equivalent 8 inch safety valves. For lines 8 inches and under, the Change will be taken as given and not multiplied.
Keywords: None
References: None |
Problem Statement: If I enter my contingency both on the Standard Basis form and the Contractor Definition form, which will be used? | Solution: In Aspen Capital Cost Estimator,there are two places where contingency can be set. The first is in the Project Basis View | Contingency and Misc. Project Costs:
The second place is in the Project Basis View for a Contractor. For the contractor, you can specify contingency for Engineering, Material, and Construction. If contingency is set for a contractor, this contingency will be used instead of the Contingency and Misc. Project Costs.
Keywords: contingency, Standard Basis, Contractor Definition, Contractor
References: None |
Problem Statement: Why I am getting the warning message SUBSTATION REFERENCE NUMBER NOT SPECIFIED during project evaluation? | Solution: Ensure the area is linked to Substation by following the steps below
Double click on: Project Basis View | Systems | Power Distribution
Click the + in the middle of the screen next to the Project icon
Highlight and use a right mouse button on a Unit Substation and choose Link Area
Add areas that appear to the Unit Substation
Evaluate your project again the warning should not appear.
Keywords: Unit, Substation,
References: , Power, Distribution, Specified, Evaluation |
Problem Statement: Do the Economic Evaluation V8.0 products support Microsoft Office 2013? | Solution: The Economic Evaluation products do not support the use of Microsoft Office 2013. Office 2010 is the newest release that is supported.
Keywords: Office 2013, Office, 2013
References: None |
Problem Statement: How do I use the new Chinese template on an existing project? | Solution: To use one of the new Chinese templates (or any template for that matter) on an existing project, you need to first create a new, separate project using the template. Once the new project is created, you can then import the areas and components from the existing project into the new project.
Keywords: template, chinese, import
References: None |
Problem Statement: How to add orifice plates and flanges to plant bulk pipes and installation bulk pipes? | Solution: Prior to version V7.3.2, orifice plates and unions can only be added to an Above ground or buried yard pipe component. In V7.3.2, a new option is added to the Valve or fitting type dropdown list: ?OP: Orifice plate and union?. This is available for both plant bulk pipe and installation bulk pipe. When users select this option and specify the quantity in the adjoining field, the appropriate number of orifice plates and orifice unions will be estimated for that pipe.
Keywords: Orifice plate and union
References: None |
Problem Statement: You will get an error message referring to specified Indirect Codes of Account contained your External Indirects file if you have specified Indirect Codes of Accounts that are not defined and allocated with your Custom Code of Account file:
ERROR> 'EXT- 1' ERROR(S) IN INDIRECT.DAT, LINE X
CODE OF ACCOUNT XX IS NOT DEFINED FOR USER
The estimate will be unable to continue until these errors are fixed. | Solution: This error message is telling you to open your External Indirects file and look at the Codes of Account that you have specified.
Make notes of these Codes of Account and then check to see if you have these Codes of Account specified in your Custom Code of Account file.
If you have Indirect Codes of Accounts that are not specified in your Custom Code of Account file, then you must specify those Codes of Accounts in your Custom Code of Account file.
Or, this message will occur if you have not attached your appropriate Custom Codes of Account file to your project to work with the External Indirects file. Check your Project Basis - Codes of Accounts to see if you have a specifications file selected.
If you do not have your unique Codes of Accounts file selected, please do so, save the project, and re-run your estimate. Your error messages will go away.
Keywords: code of account, defined, defined for user, external, indirects, not defined
References: None |
Problem Statement: When I evaluate my project, I get an error message that says:
UpdateICSFromD0.exe - Application Error. The instruction at 0x78012476 referenced memory at 0x00000041. The memory could not be read. Click on OKto terminate the program. Click on CANCEL to debug the program. | Solution: Is there an odd symbol in the project name or item description names in this project?
The ICARUS software does not allow the use of the % sign or decimals in the Item Description names or Project names or scenario names. Our excel form cannot handle them (this relates to the UpdateIcsFromD0.exe error message, which writes your data into a spreadsheet).
Keywords: UpdateICSFromD0.exe
instruction
application error
memory could not be read
References: None |
Problem Statement: When importing a spreadsheet, I get a message to check the error/exceptions tab. The Exceptions message shows a??Object reference not set to an instance of an objecta??.A What should I do? | Solution: The errors encountered when importing a spreadsheet should be repaired in the spreadsheet. The input fields in the spreadsheet will not be validated with drop-down lists. What this means is that the user could type anything in the cell that contains the drop-down list, spreadsheet will not check whether the name or label is valid or not. If the name is not valid, user will encounter exceptions/errors.
If you see below exceptions/errors, please check the area name under Parent Area in every equipment page.
The a??Parent Areaa?? name should be exactly the same as the a??Area Titlea?? in the AREAS page. If the name does not match, import spreadsheet will fail. Using the drop down button will avoid spelling or naming mistake.
A A A A A A A A
Keywords: Import spreadsheet failed, exceptions/errors
References: None |
Problem Statement: There are default values under the head line LINE SIZING MODEL. Some values have no unit or label. What does these values stand for, how do they influence the results? | Solution: The documentation that's applicable here is Icarus
Keywords: Line, sizing , equation
References: - Chapter 19 - Standard Equations for Pipe Diameter(New) (page 19-45. V7,1)
The particular equation applicable here for Max. velocity exponent - liquid is:
(In the 2nd table)
Liquid Lines - Vmax = 100 / P1^0.5
The 0.5 in the documentation is the Max. velocity exponent - liquid parameter that can be adjusted
So the document might be more clearly stated as
Parameters:
Vmax = Maximum allowable velocity - liquid(FT/S)
A = Maximum velocity multiplier - liquid(FT/S) Default = 100
B = Maximum velocity exponent - liquid Default = 0.5
Pl = Pressure - liquid(Psia)
Vmax = A/Pl^B |
Problem Statement: By trying to open a project created with Aspen Capital Cost Estimator on an earlier version, an error message appears, e.g., | Solution: This action is not supported and we do not recommend users doing this. There could be many changes in later releases making backward compatibility impossible. The recommendation is to upgrade the Aspen Capital Cost Estimator application to the latest release.
Keywords: Aspen Capital Cost Estimator
backwards compatibility
upgrade
References: None |
Problem Statement: Does Economic Evaluator contain killed carbon steel ? | Solution: It depends upon the application. For example, our plate material, A515, A516, A517, and A299 are all killed carbon steels according to the ASTM specs. But if you use the generic CS on the input form for a plate material, the system will default to A285C, which is not a killed carbon steel.
For piping, if you choose CS on the input form, it will be a killed carbon steel. For piping, CS will either be A53 or A106. Both are killed carbon steel because the material spec that applies to them is A516 grade B (which is a killed carbon steel).
Keywords:
References: None |
Problem Statement: Whenever I try to run an item evaluation or project level evaluation, I get this error message:
ERROR:
EXT - 1 ALL INSSPC.DAT TEMP TABLES ARE BLANK
What is causing this error message, and how do I fix it so that I can run my estimate without errors? | Solution: This is usually caused by the user selecting the BLANK Customer External Insulation Thicknesses and Rules file called INSSPC_BLANK.
This called INSSPC_BLANK file should not be used as a working file for projects. It is a blank file for customers to make a copy of and save as a new file name. Then, they are to populate the new file with the data that is desired.
Directions for how to use the External Insulation Thicknesses and Rules file can be found by opening up the file using Notepad or another true editor.
(The External Insulation Thicknesses and Rules files are located in either the 'c:\Program Files\AspenTech\Aspen Icarus 2006\Data\Insulation' folder for v2006, or in the 'c:\Documents and Settings\All Users\Documents\AspenTech\Shared Aspen Icarus 2006.5 Files\Insulation' folder for v2006.5.)
To resolve this error message, right-click on the External Insulation Thicknesses and Rules selection in the Project Basis, and choose remove selection.
Now when an estimate is performed, there will no longer be an error message.
Keywords: INSSPC.DAT, blank, tables, temp, EXT - 1
References: None |
Problem Statement: Using quoted cost on control valves with MOV option sometimes does not use quoted cost; why? | Solution: This is probably due to using a control valve like STD; It is only appliable to OPEN/CLOSE type control valves and you need to use an OPEN/CLOSE type control valve (ie BVO, BUO, GLO, etc.).
Keywords: None
References: None |
Problem Statement: How do I get handrails on my pipe rack? There is no field for handrails. | Solution: Handrails in the Pipe Rack model are generated when you tell it the number of catwalks. The default value for catwalks is none, but once you tell the system to generate a catwalk it will generate the handrails to go with it.
Keywords: handrail, pipe rack
References: None |
Problem Statement: After using the relocation option in Decision Analyzer the concrete pricing that I had entered for types B, C and D only changed for type B, but not for types C and D. Why did it only change for Type B and not for Types C and D? | Solution: Changing only the pricing for Type B Concrete after relocation is correct.
There is pricing for Type B concrete for all the different locations. However, there is no Type C or D pricing for any locations and we use internal estimates for % differences between the different types to calculate values for C & D. This is why the C & D types do not see a change in pricing after relocation.
What the you need to do after relocation, is to remove the concrete type C and D values (the B value will change automatically with the relocation) since they will no longer be valid (after relocation) and have the concrete type C and D pricing based on the internal calculation off of the new B pricing. You can always adjust any of the values.
Keywords: concrete, type, relocation, Decision Analyzer,
References: None |
Problem Statement: What are the permissions required for the installation and running of the Aspen Icarus v2006.5 software? | Solution: Administrator privileges are required to install the Aspen Icarus 2006.5 software.
With the release of v2006.5, it is no longer required that the end user of the software have Administrator rights to run the software.
However, it is required that in order for the software to run properly, the end user's login (i.e. domain login: CORPDOMAIN\userlogin), must be included in the Local Group Account called 'Users' on the laptop or desktop computer.
This is because for the ?C:\Documents and Settings\All Users\Documents\AspenTech\Shared Aspen Icarus 2006.5 Files? folder, the Local Group permissions are: SYSTEM and Users.
If the end user tries to run the software and they are not part of the 'Users' group on the local desktop or laptop computer, then the Please wait while Aspen Icarus configures....
Contact your System Administrator if you believe that your domain login is not part of your computer's local 'Users' group, so that it can be added.
Keywords: configures, configure, wait, permissions, privileges
References: None |
Problem Statement: To install some of the Icarus emergency patches, I need to locate certain folders such as C:\Documents and Settings\All Users\Application Data, and etc. But for some reason, I could not find such folder in my computer. | Solution: Some of the folders mentioned in the emergency patches are hidden folders by default. To make the hidden folders visible, open windows explorer, go to Tools | Folder Options | View, and check ?Show hidden files and folders? option.
Keywords: Folders, hidden
References: None |
Problem Statement: When specifying a reducer in the Aspen Icarus software, what size is it reduced down to? | Solution: When specifying a reducer, the reducer will be the line diameter on one end and a 1 inch diameter reduction in size on the other end.
But, as you get up into the larger pipe diameter sizes, we will end up reducing down to the next standard pipe size (ex: 24 pipe reduces down to 20).
See the Aspen Icarus
Keywords: reducer, pipe, reduced, fitting, diameter
References: Manual, Chapter 18 - Pipe Diameters, for the pipe sizes. |
Problem Statement: Why do Aspen Capital Cost Estimator version 2006.5 and V7.1 give different results in paint (COA 912 and 922) for small diameter pipes? | Solution: The difference is caused by the change made in V7.1 CP1 to make the model more rigorous with respect to the fact that small diameter pipes have a much higher overspray rate. The consensus is that it takes as many hours and quantity to apply paint to any line less than 3 inch diameter as it does to apply to a 3 inch diameter pipe. So for the purpose of calculating paint quantity and hours, a pseudo diameter of 3 inches is used for pipes with diameters less than 3 inches in the paint routines since V7.1 CP1. As a result, V7.1 will give higher paint quantity and hours than older versions, such as 2006.5 for small diameter pipes.
Keywords: Paint, quantity, hours
References: None |
Problem Statement: Aspen Capital Cost Estimator is generating some pipe lines I would like to remove; is there an easy way to remove them from my estimate? | Solution: Aspen Capital Cost Estimator (ACCE) and Aspen Process Economic Analyzer automatically generate piping with the various equipment in a project. You can adjust this piping, add piping, or remove (delete) piping. To delete a pipe line you do not want as part of your estimate, do the following:
1.) Go to the Component you would like to delete the pipe line from and open that Component.
2.) In the OPTIONS drop down menu, choose Pipe - Item Details.
3.) In thePiping Volumetric Model field, enter a D, in the line number, enter the line you wish to delete, and in the description field, enter a short description
4.) Hit APPLY and the do an Evaluation. The line will no longer be included in the estimate.
Keywords: pipe, delete, remove
References: None |
Problem Statement: We have created a pipeline project in Aspen Capital Cost Estimator. If we use option ?M? for Suppress default equipment/area/project bulks in General Project Data form in Project Basis View, we will get a fatal error when evaluating the project. | Solution: By selecting ?M? option, it emulates Aspen In-Plant Cost Estimator (AICE) in Aspen Capital Cost Estimator (ACCE), because AICE does not generate bulk automatically. But pipelines are not available in AICE, thus you get a fatal error when using M option in ACCE with a pipeline project.
Keywords: Bulks, pipeline project
References: None |
Problem Statement: While trying to generate an Excel report, using the Interactive Reporter, I get the following error message:
Aspen Icarus Reporter- Excel Report Error
Error #9 Subscript out of range | Solution: When using the Interactive Reporter, Item Summary by Contractor or Installation Details by Contractor, the Excel report fails to load and generates the error message: Error #9 Subscript out of range.This error will occur if you are trying to use older ProjectTemplates.xlsx file with EEV8.4 or later version.
In EEV8.4, two new Excel reports were included, 1- Item Summaries by Contractor and 2-Installation Details Combined (By Contractor)
These can be found at 'Full Import | Capital Cost Reports | Direct Costs | Item Summaries | By Contractor’
and at 'Full Import | Capital Cost Reports | Direct Costs | Installation Details | Combined (By Contractor)’
In EE V8.8, ten new Excel reports were added to the Interactive Reporter. The Module Summary by Contractor report was added to the Direct Costs section and provides summarized costs and shipping weights for modules. New Engineering by Contractor reports have been added to the Indirect Costs section and include the following:
a. Basic Engineering
b. Detail Engineering
c. Home Office Construction Services
d. Field Office Construction Supervision
e. Construction Management
f. Plant Startup
g. Basic Engineering Drawings
h. Detail Engineering Drawings
i. Procurement
Additionally, a new Excel report, Direct Cost Metrics, was added. In the Aspen Icarus Reporter GUI, this report can be found at the Full Import | Other Reports | Project | Direct Cost Metrics tree view location:
If you have customized reports, the customized ProjectTemplates.xlsx file from earlier versions will be missing these two templates. You can import the these tabs from the new version into your customized template (in the same order). In other words, you can add extra tabs and copy paste those report types into your template.
These templates are located at- C:\Users\Public\Documents\AspenTech\Shared Economic Evaluation V8.x\Reporter\Templates
Keywords: Error 9, Icarus reporter, contractor
References: None |
Problem Statement: How to link a primary control system to an area. | Solution: The primary control systems are linked through the Project Basis View. Go to Process Control and highlight the control system you want to have associated with an area:
Then click the right mouse button and choose ?Link Area?. You will then have a list of all the areas that have not been linked to a primary control system. Highlight the area (or use the shift key to highlight multiple areas if you like) you want linked (associated) to that control system:
Then click OK. That will link the chosen area(s) to that control system as the primary control system for the area.
Keywords: Process, Control, area, link
References: None |
Problem Statement: Can selection of reports in ICARUS Reporter (Aspen Capital Cost Estimator, Aspen In-Plant Cost Estimator, and Aspen Process Economic Analyzer) be remembered so that I don't have to repeat the same selection each time I run the reports? | Solution: The Reporter allows users to select and run multiple Standard reports or Excel reports. These selections can be retained for future use by clicking the Remember Selections button in Aspen ICARUS Reporter window. When Remember Selections is utilized, the selections are retained and shown the next time the Reporter application is run. In V7.3, the Reporter will retain the selections in both the product as well as the project. These selections are displayed until the user chooses to do otherwise.
The selection can be remembered product wise, namely the Reporter can retain the selections made for each of the 3 products separately (Aspen Capital Cost Estimator, Aspen In-Plant Cost Estimator, and Aspen Process Economic Analyzer). In addition, when the Reporter application is run on a newly created project, the last remembered selections (if defined) for that product type, will be shown by default. Similarly, for an existing unsaved project, the last remembered selections (if any), for that product type will be shown by default.
Selection can also be remembered project wise in V7.3. The selections will be saved permanently when the project is saved. When the Reporter is invoked on such a saved project, the retained selections will be displayed.
Keywords: Reporter, remember selection
References: None |
Problem Statement: Why do I get the error Microsoft Visual Basic for Applications Can't Find Project or Library. Problems with Aspen ICARUS Reporter Assistance when exporting an Excel file from Aspen ICARUS Reporter? | Solution: This appears to be an Excel type library issue. If this issue appears when running the Excel reports and the Standard Reports, then try re-registering Microsoft Office. Close all Office applications prior to doing this, including Outlook, Powerpoint, etc. and ensure no office processes are running from the task manager.
The steps for re-registering Office are:
1. Open C:\Windows\System32 directory from Windows Explorer and then run cmd.exe (Command Prompt) as administrator (right mouse click on cmd.exe and select Run As and select Administrator).
2. Type following at the Command Prompt
For Windows XP:
C:\Program Files\Microsoft Office\Office14\Winword.exe /r
For Windows 7-64 bit with MS Office 2010 (32 bit)
C:\Program Files (x86)\Microsoft Office\Office14\Winword.exe /r
Keywords: Aspen ICARUS Reporter, MS Office, standard reports, Excel reports
References: None |
Problem Statement: What are the equipment footprint and coordinate parameters in equipment input forms? | Solution: These parameters are related to plot plan layout tools, which can be enabled by changing the option for Print Equipment Coordinates to Y, under Project Basis | Basis for Capital Costs | Design Basis | Equipment Specs. The typical workflow for using plot plan layout tools is:
Run project evaluation in Aspen Capital Cost Estimator and export data to Aspen Basic Engineering, such as area dimensions, equipment footprint dimensions, and dimensions of exclusion zone around equipment.
In Aspen Basic Engineering, the new Layout drawing type is accessed in the Drawing Editor application. Certain modifications can be done in the layout, such as changing area dimensions/locations and equipment locations. Equipment footprint size and safety dimensions cannot be graphically modified in the plot plan. These values (either calculated or input by the user) are set in Aspen Capital Cost Estimator. Only equipment coordinates (used to calculate spatial relationships) are modified within the layout.
Import the data back to Aspen Capital Cost Estimator. Area dimensions, locations and equipment locations from the user generated plot plan are imported into Aspen Capital Cost Estimator. Area coordinates (bottom left corner X, Y) with respect to Plot Plan datum (0,0 coordinate of Plot Plan) and equipment coordinates (X, Y, Z) with respect to parent area coordinates (bottom left corner) will be passed to Aspen Capital Cost Estimator interface. Area sizes will be passed to Aspen Capital Cost Estimator from Aspen Basic Engineering
Keywords: Equipment footprint, coordinate
References: None |
Problem Statement: For a vessel, when entering Vacuum Design Gauge Pressure would you enter that as -14.7 psig or 14.7 psig? In otherwords, is a minus (-) sign required? | Solution: To input 'vacuum design gauge pressure', you can input either of the values, -14.7 psig or 14.7 psig. Economic Evaluator understands it is 14.7 psig from external pressure. You can see same result of -14.7 psig and 14.7 psig. Generally, users input negative values.
Economic Evaluator calculates thickness based on ASME Vacuum Design Procedure.
. To design according to vacuum the system first determines if the calculated pressure thickness meets vacuum requirements. If yes, vacuum design is complete, if no,
. It adds stiffener rings spaced one-half (.5) the diameter of the vessel apart. (This spacing can be changed in the vessel input specs.)
. If vacuum requirements are still not met, the system adds to the wall thickness until vacuum requirements are met.
. This design results in a uniform thickness reported in design results as base shell thickness.
. Any negative number in vacuum design yields full vacuum design.
Sometimes Economic Evaluator thickness results are thinner than other software results. Please check stiffener rings specification.
Economic Evaluator adds stiffener rings automatically. You can see stiffening ring spacing on evaluation form. If there is no stiffening ring for a design, zero is there. You can input zero in vessel input form if you don't want to specify stiffening ring.
Keywords: vacuum design, pressure.
References: None |
Problem Statement: The fitting rule file cannot be found in the location referenced in | Solution: 110768 and in Chapter 18 of the reference guide. Have the names of the files changed or their location?Solution
The fitting rule file is no longer named FITSPC.dat, but FTRULEIP.dat or FTRULMET.dat (depending on the units).To make modifications to these files, follow the next procedure:
1. Go to C:\Documents and Settings\All Users\Documents\AspenTech\Shared Economic Evaluation VX.X\Fittings and there you will see 2 folders depending in the units system that you work on, IP or Metric. X.X is your Economic Evaluation suite version.
2. Within those folders there is a .dat file (FTRULEIP.dat or FTRULMET.dat depending on the units). Make a copy of this file in this folder and rename it.
3. Open the newly created .dat file in Notepad and make any modifications. The file itself contains some instructions on how to do this, but basically you need to change the information in the table by the end of the file. Save the changes.
4. Go up one folder and there should be a file named PIPEDATA.set. Open it in Notepad and add a new line specifying the units and the new file's name, E.g.,
SAMPLE FITTINGS RULE I-P MODIFY.DAT
Save the changes.
5. Open the project with ACCE. Go to the Project Basis View tab > Customer External files and right-click on Fittings. Click on Select and choose the newly created Fitting rule file.
6. Now go to the pipe component and select the Piping routing, Fitting and valve rules application as Y to apply the changes.
Keywords: Fitting library pipe piping
References: None |
Problem Statement: Is there a way to get my newly exported spreadsheet from Aspen Capital Cost Estimator to automatically open after I create it? | Solution: Starting with V8, there is a new check box option in the spreadsheet import/export GUI which will automatically open the exported spreadsheet after the spreadsheet is created. The option is enabled by default.
Keywords: excel, export, import
References: None |
Problem Statement: What is primary and secondary equipment tag? | Solution: Example 1 shows a preliminary layout for a storage area with two tanks and a centrifugal pump to transfer fluid from tank 1 to tank 2. Pipeline 1 and 2 are connected as the inlet and discharge lines for pump, CP104.
In ACCE, the pipeline added is not connected to the equipment by default. To connect the pipelines to the equipment, primary and secondary tags are used as reference.
The primary equipment tag for PIP102 is VT101 while the secondary tag is CP104. The location of the pipeline connected to the equipment can also be provided in the primary/secondary equipment connection field(s).
Keywords: Primary equipment tag, secondary equipment tag, connection, pipeline.
References: None |
Problem Statement: There is an FRP storage vessel in Aspen Capital Cost Estimator but no FRP process vessel: how can I estimate an FRP process vessel? | Solution: For estimation, the main difference will be in the piping and instrumentation for an FRP process vessel will be different than the FRP storage vessel. You can use the FRP storage vessel and then add the piping and instrumentation needed to give you a better estimate for an FRP process vessel.
Keywords: None
References: None |
Subsets and Splits
No community queries yet
The top public SQL queries from the community will appear here once available.